Automatic release of production order for perticular work center

hello,
any body please help me how to set automatic release of production order when creation for a particular work center. please suggest me.
Thanks & Regards
Bhakta

Dear,
Use T Code COHVOMRELEASE here select work center as ZPACK then in header menu Program--Schedule in background here define as perodic job and set ferquency as Hr.
Or Use Transaction SE38 to create  the variants for program PPIO_ENTRY and schedule it through SM36 or use standard variant as SAP&RELEASE.
Please try and come back.
Regards,
R.Brahmankar

Similar Messages

  • How to get a list of production orders for a work center?

    Hello SDN Community, 
    I have an requirement to display in a pop-up window a list of production orders for a work center.
    Does anyone know which screens/transactions would show this relationship?
    Or better yet, does anyone know how to demonstrate this from the tables themselves?
    Thank you,
    Dean Atteberry.

    Hello Mangalraj.S
    >>Goto COOIS-->For the field List select PPIOO000 - operations and layout -->standard layout
    >>and execute,by this you will be able to see the operations for each order and to which
    >>work center they are assigned.
    The system I am working on is ECC 6.0.
    For this system the values in the dropdown for the "List" field are "Capacities, Items, Order Headers, Sequences, Trigger Points, etc".  But nothing that says PPIOO000 - operations and layout.
    >>Or else in the in input screen of COOIS,enter the work center for which you want to see which
    >>are the production order's assigned and execute.
    For system I am working in, I do get a grid display when entering a work center.  It has columns like "Order, Material, Icon, Order Type, MRP cntrlr, etc."   But no column with Work Center.
    Any further insight into how to use this transaction to display a list of production orders for a work center would be greatly appreciated.
    Thank you,
    Dean Atteberry.

  • Standard Values in Production Order for Alternate Work Center

    Hi SAP Expert,
    I would like to find out whether there is possible solution for the requirements as below:
    e.g.
    >>> Routing for Product A only has one Operation 0010.
    >>> 4 Work Centers/Resources (A,B, C, D) can be assigned to run this operation where all these 4 Work centers/resources are having different capacities (Setup, Labour, Machine hour & Electricity are different).
    >>> Out of these 4 work centers, only one work center will be selected (Selection criteria will be based on the capacities & availability).
    >>> In my current setting, only one preferred work center (A) is maintained in the routing for operation 0010.
    Issue:
    >>> If I select the work center B manually in APO during the planned order creation, the Production Order created will be tied to work center B but the standard values captured in the Production Order are still referred to the standard value of A.
    Question:
    1. Is there any way I can maintained in the routing so that it will captured all the different standard values for each work centers?
    2. If the answer is yes for Q1, then can the SAP auto populate the correct standard value into the Production Order according to the work center I selected before the planned order is converted into Production Order?
    Thanks.
    Regards,
    Hooi Chia

    Hi,
    You can use alternative sequence in routing and mainain three different sequence for all 4 workcenter.
    At APO side you can maintain priority for alternative sequence in PPM/PDS.
    Now when you execute the scheduling Heuristic depending on priority and capacity workcenter will be assigned.
    Regards,
    Vishal

  • Release a production  order for partial quantity

    Hi gurus,
    Can you please tell me how can i release a production  order for partial quantity without splitting the order?
    Regards
    Rajib Pathak

    Dear,
    Best way you can conver the planned order to production oreder in partial in CO40.
    Or from MD04 screen click the planned order, choose pratial release and enter the quantity you want to release and press Generate button. the order gets converted to production orders of yr specified quantity and rest planned order remains for further processing.
    Or,
    Create order
    Goto operation overview
    Select the operation and click on release button...which will release the opration alone instead of releasing the order. If you release the order, then all the eperatios are released onec for all.
    If you go for operation release...you can release operation by operation, which will be partial release of order at header level.
    at operation level - partial release
    Hope it will help you.
    Regards,
    R.Brahmankar
    Edited by: R Brahmankar on Nov 12, 2008 9:44 AM

  • Actual hours done against a work order for a Work Center by non-maintenance

    Hi All,
    I have below question with respect to work center.
    -If there is this actual work hours done on a work order by non- maintenance personnel for a certain work center and same is not reflecting under operation tab of work order, then where & how this hours (done by non- maintenance personnel) for a work order is maintained for that work center?.
    -In which database table these hours done by non- maintenance personnel for a work order is stored by work center wise.?
    Thanks

    Have a look at the document flow button in the order header.
    The confirmation data resides in table AFRU
    PeteA

  • Production Orders Controls by Work Center

    Hi PP Gurus!
    We have to check the production orders by work center. Can we do it? If yes, could you inform us which conditions are necessary to do it?
    Our release is 4.6C and we are using PP-Manufacture discrete.
    I would like to thank you for help us with this issue...
    Best Regards,
    Valdevair

    Hi Krishna,
    Thanks for your reply...
    We've executed the transaction according your suggestion, but the values for this column are in Blank in the report.
    Is there any specific condition for the SAP shows us?
    We are using transaction CO11n to register the hours per operation.
    Once more...thanks a lot.
    BR
    Valdevair

  • Production Order Confirmations by Work Center

    Using COOIS, I can see confirmations for production orders by work center, but it doesn't give me the option to display the material number and material number description.
    Is there an easy way to create a quick view for this?
    Could someone help me out?

    Hi,
      Try with tcode co28 ,choose order header
      Enter order category as production orders.
      Enter the profile as standard one
      Enter order number and execute.
      select the displayed order order number and choose the ALL Fields icon.
      OR
      Try with tcode co28 ,choose order header
      Enter order category as production orders.
      Enter the profile as standard one
      Enter order number and execute.
       Choose the  Fileds icon and selet the fileds you need and save .
    Regards
    nandha

  • Creating a production order for a semi finished product

    Hi
    I am having a multi level bom scenario over here.
    one of the bom components of the header material is a semi finished product.
    I am using the planing stratagy 40 for that material.
    in standard sap when i create a production order for  header material. the requirement gets transerd to all the components. if the components are not available then only  a requirement is placed. when i run MRP that requirement gets converted in to a planned order. which converts in to a purchase req or a production order,
    well for my semi finished product. its a Work in process item. there wont be any stock for that item in the storage location any time.
    what my requirement is. when i create a production order for my finished product it should automatically create a production order for the semi finished product.
    is this possible with some configuration settings.

    Dear Deepu,
    for ur requirement u need to maintain MRP type PD for FERT material and also for ur HALB.
    If u run  MRP  only, it will create planned order for FERT and for all its dependent requirement(for PD).
    If u create order manually for FERT material then it will not create order for HALB material, u need to create manualy for this also.
    sree

  • Sap pp-releasing the production order?

    at are the activities carried out while releasing the production order?

    Hi,
    Order Release
    Use
    A production order must be released, before it can be processed. You can use the time period between creating and releasing a production order, for example, to carry out company checks and preparations. If you do not require this time period, you can automatically release the production order when it is created (see Automatic Release).
    A newly created production order initially receives the status CRTD (created). The following restrictions apply to a production order that has been created:
    Confirmations for the order cannot yet be executed.
    Shop floor papers cannot be printed.
    Goods movements for the order cannot yet be executed.
    Releasing the order lifts these restrictions.
    Features
    Order release can be executed at the following levels:
    With Release at Order Header Level all operations are released. The order and the operations receive the status REL (released).
    With Release of an Operation the operation receives the status REL and the order receives the status PREL (partially released). If all operations in an order have been released, the order has the status REL.
    Hope this helps.
    Revert if you need more information.
    Regards,
    Tejas

  • Error while release of production order u201CNext period is not openu201D

    Hi Experts,
    Need your opinions on this issue where my client is facing a problem while create and release a production Order on the last day of the month (Last day of period change).
    While create and release of production order for Plant xxxx, system uses to give the error; period Next (e.g. 12) is not open. Same thing if I have created the order using T. code CO01; but when I tried to release and save the order through T. code CO02 then it gave me the same error (Next period is not Open), it checks for the next period to open.
    The above scenario happens only on last day of the month. Earlier this kind of error was not there so the question is why the period check is happening while saving the production order.
    After speaking to the user, it is determined that they are facing this problem since upgrade (Since last 8 month). Hence need to check what additional check has been implemented with upgrade from R/3 4.7 to ECC 6.
    Error Message No F5201
    Appreciate your help how to dig up this issue.
    With Regards
    Anant

    Hi Guys,
    Please throw some light why on the last day of the month (Last day of period change) at the time of release the order user is getting error: Period Next (FI Next period) is not open ( message No. F5201).
    My question is why system carried out period checks at the time of release of Production Order.
    With Regards
    Anant

  • Batch is not determined automatically in PRODUCTION order for components

    Hi All,
    Am working on the batch determination for the components by Goods receipt date(FIFO) during production order confirmation.
    All the required settings are completed upto batch determination.But when click on the batch determination tab,batch is not picking in production order confirmation goods movement screen even though three batch stocks are available.
    Kindly find the attachment for your reference.
    Would grateful to your quick response.
    Thanks!
    Asirvad

    Hi,
    In general it should not be a problem. Request you to check below:
    For the Batch Determination to work in production order for the components, you should have a value for the “batch entry” field. The values if set to “3” will carry out batch determination automatically and if set to “blank” will not carry out batch determination for the components in the production.
    As well please refer the link for step by step checking.
    SAP Batch Determination - SAPs'WORD - We SAP For Your Cause
    Hope success :-)
    Regards,
    Krishnendu.

  • Cannot release production order for a plant

    Hi:
    When I try to release a process order , I get this error message:
    "CAnnot release production order for plant".
    I get this message  for a particular material in the plant. For other materials, it's working fine.
    Please give your suggestions!
    Gautham

    Hi,
    Check the Tasklist usage for your routing for that material.
    For this usage ,check in op45 against the task list type whether until release indicator has been enabled.If so remove
    and do the release.
    or
    check whether workcenter which is used for producing the   material has been locked in work center itself.
    Indicator: Usage only until release in orderIndicator used to specify for a task list usage and a task list type that an operation in the order cannot be released.  This occurs when a work center group that is not intended for production is allocated to this operation.
    When this type of operation in the order is released you must enter the work center where production should take place.
    Regards,
    nandha

  • Don't release Production Order for negative stock.

    Actually i don't want Production Order to be released, if component (child) items falls into negative stock. Is there any solution for that. If yes, please help me out.
    Thanks

    HI!
    you can write a SP to block Release a production order from planned state.
    Check the onHand stock of all child items w.r.t the warehouse and block updating the status to release

  • Control availability check during release of production order

    friends,
    Can you guys help me find the user exit/BADI which will allow me to control the release of production order after the availability check is complete.
    In detail, the scenario is that : based on a flag on material master, I should be able to ignore this product's availability during release. I cannot change the availability check to "KP" ( No check) as this product can be sold seperately. So what I thought was that if I get to control the availability check during production order release I would be able to ignore this product before check or may be after check and before the status change.
    I found PPCO0021 exit and function module EXIT_SAPLCOZR_003 which is actually intended for release control for automatic batch determination. I am not sure if I can use this.
    Please let me know if you guys have any idea.
    Thanks
    Prod_Planner

    Let me rephrase the scenario :
    I have a production order for a product P1 which consumes raw materials R1 and R2. R1 is supplied by a nearby vendor every 1 hour to my plant so I do not need to worry about the availability of it when releasing the order but R2 availability should be taken into consideration. So, function 1 or 2 in OPJK will not work (as release need to be stopped if R2 not available) hence I will be using 3. If I use 3, R1 availability is also considered hence the whole order is not released. I will maintain a flag on material master so if R1 has flag, I need to ignore R1's availability but still considering R2.
    As mentioned, I found PPCO---21 which could help me but need your help to understand if there is any other way.
    Thanks
    Prod_Planner

  • No release of production order without standard cost estimate

    Hi All,
    I have an requirement, that is production order for a material should not be released or saved if standard cost estimate for that period is not released. Basically it should not allow to release or save the production for that material, is SCE is not run for that period. I tried various options, i also overheard its possible through user exit and many people have succeed in that.
    Has anybody overcome this problem, please do let me know. And which user exit??
    Thanks in advance
    With Best Regards
    GJ.

    Hi...
    I have faced the same problem in my previous project. What i have instructed to my client is to take control of Master data and put the status as "03" Blocked for movement till the statndard cost is released for this material.
    You can relase the status to "E2" in Cross Plant Status Field in Costing one view once the cost estimate is released for the material.
    I hope this works for you.
    Please let me know if you require any fruther information.
    Thank you,
    Regards,
    Santosh
    Rewards points if helpful.

Maybe you are looking for

  • Error in report for activated hierarchy

    Hello Experts,                       I have following problem in my report: I have created 1 hierarchy for 0cust_sales infoobject other than Standard hierarchy.to get this hierarchy in place have done following steps: created authorization object wit

  • How do I update ios 7 without using itunes and get rid of this message?

    I pressed update and it has a picture message that won't go saying connect to itunes, but I don;t have itunes installed on my laptop! How do I get this to stop as I need my phone?! Help would be much appreciated!

  • My mac computer got slow.

    Hi there, friends have a problem with my mac, it happened when you download the "MacTubes" install, I set down my video, but either surprise that this does not begin downloading until there all goes well, and I started to find out why the video did n

  • AWT/Swing gui flickering

    I am trying to add the swing JDesktopPane to java.awt.Frame .The JDesktopPane includes JInternalFrame.The problem is that the GUI is flickering when resized or moved. I migrated from jre1.4 to jre1.5 and the flickering of the JDesktopPane stops but t

  • Dell 3008WFP problem

    My monitor Dell 3008WFP is broken. No image from computer, just service video with different colors. the authorized service center in Russia say that the company is no longer support this model. Why Dell refuses to support products in Russia? I can p