Asset - WBS element-PO

Hi All,
I have created a wbs element. Assigned it in the Asset master.
Now, when I create an asset PO for the said asset, it is not populating the WBS element automatically.
Which other settings needs to be done other than giving the WBS element in the asset master.
Also, I need to assign a budget for the WBS element so that any PO created over and above this budget is not created.
Thanks,

Hi,
Actually, it should work the following way:you post your documents on WBS and then settle the costs to the asset. You can put the budget on the WBS and the document posted on it would be controlled budget-wise.
Regards,
Eli

Similar Messages

  • Settlement of WBS element down payments to an asset under constructions

    The down payment (of the transactions tcode F-47 and tcode F-110), are
    always settlement wbs element (tcode CJ88), we do not want to post down
    payments to the receiving asset under construction (transaction type
    180 or 181).
    In the down payments are always taken into account in the settlement to
    an asset. The settlement of the down payment is the actual reason for
    the previous update of down payments in FI (Transaction type group
    15). Furthermore, the settlement of down payments to assets should
    not be capitalize.

    When you search on this forum try to put Date range "ALL" to get more results. Please read below threads and you will get the solution.
    MIRO:Transaction in area 15 contradicts the net book value rule
    Transaction in area 01 contradicts the NBV
    Looks like you have a negative balance in your WBS which you are trying to settle to FA.

  • WBS element in Asset master & investment order

    hi,
    till now we are using the capital investment order for capitalising assets, but now the client is asking for settling wbs element on to auc, can we have both WBS elment and investment order for a single asset. does any one have img document for wbs element related config.

    Hi Sai,
    I think I can answer part of your question.  If a posting is being made to wbs element and internal order (both are real).  The real posting goes to wbs element and statistical posting goes to internal order.
    In this case, you will be settling the wbs element to the AUC rather than Internal Order.
    Coming to the configuration, most of the configuration settings are same on Internal Orders / WBS elements.
    I am sorry, I do not have any documentation.
    Regards,
    Sreeni

  • System is not picking up the WBS element from Asset in PO.

    Hi,
    While creating Purchase Order with account assignment category
    as "A"(i.e.Asset), system is not picking up the WBS element from Asset
    Master, even though it is defined in the asset master.
    Please help.
    Thanks,
    Ninad

    Hello Ninad,
    Please, see the SAP Note 21583. I think it might be of help for your case.
    Best regards,
    Esther.

  • Report: Statistical WBS elements with assets assigned to them - actual cost

    Hi all,
    I would like to run a report that gave me this info:
    WBS Element (all statistical)
    Assets assigned to each WBS
    Actual costs
    It would be perfect CJI3 but it doesn't show assets. In AM I haven't see either any report that shows WBS elements...
    any ideas???

    Hi
    There is not a standard report which can cater to your requirements. You need to develop one.
    You can take the refernece from CNS41 report for development. Some of the fields you need are PRPS-XSTAT for statistical WBS and will have to use tables ANLA and ANLC to fetch asset master data.
    Regards

  • WBS Element Populated on Asset GL Account Line Ledger 90

    Hello All,
    For preliminay settlement of a WBS element to an AuC asset, how do you get the WBS element to populate on the account line for the asset gl account in ledger 90?
    Currently, I'm working in R/3 4.7 and the WBS populates on both sides of the accounting document (on the asset line as well as the settlement line). We are upgrading to ECC6 and this does not work the same. The WBS element is blank on the asset line. I cannot remember how the R/3 4.7 system was configured in order for the asset line to mirror the WBS element on the settlement line. If I can understand how it works in R/3, then maybe I can get it to function the same in the upgrade.
    Any assistance would be greatly appreciated.
    Thanks.

    Hi
    When the WBS element is settled to the Asset, ideally the balance in the WBS element would have become Zero. Then there is no question of calculation of Interest on WBS element. You can change the status of the WBS element to TECO or CLSD if you dont want to use the same WBS element further.
    Regards,
    Lakshmanan Krishnan

  • WBS Elements and Asset Under Constructions have different Cost Centers

    Hello Experts,
    We have created a WBS element in one of the projects.
    As per standard process, when we create the WBS Element the Asset under construction is also getting created through the settlement rule within the WBS.
    These assets should have the same Cost Center as the WBS has. However we are in a situation wherein the Cost Center in the asset under construction is different than the Cost Center in the WBS.
    I have checked the settings like automatic account assignment, etc but all settings look correct.
    Can you please explain first what could be the reason for such a difference between Cost Centers in WBS and AuC's and what is the solution to avoid it in future?
    Thanks in advance
    Leena

    Thanks for your replies...
    @ Alex - There is no Investment Programme ID maintained for this WBS in question since there is no IM for this project.
    @ Abdul - Please elaborate more on Validation and Substitution.
    Regards,
    Leena.

  • Distribution of Depreciation of an asset to multiple wbs elements??

    Dear Members,
    our requirement is as follows.
    our cost centers are for 1) departments at head office level 2) Regional offices
    whenever depreciation is calculated it's posted to Head office cost center and the same asset will be used for multple projects.
    so here our requirement is the depreciation posted for a  particular asset is to be distributed to multple WBS elements or Regional offices (cost centers) ..
    please guide us to meet this requirement.
    regards,
    sashi kanth

    Hi Sashi Kanth,
    In Asset Accounting Module, you can only assign one cost center to a master data, so all the depreciation posted will be accumulated only on one asset master / cost center. Though, you can settle the multiple WBSelements to a single asset you cannot apportion the depreciation cost per WBS element.
    To meet your requirement, you have to create separate Asset Master Records (AMR's) with the required Regional Office cost center, so you will get the depreciation cost regional office WBS element or cost center wise.
    Regards
    Nitin

  • Statistical WBS element posting - Asset

    Hi,
    From the SAP help on AS03 transcation field on Origin tab >Account Assignmnet for investment  - WBS element  , I see the following information.
    WBS element investment project
    Enter the WBS element here, if the system should automatically make statistical postings of the transactions on this asset to this WBS element.
    You can specify in the Customizing definition of the transaction types, whether statistical automatic posting should take place for certain transactions.
    But I am unable to find a setting in the transaction type which allows the statistical postings on the WBS element , when we are posting to the asset.
    We have a requirement to post statistical postings to WBS element when posting to the asset and we thought of using this funtionality but unable to find the setting which allows the statistical postings on the transaction type.
    If anyone knows how to make this setting , could you please share with me.
    Thanks
    Vara Prasad

    Hi Markus,
    Thanks for your response.
    Even with the OSS note I am unable to find how to change the asset accounting transaction types allowed for statistical postings to WBS elements.
    I am aware of other steps in the configuration except this setting, could you please let me know if you have any idea on this setting specifically.
    Regards
    Vara Prasad

  • Field WBS element is not modifiable in asset master data

    Hi Friends
    In case of one of my asset classes, i am not able to modify WBS element. It is greyed out.
    I checked in screen layout rule assigned for that asset class, the fiield status is modifiable.
    Please inform whether i need to check any other thing also.
    Thanks & Regards
    Bhairavi

    Hi Paul,
    Thanks for your reply.
    Currently no WBS is assigned in the asset. I want to assign one WBS .
    Currently one internal order & 1 cost center are assigned.
    I tried insering qa new time interval also , but the field is grayed out & i cant do any changes in the field WBS element.
    I have already checked the field status of this field in screen layout rule , its modifiable.
    Kindly advice.
    Thanks & Regards
    Bhairavi

  • How to change WBS Element in FI Entry for Asset

    Hi all,
    I have a scenario where an asset has been capitalized with  WBS element 1. After several months we realized that it has to go to WBS element 2.
    We update the Asset Master Data with a new WBS Element 2.
    Depreciation from this date onwards is posted to WBS Element 2 (this is expected), but in FI the asset acquisition cost is still in WBS element 1.
    Does anyone know how to rectify the FI document with correct WBS element i.e  WBS Element 2
    Any advice would be greatly appreciated
    Regards
    Pramod Saraswat

    Hi Pramod,
    In posted document you cant change the WBS element.
    In order to post on WBS 2 , you have to reverse the acquisation entry posted on WBS1. Then update correct one in  asset master then post acquisation.
    Ravi

  • How to use WBS element in Asset master data upload

    Dear All
    Does any body know how to treat field WBS element in Asset master during upload.
    Field POSNR in table ANLA is of 8 characters, but WBS element which is entered in asst master is more than 8 char.
    I vaguely remember tht with wbs system internally assign a different number.
    Has anybody come across this issue?
    Please help
    Thanks
    Sanjeev

    There are in the asset 2 fields for PS
    One is filled when you do an settlement from an WBS (is not possible to fill in)
    The other one you found in the the tab time dependend like cost center.
    This field is available when you have assign the possibilety to do depreciation to an WBS.
    Paul

  • Report:actual costs:statistical wbs elements and assets assigned to them

    Hi all,
    I would like to run a report that gave me this info:
    WBS Element (all statistical)
    Assets assigned to each WBS
    Actual costs
    It would be perfect CJI3 but it doesn't show assets. In AM I haven't see either any report that shows WBS elements...
    any ideas???

    Thanks for your reply but this is not the question.
    The question is:
    Example:
    I have 100 WBS Elements. Each of them has an average of 5 assets assigned. (what makes 500 assets)
    I post lot of invoices in each asset.
    I would like a report that tells me at once the total actual amount posted in each ASSET and group those costs by each WBS element.
    Thanks and regards,
    Miguel

  • Asset master to be distributed to WBS element

    Dear all,
    I have created a Asset and run the depreciation for the month. (Dep. key maintained for book accounts and cost accounts) it wll get posted to FI as well as Cost center. now i am using KSV1 actual distribution to distributed the cost center to WBS element based on percentage.
    after create and saving it the distribution have not been carried out. help is need
    Regards,
    Raziq

    when i checked t.code KSB1 for that cost center and cost element before distribution that was there in the report, after when i created KSV1 for distribution with this same cost center to WBS element the when i checked it in the same report after the distribution have been done the cost center and the cost element is not there. then when i checked CJI3 against the WBS element there also the cost center and cost element is not displaying.
    it simply says No objects were selected using the criteria entered
    cost element category - 22 external settlement is it ???
    regards,
    Raziq

  • Can't change an asset that originated from a WBS element that is now closed

    When we try to transfer or make a change to an asset that originated from a closed WBS element we receive the following error message. 
    System status CLSD is active (WBS CP-00000999-009-009)
    Thanks, Kevin

    When we remove the wbs element number under the "Account assignment for investment" heading, then we are able to perform the asset transferwithout reopening the wbs. We were wanting to use that field so that our auditors could see the wbs from which the asset was created. If we do not use that field, how can we trace an asset back to the originating wbs?
    Thanks,
    Kevin