Alternative UOM.

Hi,
I need to display Order unit, if it is blank I need to display UOM with the key figure.
Presently Iu2019ve added new field in the report and displaying the Order unit/UOM.
Presently i am displaying as below:
UOM (Order Unit / UOM)     Qty
PC                            10
EA                            20
But my requirement is to display it as
QTY
10 PC
20 EA
When I use nodim itu2019s automatically picking UOM, I cont change the values of cube because its used in different report so please help me how to achieve this.
Regards,
Vikram

You can display the unit which is associated with the Qty. To acheived what you need you should create a Qty KF with Unit as POU and populate it accordingly (i.e. fill it with Base UoM if POU is blank). Then use it in the query.
Regards,
Gaurav

Similar Messages

  • Report for material and alternative UOM

    Hi Guru's
    is there ant transaction/standard report where i can see the list of materials and alternative UOM
    Thankyou

    Hi,
    No such standard report available in SAP to see for many materials. in MM03 under Additional Data, you can see but material wise.
    Better use table MARM to see the same and create an ABAP Query of Report using this table.

  • Stock report in alternative UoM

    Hi we are maintaining the stock of our FG in PCs as a base UoM . But our sales and distribution dept needs a sotck in alternative UoMs also
    Eg 10 Pc = 1 Box , and 120 Box = 1 Case likewise
    They needs the stock in Boxes and cases also
    I have maintained conversion in Material Master , but I do not find any report which shows me these alternative UoMs
    Please tell me is there any such report available

    Hi Bhushan,
    You will have to go in for Z report. In MB51 you can see only by movement type & also Unit of Entry & Base UoM.
    In MMBE per material, you can change the UoM & see the stocks, but this will be material by material & not for a range of materials.
    Read the data from MARD, MARM tables & also if you're maintaining special stocks, refer to MSPR, MCHB etc.
    Hope the above helps.
    Regards,
    Vivek

  • Mass deletion of alternative UOM conversion

    Hi Colleagues,
    Does anybody knows is there an easy way for mass-deletion of alternative unit of measure conversion rules in material master?
    Thanks,
    Artashes

    I did the following way:
    1. created a recording which always deletes the second line in Additional data-> uom conversions.
    2. by multiply running this recording via lsmw will delete all uoms.
    3. I was not able to do it at once as different materials has different numbers of alternative uom entered.
    Thanks,
    question closed.

  • Alternative UOM in product overview(/n/sapapo/pov1)

    Hi,
    In the product overview,we can see the product quantities in base UOM. our requirement is,we have to see Alternative UOM.
    How to get this?
    Thanks & Regards
    Akthar

    Dear Akthar,
    you can define in /sapapo/mat1on ATB tab a "Display Unit". Here you can choose your alternative UOM and then while displaying the quantites your Alternative UOM will be used.
    On PP/DS area if you want to use a particular unit of measure for certain products that is different to the base unit of measure, you must have maintained a production unit in the product master. Choose Master Data -> Product. You can maintain a production unit on the PP/DS tab page in the Units of Measure group frame.
    For further help please read following link:
    http://help.sap.com/saphelp_scm2007/helpdata/en/8f/5b507e5c91e748acbe37cc185a34ef/content.htm
    Regards,
    TIbor

  • Planing in COPA in alternative UoM

    Hi all,
    a question : Is it possible to plan in COPA in alternative UoM.The stock keeping unit is EA, but unfortunately the planning department wants to plan in KG. Conversion between the UoM's  is maintained in Material master.The project itself is a roll-out and COPA is pre-configured. There is 2 value fields in the operating concern that can store the data for volume in those two UoM
    Also I saw in TC KEDR , that a step" Clear " is customized to clear all the postings in the value field where KG volumes are posted.From conditions there i remove the our company code, but w/o any success. Whatever I have posted to the KG value field without any conversion is moved / reposted in value field for EA.
    Can you help me with this.
    Thank you for your time.

    Hi Maria
    In my opinion, you should not remove the entry of your company code from KEDR
    In the conditions, you should put condition as "BUKRS <> XXXX", where XXXX = your company code... This means, the derivation step will run only if the company code is Not Equal to Your company code
    Regards
    Ajay M

  • Why should we turn off query cache when alternative UOM solution is used?

    Hi, all, Why should we turn off query cache when alternative UOM solution is used?I found it in "Checklist for Query Performance", but I dont know why.
    Please tell me if u know.
    PS: I also dont know how to turn off the cache, Need your help, thanks!

    hi ,
           I have also some confusion regarding Cache Parameters . What is the importance of cache ,  Should we delete the cache memory time to time for each query ? I have chked it in RSRT but never use the chache monitor function .

  • Using Alternative UOM in transaction VA21

    We want to use alternative UOM for Hydrocarbon Product during creation of a quotation using transaction VA21 and document type QT so that user can change the Alternative UOM say in KG or L15 or change the temperature and density of the material.
    Grateful if anyone provides a solution.

    Hi!
    Please solve:
    In Material Master for material HSD02, Base UOM is L15 and Sales Unit is KL.
    Earlier in Additional Data, 1 KL <= 1000 L15 is stored.
    Now I want to chage the conversion factor as 1 KL <= 987.9 L15 or 10 KL <= 9879 L15.
    Hence I wanted to delete the earlier entry with 1 KL <= 1000 L15  and tried to maintain 10 KL <= 9879 L15.
    This is not allowed. On saving the change again earlier entry 1 KL <= 1000 L15 appears in Additional Data -> Unit of Measure.
    Thanks in anticipation.
    Pranjal

  • Alternative UoM in HU monitor screen

    Hi Expert,
    I have a problem regarding the Alternative UoM in Handling Unit monitor screen (HUMO).
    We use alternative UoM to manage the material in our plant. and all the material is in Handling Unit management. for example, 1bag = 13kg.  when we sale it in bag unit of measure.
    we can display  stock with different UoM with transaction LS26. but we can not display the material in UoM "bag" in HUMO transaction.
    SO the sale people need to calculate it manually and convert them to bag since we use HU manage it.
    Do anyone have the same situation?
    Thanks
    Rocky

    It is not possible to view alternate UOM in HUMO,another option to see th HU stock in location MMBE by giving alternate UOM.
    For end user to see the stock alternative UOM then you need to write aABAP query to put some logic to show alternative UOM qty or develop a new report.

  • APO SNP Planning Book Show Product View alternative UoM

    Hi,
    I have a base UoM of BTL and an alternative UoM of CAS.
    I can change/save in my users settings the in transactions /SAPAPO/RRP3 (Product View) and /SAPAPO/SDP94 (Planning Book) to show the alternative UoM CAS as default.
    The problem I have is when I enter the Planning Book, load a product, right click on the product (in Selected Objects), select Show Product View and then look at the stock tab, this always shows as the base UoM BTL.  Can this be saved to show the alternative UoM CAS?

    Hi Linda,
    Try changing you user settings for a product in RRP3 Screen.
    Page Menu --> Settings -->General Tab -->General Panel -->enter AUOM value (CAS in your case).
    Note - The conversion only takes place for the products, for which the alternative unit of measure entered is also entered as the alternative unit of measure in the product master, or for the products, for which the base unit of measure has the same dimension as the alternative unit of measure.
    Caution: Test it , how its affecting for other products which doesnt have CAS as AUOM.
    All products which have BUOM as BTL will be changed to CAS when AUOM is maintained for them in product master.
    Thanks
    Vinoth

  • Rounding OF alternative UOM

    Dear All,
    I have maintained alternative UOM in material master which I am using in pricing procedure through info records.
    In the pricing if my value is coming 243000 I want to make it round off 25000.
    Tell me hw it is possible thr routine or thr some customisation.
    Regards
    GITESH

    Jeyakanthan A  ,
    Thanks for ur reply.
    I cant adust alternative UOM
    I should come round off Tell me can I use routin here for calculation of condition base vlue .
    regards
    Gitesh

  • Sample Quantity to be in alternative Uom

    Dear QM Gurus,
    We have a material which has basic uom as KG. We will be maintaining the alternative uom as PCS and conversion factor as 1KG = 1330 PCS in Material master. Now we want sample quantity in the inspection lot to be created in alternative uom instead of basic uom. Already we maintained PCS in inspection plan header level & MIC. But still the sample quantity is coming in KG.
    Kindly guide me to solve this issue.

    Refer
    Sample size to maintain in gram when base qty in Tons

  • UOM and Alternative UOM

    Hi All,
      Please clarify this, is the UOM is based on Material type if it is then we have to find UOM and alternative UOM based on material type.
    Regards,
    Babu

    UOM is the base unit of measure which exists in Basic view of material. This is the least possible unit defined for a material. FOr example Piece PC or ST
    Alternative unit of measures are the other unit of measures used in different views of material master. Issue unit, order unit or Sales unit....We have to maintain the conversion of these Alternate UOM's and Uom's in MM01 or MM02. Material UOM's are stored in MARM table.
    Alternate UOM could be BAG or PAC or CS (case)...
    Conversions are like BAG = 10 PC where PC is the base unit of measure and BAG is the alternate unit of measure.
    -Kriss

  • Alternative UOM wrong quantity conversion

    While issuing the material qty 50 PCE its converts into 300.002 Kg, as it should be 300 Kg.
    The alternative UOM is maintained as, 1PCE = 6 Kg.

    Can you provide more details about where you issuing it. If possible upload screenshots n paste the link here of mtl master (Alt. UoM page), then stock keeping unit, the goods issue posting etc. to get a better understanding.

  • Advantage of Alternative UOM as supposed to changing the UOM of material

    Hi Friends,
    What are the advantages of using alternative unit of measure as supposed to changing the UOM of material? &
    what are the necessary activities in SAP if we change the unit of measure of the material?
    Any pointers.
    Regards
    Ashu
    Edited by: ashutosh p on Jan 14, 2010 6:29 AM

    When you want to handle the material quantity in other units other than it's Base Unit, then alternate unit should be maintained.
    Alternate unit is decided on the basis of area of it's usage.
    If A material is having base unit PC and you want to sale it in KG then mainain the Sale Unit as KG by providing the conversion between PC and KG.
    In the same way Order unit is the unit when you want to procure the material in the unit other than Base unit.
    For maintaining alternate unit, it's corresponding conversion with Base unit is necessary to maintain.
    You can change the base unit of material unless and untill no transactions are done on that material.

  • Material replication - alternative uom

    Hi,
    I have a material in the back end with alternative units of measures.
    When I replicate the material to SRM only the base uom is replicated.
    How can I replicate also the alternative ones ?
    Thanks !

    Hi. You can not see them in "Material > Other Units of measure" in transaction COMMPR01?
    You have maintained them on the material master in the backend, not in an info record or something?
    Regards,
    Dave.