Billing in the basis of billing plan for multiple schedule lines

Hi All,
I have one scenario in which we have created milestoen billing via project systems in sales order. Now Suppose I have three line items in my sales order and against each line items we have maintained multiple schedule lines. ex. 10%, 40%,50% respectively. Similarly for other line items also we have maintained the same. Now I need to generate invoice on the basis of schedule lines(billing plan). for ex. single Invoice covers 2 schedule lines out of total schedule lines in the line item. Similarly for other line items.
Kindly guide.
Thanks.

Hi
Your milestone billing plan integrates with PS means that you have an order related billing.
Hence schedule line is a confusing word and I assume it as a billing plan.
Each milestone-related billing date is blocked for processing until the Project System confirms that the milestone is completed. The billing block will automatically be removed once the milestone is achieved.
Do maintain copy controls properly at item category level (VTFA) and your billing should happen standard SAP way.
If still you face any errors, please post the screenshots.
Thanks
Atul

Similar Messages

  • Delivery date variance for multiple schedule lines in EKET

    Hi experts,
    can anyone tell me what dates  are used (from EKET, EKBE or any other table)  to calculate delivery date variances when there are multiple schedule lines in EKET table. I am able to match single schedule line POs but not POs having multiple schedule lines.
    thanks in advance,
    purvang

    can anyone provide input on this?

  • I purchased the Adobe Creative Complete Plan for Annual Prepaid, and the Check Out just wouldn't proceed. It is still loading after click the confirm button. Dear adobe staff, please assist urgently.

    I purchased the Adobe Creative Complete Plan for Annual Prepaid, and the Check Out just wouldn't proceed. It is still loading after click the confirm button. Dear adobe staff, please assist urgently.

    I am having a similar problem. I am using Chrome and tried on Mac and on PC but the same. Its not completing my order and on PC saying:
    We were unable to process your payment please contact our customer support.......... etc
    But strangely its giving a confirmation button again. It gave me this error upon reconfirmation:
    PMT_000011 : adbehme, en_IE, There is money to authorize, But no Aurthorize delegated were applicable, 12834289525

  • I purchased the Creative Cloud Photography Plan for 9.99 and I cannot gain access to Photoshop, just Lightroom. It worked for night I purchased it and now I cannot open up Photoshop.

    I purchased the Creative Cloud Photography Plan for 9.99 and I can't open up Photoshop.  I had access to it the night I bought it online and now I cannot use it. Will someone help figure this out.  Perhaps I'm an idiot and just missing an obvious step so I apologize for that but, I still NEED HELP!!!

    I have a laptop with a Windows operating system (not lucky enough to have a Mac) and as far the Adobe version, it's the plan for 9.99 that Adobe is offering.   I was under the impression that the Creative Cloud Photography Plan included Photoshop and Lightroom, the latest versions of both, because that's what it said when I purchased it.  I'm sorry my information is too limited or not detailed but, it's a pretty basic concern. I bought something,  it's not working and I want to know why.  Thank you and apologies for sounding rude. Thank you for responding as well. 

  • HELP! i currently am signed up for the month to month plan for Photoshop...

    Hi, i currently am signed up for the month to month plan for Photoshop.. there has veen no problem in my payments etc until now when i open up photoshop its tells me to Renew my Subscription, and that my computer cannot connect to adobe server even though im connected to the internet.. the payment for this month has already cleared my bank!? Any Ideas whats wrong???

    When you sign in to https://creative.adobe.com and check your account info (click the upper right), does it say you're still active? Sounds like something got borked in the CC app and/or PS CC.

  • I currently have the 2 gig data plan for $50, plus a free 1 gig promotional attachment but Verizon is currently offering the 3 gig data plan for $50, but if I upgrade will I lose the free 1 gig promotion I currently have attached to my account?

    I currently have the 2 gig data plan for $50, plus a free 1 gig promotional attachment but Verizon is currently offering the 3 gig data plan for $50, but if I upgrade will I lose the free 1 gig promotion I currently have attached to my account?
    I understand I will still be getting 3 gigs of data for the $50, I would just like to continue to have the free 1 gig promotion I was already getting, if you Verizon was willing to do it before then why can't they continue to do it now?

    Like Ann154 said, changing plans often results in the loss of any promos you may have.  In your case, it makes no difference to the price you will pay - you'll have 3 GB for $50.  Whether you have 1GB free, or a better price on the 3GB plan is a wash.  I'd leave things alone....

  • I am considering a base 21" iMac ($1099 @ Best Buy) for home use.  It would be my first Mac.  Is the base model powerful enough for everyday home use and some light video editing or should I upgrade the CPU, Ram and to a Fusion drive?

    I am considering a base 21" iMac ($1099 @ Best Buy) for home use.  It would be my first Mac.  Is the base model powerful enough for everyday home use and some light video editing or should I upgrade the CPU, Ram and to a Fusion drive?
    Purchasing with the upgrades through Apple would add about $800 over the Black Friday deal at Best Buy.  Just looking for some advice if I will be satisfied with the based model.

    All models will do what you want. Upgraded models will do it faster than the standard models.
    Just why are you thinking of switching to a Mac?

  • Can you have one icloud storage plan for multiple devices

    hi,
    i'm wondering if there is a way of consolidation various icloud storage plans into one.
    i only use my free 5gb for my 5s as i back up photos to my mac, however my wife has already upgraded her storage plan for her 5c to the £1/month.
    with the new release of backing up your entire photo library on you mac (which im keen to do) im going to need to upgrade my own account as the mac is set up for my apple id.
    i currently also pay for itunes match.
    im keen to know if there is a way we can use one large back up facility for: my 5s, the mrs's 5c, the mac, with out paying for multiple storage plans.
    im guessing the itunes match is stand alone but if i can have one payment for large storage and put everything there that would be ideal, and seem a reasonable request for most families.
    any help greatly appreciated
    thanks
    Scott

    Accounts can't be merged.

  • Shared planning for multiple companies

    Hi SB1 guys,
    We have a prospect which is divided in <b>3 different companies</b>.
    A large part of the payroll is common for those three companies (in other word, employees from company A work also for company B & C - so they have the same user name and password in the three DB)
    <u>My question is</u>:
    "<b>Is it possible to get a shared planning/agenda for the three companies</b> ?"
    If you don't see what I call "Planning/Agenda", it contains informations you synchronize with MS Outlook.
    In this planning/agenda, I want to get informations from different companies BUT for the same users ! (as I said, ONE employee works for several companies). 
    In some other words, I want a common visual planning for three companies in the same time.
    I search for an answer for several weeks now, someone would be really kind if he brings me an answer (even it's not possible) !
    Many thanks,
    David

    Thanks Baskar but I've already think about this issue.
    In fact, my prospect want a visual planning where the manager could see a global view of employee's planning.
    Sync with MS Outlook is helpful and sufficient for "individual use", I mean you could easily obtain info of your planning from different companies in MS Outlook but it's not possible to get this planning for multiple users.
    My main request is to get a visual common in SAP Business One, but not in Outlook (where it's not possible in fact)
    Thanks,
    David

  • How can you use the same e-mail address for multiple ipads?

    I have two iPads.. an iPad and an ipad 2.  I registared my new ipad 2 and now my old ipad is will not let me log on and is telling me that my e-mail address is already in use.  how can you use the same e-mail address for multiple ipads?

    And by using the same Apple ID you can also share purchases.  If you have a different Apple ID for each iPhone then you can't share purchases.

  • Can you buy a plan for multiple computers?

    Can you buy a plan for multiple computers? For just one price and one account?

    MBAs do not have user replaceable batteries. I'm not sure you could even buy third-party replacement batteries. You may be able to purchase an Apple part through places like ifixit.com.

  • Requirment class & Procedure for each schedule line category

    Hi all,
    In requirment class we have a switch on/off indicator for avai check and TOR.In define procedure for schedule line category also we have the same.
    If I dont want the system to carry out availabilty check, I can switch off the indicator in requirment class or at schedule line category.
    My question is why we have these indicators in 2 places.
    It is written we can fine tune these settings at Define procedure for schedule line category settings
    Could anyone explain in details with Business scenarious
    Thanks in advance
    Mano

    Hi,
    1. Availability check at Requirements Class level -
    The requirements class contains all control features for planning such as relevance for
    planning, requirements planning strategy and requirements consumption strategy.
    In addition, it is specified at a global level whether an availability check is to take place for
    the material in the sales and distribution documents on the basis of the ATP quantity
    (ATP = available to promise) and whether requirements are to be passed on.
    2. Availability check at Schedule line category level -
    A finer degree of control can be obtained for sales documents using the schedule line category.
    Replenishment lead time is only included in the check performed on the basis of the
    ATP quantity.
    You can control with the schedule line category whether an availability check and
    transfer of requirements should be carried out in the sales documents.
    Note -
    1. At the global requirements class level, the availability check can only be switched on in combination with the transfer of requirements. At schedule line level, the settings are proposed from the requirements class.
    2. If the availability check is switched on at requirements class level, it can be switched off at schedule line level. However, you cannot switch on the availability check at schedule line level, if it is switched off at requirements class level. You can make this setting at schedule line level. But the system ignores it and the setting for the requirements class applies.
    3. Also, at schedule line level when the availability check is switched on, the transfer of requirements can be switched off. For example, this makes sense for inquiries or sales information.
    4. The settings specific to schedule lines for performing an availability check are only relevant for sales documents. In the shipping documents, the settings from the requirements class and the delivery item category are used. As with the schedule line category, the availability check can be switched off as required in the delivery item category.
    regards
    bhaskar

  • Percentage wise Confirmation for Multiple Service line items

    Hi,
    Percentage wise Confirmation for Multiple Service line items    
    During doing service entry sheet am able to do % wise confirmaion from
    Menu -> Entry Sheet -> Create -> With Planned Service -> Enter Percent.
    But this works only for single line item the first line.
    If we have multiple line items & if i give 10%, It calculates 10% for
    all items.
    We want Line wise % confirmation can be given as % confirmation will differ from
    line to line.
    Thanks
    Shashank

    Dear ,
    This percentage is a header data i.e applicable for all service items
    F1 help clearly says
    Percentage quantity to be adopted
    Use
        If you wish to adopt the planned services from the purchase order, you
        can enter an additional percentage in this field in order to have that
        percentage adopted instead of the total quantity shown in the purchase
        order.
    Example:
        Quantity specified.............Quantity to be adopted:.............Quantity specified "
        in purchase order:....................... 10 %..................................entry sheet:
        Service  1.......100 pc ................................................................10 pc
        Service  2.......200 m  ...............................................................    20 m
        Service  3. .....30 h   .................................................................   3 h
    Edited by: redriver on Jan 22, 2012 6:50 AM

  • Split delivery for each schedule line

    Hi,
    We have a requirement to split deliveries for each schedule line in the order.
    For example: I have an order with one line item which has 2 schedule lines. If the schedule line date on one is 01/29 & the other is on 01/31, and the delivery due list VL10A is run with a range 01/29 - 01/31, it picks both the schedule line & combines them into one delivery.
    Is there a way by which we can force them to create 2 different deliveries (as it would if the delivery due list was run for each day at a time).
    We created a data transfer routine (deliveries), and populating ZUKRL with schedule line date & that doesnt solve the problem since the routine is triggered once for each sales order line and not for schedule lines.
    SAP reverted back that this is standard SAP behaviour to cumulate all due schedule lines into one delivery, but I would like to know if anyone has any other solution ?
    Thanks in advance!

    First of all you have to use VL10E to create deliveries, since it creates one delivery item for each schedule line.
    Then play with your own delivery role copied from standard profile 0201:
    you can trigger 3 different flags to reach your goal:
    Cumul. Rule: Rule for calculation of quantity to be delivered
         There is a field that contains a cumulated quantity in delivery lists
         with item or schedule line views. The quantity at which the list line
         (document item or schedule line) is delivered is defined in this field
         when it is selected and the delivery process is started in the
         background. The value is a default and can be changed by manually
         processing the delivery list on the item or schedule line level.
    SplitSchedLine: Rule for creating one delivery item per schedule line
        In a delivery list in item view with multiple schedule lines, you can
        decide for the same document item whether you want to generate one
        delivery item per schedule line or whether you want to deliver the
        cumulated quantity of the last schedule lines selected.
    LimitSchedLine:  Allow constraints on schedule line level
         You can use this indicator to limit selection o
         delivery when
         o   Delivery due date and/or
         o   Planned goods issue date and/or
         o   Route schedule
         does not fall within selection range.
    This should help you to solve your problem.
    pls. reward points if helpful
    Regards
    Roberto

  • How to create diferents deliveries for each schedule line

    Dear gurus,
    I have sales orders with many schedule lines in order to deliver in diferents dates. We need to create all the deliveries together but each schedule line needs to be in a diferent delivery with the corresponding delivery date.
    I analiced the customizing about pool for delivery creation (VL10) but all I can change is for display and can not change the way the delivery is created. If we select two schedule line with diferent dates, the proccess create only one delivery with the total quantity and the first date of delivery.
    Anybody knows some way to make the proccess create individual deliveries from diferents schedule lines?
    Tanks in advance!
    Marina.

    Hello Marina
    I hope you are using VL10E. Did you try working with Delivery creation date (range) and Delivery Date calculation rule? For example if you go for a value of 2 for the CalcRuleDefltDlvCrDt ('Rule for determining default value for deliv. creation date), then system will consider only those sched lines which are to be delivered today and tomorrow.
    You also have the possibility of setting up your own routine for CalcRuleDefltDlvCrDt.
    Thirdly SAP has suggested a solution for Scheduling agreements ( valid for releases upto 4.7). In this SAP has suggested solution 4 for ensuring all schedule lines are not delivered together. You can customize the code to include Sales orders ( in stead of Sched Agreements)  in your case. Though it is for release 4.7, I think you can use the smae concept in ECC also.
    137937 - SD scheduling agreement: Delivery split for each schedule li
    Check it out and let me know how it goes. Good luck.

Maybe you are looking for

  • IHC Duplicate Payment Request

    Dear All, I have an interesting scenario for IHC. Is there a way of checking and stopping duplicate payment requests. My scenario is as follows: Step 1: Execute payment run for subsidiary for external vendor payments (F110). This creates an IDoc and

  • Problem of opening pages 2.0 document in Macbook pro

    I have just downloaded ipad pages 2.0. I created a file and sent it by email, but it comes out as a pages.zip file and I cannot open it in pages 2009. What to do?

  • Original itunes account computer crashed

    My main computer (laptop) completely crashed/just flashed it self off and died. This was the computer that had my original itunes acct on it. Since then I have not been able to upload any of my new music to my iPhone 5.  It has the old stuff but will

  • Upgrade to SQL2008 to SQL2008 R2 on 32 bit 2008 server

    Hi There  We have 2008 32 bit server  running with SQL2008 & now we want to upgrade the it to SQL2008 R2.  Is it possible to upgrade or install the  SQL2008 R2 on 32 bit server. Regards Rahul

  • Change optimizer_mode from rule to choose ?

    Hi All Could we change optimizer mode from rule to choose by restarting the instance thanks kedar