Automatic settlement of delivery costs MRDC for service PO

Hi,
We configured a custom condition type ZCOM (Commission). This condition was assigned to pricing procedure RM0000. This condition is defined as a delivery cost condition with accrual.
PO for non-inventory material:
- Free text item for 10 EA @ $100/EA
- ZCOM condition added at the item level for 10% ($100). Vendor in this condition is different that PO vendor.
- GR for 1 EA
- PO history shows: GR (101) for 1 EA with total value $100. It also shows DCGR for 1 EA in the delivery cost quantity and value $10.
Run automatic delivery cost settlement (MRDC): It created invoice for the freight vendor using the delivery cost amount of $10.  In PO history it shows: DCIn for 1 EA in delivery quantity field and amount of $10.
PO for services:
- Free text service for 10 EA @ $100/EA.
- ZCOM condition added at the item level (not at the service level) for 10% (value $100).
- Service entry sheet for 1 EA with value $100
- PO history shows: SEnt for $100. GR (101) for $100. It also shows DCGR for 1 AU in the delivery cost quantity and amount of $10.
Run automatic delivery cost settlement (MRDC): It created invoice for the freight vendor NOT using the delivery cost amount of $10.  It created an invoice for the full line item amount of $100. PO history shows: DCIn for 1 AU in delivery quantity field and amount of $100. This is wrong. It should have created the invoice only for $10.
Any help on what is going on it is greatly appreciated.
Thanks and regards, Jose Oyon.

no, SAP does not know this kind of fixed conditions.
even a fixed condition is depended on the quantity, and adjusted to the GR quantity if it differs from PO quantity.

Similar Messages

  • MRRL MRDC Automatic settlement of delivery costs

    I have a question regarding ERS and fixed delivery costs.
    We want to use ERS for a service with orderquantity independent costs and order quantity dependent costs. The purchase order is created based on an external operation from a production order. Initially the purchase order is created for the planned quantity of the production order.
    Realized quantities can and will deviate from the planned quantities. The realized quantities are posted to both production order and purchase order.
    Eg.:
    Production order for 10 PC --> purchase order for service of 10 PC.
    Cost of service is 0,1 per PC + 5 Eur per order--> for this order this means 0,1*10 + 5 = 6 Eur
    Now 15 PC have been realized and posted GR for the purchase order.
    Using ERS with MRRL with option Settle goods items and delivery costs has following results:
    15 * 0,10 --> 1,5
    15 * 0,5  --> 7,5
    I expect the system to post 1,5 + 5 Eur.
    Is that possible? How can I realize that?
    thanks for any help
    Jean

    no, SAP does not know this kind of fixed conditions.
    even a fixed condition is depended on the quantity, and adjusted to the GR quantity if it differs from PO quantity.

  • Planned Delivery Cost - MRDC

    Hi,
    I am trying to settle planned delivery cost maintained in PO through condition type - FRB1.
    Also maintained tcode details in table t169f.
    Did configuration in node - MM - LIV - ERS - maintained required details for the vendor
    I did GR against the PO.
    Now I am executing MRDC, nothing happens?
    Did I miss any step?
    Please revert.
    Regards,
    Dipak

    Hi
    check this
    add your freight vendor to configuration transaction: Materials Management > Logistics Invoice Verification > ERS > Specify Automatic Settlement for Planned Delivery Costs.
    Regards
    Kailas Ugale

  • No delivery costs exist for purchase order

    Dear Friends,
    While doing MIRO, i am getting an error message as mentioned below----
    "No delivery costs exist for purchase order xxxxxxxxx"
    Message no. M8014.
    Kindly guide me in resolving the error.
    Thanks & Regards,

    hi
    >"No delivery costs exist for purchase order xxxxxxxxx"
    itself says that there is no delivery cost,
    firstly check ur PO ,Did u entere the delivery cost conditions like for freight or octoi in the PO
    or if u have entered the condition then check if it is not already invoiced
    if u dont have delivery cost in po and wanna do IV for material then in miro
    change the option of delivery cost to goods/service
    (at right side of the po no field)
    regards
    kunal

  • Delivery cost (freight) for finished goods

    All SAP Gurus,
    We are supplying finished goods to our customers (against sales order).
    The delivery cost (freight) for this is beared by us, so payment to transporter's are made by us.
    For making payment to transporters, we are raising service PO.
    Is there any link between sales order and service PO or between service entry sheet and sales order?
    because there are chances that transporter may send us two bills against same sales order.
    Regards,

    not answered.

  • Delivery Completed Indicator for Services

    Hi Guys
    In PO's, in the delivery tab, the Delivery Completed Indicator appears only for Stock PO's. Is it possible to make the Delivery Completed Indicator appear for non stock PO's as well, I mean for services?
    Thanks

    Hi,
    It is not possible to setup Delivery Completed Indicator For Services Purchase orders or Non stock Items.
    Reg,
    Ashok
    Rewards welcome.

  • DELIVERY COMPLETED indicator for Services Purchase Order

    hello experts,
    i'm working in SAP with R3 4.7 for developing funtion / BAPI for a mobile web application for services purchase order.
    i have a big problem:
    is it possibile to set the DELIVERY COMPLETED indicator (<i>ELIKZ</i>) in services purchase order via BAPI or Function Module?
    <i>I'm working with BAPI_PO_CHANGE but and i succeded with material PURCHASE ORDER but not with SERVICES PURCHASE ORDER</i>.
    can anyone help me?
    thanks in advance,
    Eliana

    For material:
    Delivery completion (DCI) tick available at line item level for each material (EKPO- ELIKZ)so you can check for the each material in PO the DCI is available or not.
    For Services:
    As Service code (Service line items) are maintained in details screen of Header line item. So whenever the DCI (Delivery completion indicator) marked for that Header line item it means that all the service line items are marked as DCI for that Header line.
    DCI indicator can mark manually in Change PO mode and automatically when service entry done as final for that Header line.
    So you can check the DCI for service same way as you do for material
    Hope it will help you
    Regards
    Vikrant

  • Delivery completed indicator for Service purchase order item

    Want to check the PO item for services already delivery completed.
    Field EKPO-ELIKZ (delivery completed indicator) is for material line item, is there a equavalent field for Service line item?
    What field /how to to check for a service line item in Purchase order already delivery completed ?

    For material:
    Delivery completion (DCI) tick available at line item level for each material (EKPO- ELIKZ)so you can check for the each material in PO the DCI is available or not.
    For Services:
    As Service code (Service line items) are maintained in details screen of Header line item. So whenever the DCI (Delivery completion indicator) marked for that Header line item it means that all the service line items are marked as DCI for that Header line.
    DCI indicator can mark manually in Change PO mode and automatically when service entry done as final for that Header line.
    So you can check the DCI for service same way as you do for material
    Hope it will help you
    Regards
    Vikrant

  • Third Party Order Delivery Costs ( COGS for Purchasing)

    Hello Experts
    We have a Scenario where in its a 3rd Party Order direct shipment Process where the Shipping is done by a Logistics Vendor!
    So->PR>PO>Inbound Del->GR->IR>Goods Issue-->Customer Invoice.
    Now the Issue we have is Delivery Costs(Freight,Insurance,Duty etc) raised by Logistics vendor are taken as estimated costs during the PO creation with appropriate Condition Types but when at the end of the Month when Actual bill is sent the Prices are to be settled and paid back!!
    2)Assuming vendor invoice of $100 and Freight invoice of $10. The accounting entries aare as follows:
    Vendor 100-
    GIT(Goods in Transit) 100
    Fright Forwarder 10-
    GIT 10
    Since the Stock is Non Valuated here how can Account postings from PO/GR is shown for COGS in SAP.
    Understood that COGS is hit when Goods Issue(GI) is done but our need is to account COGS in Purchasing.
    Can anybody throw some idea of how to Capture the COGS in PO and post then individually with different G/L accts for Freight,Insurance etc.
    Full points guaranteed heheheh! Pls help me with your expert suggestions.
    Regards,
    Hari'
    Singapore

    Hi Suraj,
    Thankx for your reply and sorry for my delayed reply.
    Well your answer is too immature for me to apply since I have already done all those and surpassed those things.
    Well to make my question simple I need to account Delivery Costs(Freight,Insurance etc) during GR.Although I have setup all the COnd types in PO Pricing.Now I need to know since GR is Statistical and Goods are in Transit can I account the Delivery Costs into seperate G/L acounts??
    It would be great if any of the Forum ppl have already setup capturing of the Delivery Costs in PURCHASING and accounting them into Sepate a/c's. I feel this is Common Scenario in most of the Mfg Org. So knowledge transfer is higly appreciated!!
    Rgds,
    Hari

  • Reg:Delivery complete indicator for service PO

    Dear all,
    I have configured delivery completed incator for the specific field selection group for the particular plant for service PO's also i have activated in inventory management the same indicator for that plant but for service PO document type i dont get that indicator . Is there any specific settings to be done plz guide
    regards
    VKK

    Hi,
    Have you checked the field settings for the below field selction keys, because the field status follows the link rule and priority is assigned based on that.
    Field selection keys:
    - Transaction: E.g ME21N, ME32, ME33 etc.
    - Activity Category: Create AKTH, Change AKTV, Display AKTA & Extend PO AKTE
    - Document type: UBF for UB, NBF for NB
    - Item category: is determined in combination with the document category.
    First two characters consist of letters PT, third item category and fourth document category:
    A for RFQs, B for PRs, F for POs, K for contracts, L for SAs. e.g PT3F for a SC item in a PO.

  • Cost Report for service order

    Hi All,
    How to take out a cost report for a service order? like my requirement is how the cost of a Service Order  is hitting to which cost center and profit center and company code and posting of the concerned GL along with the activity type.for example i have a service order where some activity is there with various hours all togather 25 hrs, how this is costed and posted in whic cost center and GL and Porfit center along with the rate.
    Thanks,
    Prasad

    Please, try transaction KOB1.  You also should be able to drill-down to line items with a partner object view.

  • No delivery costs exist for PO

    hi,
    during miro, i click on planned delivery cost indicator and got the error message as above.
    may i know how to know the PO has no delivery cost?
    1) is it from purchase in record?
    2) or is it from condition type? if from condition tab how to know there is no delivery cost condition type?
    thanks
    rgds

    Under the conditions control tab, you need to check off Print price and then on the item detail line, check "Free"
    This will give you a soft error to proceed.

  • MIRO for Planned delivery cost

    Hello,
    Its Raw material  PO with Freight  & unloading Charges codition.Excise duty applicable only for Raw material .
    service tax applicable for Freight & unloading charges vendor.
    while booking MIRO for  Raw material ,excise accounts should be hit  & for  Planned delivery cost  service accounts shoud  hit.
    but While Posting Planned delivery cost tax code for which sevice tax code has been used, excise offset account is getting Posted together with service tax accounts.
    How to Post MIRO for Planned delivery cost with only service tax accounts.
    Regards,
    Jyoti

    Hi Deva,
    Is the problem about the rounding of the value?
    If so I sugest you modify the rounding scheme of the conditions to 'round up' in the condition master. In this case 0,004 would become 0,01. It's important to know that currency is always posted with two decimal numbers, but you can always do this: 1000units cost 4$ (for example).
    For what I know you cannot post a value in invoices for less than 0,01$.
    Give more feedback.

  • Tab option for choosing Planned delivery cost in Miro screen

    Hi all
    I'm a new user in SAP system and I have a question as follows:on Miro screen, I do not see the tab, select Planned delivery cost, I think someone did somthing in  system and made it hidden.it displayed above the layout tab, so  I want to know how displays it on the screen?
    Thanks for your help

    Dear,
    Please go into transaction MIRO
    then on item level u can see One option with 3 selection criteria
    1) goods/serv item
    2) planned delivery cost
    3) goods service + planned delivery
    please select the 2 option
    regards
    amey

  • Planned Delivery Cost Settlement (MDRC)

    Hi All,
    I tired so many ways to settle planned delivery costs through MDRC since ERS don't settle the delivery costs. I keep getting "No values for this selection" msg. I made sure I fill in the correct information at the intial screen.
    What am I doing wrong?
    Thanks!

    Hi Duke
    I still unable to see MDRC tcode anywhere....
    i have not understood ur query also, if u want to settle planned delivery cost it will be captured at the time of GR to freight clearing account.
    The stock account is debited with the planned delivery costs at goods receipt and the system makes the offsetting posting to a freight clearing account. This posting is then cleared by an offsetting entry to the vendor account at invoice receipt.
    Regards
    Yogesh

Maybe you are looking for

  • Difference in Balance between FAGLBO3 and FAGLL03?

    Hello Experts, I have perticular one GL Account (ASSET UNDER CONSTRUCTION) where the fagll03 and Faglb03 balance are not matching. What may be the reason and how i ll sort it.It is high praority. Regards, Sumeya offrin

  • Calculated rows

    Hi All, I am trying to create a simple report in obiee 11g dashboard. I created the National column through selection steps ( Region1+ Region2 + Region3).I am thinking how to create the calculated measures ( B%). Do we need to create this measure in

  • Drill down report in EBS

    Hello Experts, we are implementing oracle EBS R12.1.3 for our one of the client, and they want the feature like drill down reports. As per my knowledge we cannot create drill down report using oracle reports builder. client doesnt have license for or

  • How to display the status message based on student marks..

    Hi all, i have student table that has columns mark1,mark2,mak3... i want to display the student name,staus as pass or fail based on the marks.. in a single query.. if the student score above 30 in all the subject i should display the status as pass o

  • Dynamic LDAP Groups with WLS5.1

    If I am using the Dynamic Groups feature of Netscape Directory Server V4.1, can I use this to define a group using using the LDAP Realm. Thanks Ken [kyoung.vcf]