Calculation of dates in Sales order in gATP

Hi
Can anybody please tell me how scheduling works for the following dates in sales orders for materials planned in gATP.
1) Unloading date 2) Delivery date 3) Goods issue date 4) Loading date 5) Material availability date 6) Transportation planning
My understanding is that gATP gives the MAD date and other remaining dates like transportation planning date, unload date etc are calculated using master data in the calling system eg ECC.
We are facing an issue in our system where if a material is planned in ECC, it has all dates in the sales order calculated as expected based on ECC master data.
If the same material is planned in gATP, it simply copies the MAD date to all other dates. So it is not considering the pick/pack , transportationplanning times from the ECC master data.
Is this standard system behaviour and to avoid this  Do we need to activate Scheduling in gATP along with master data maintenence in APO ?or any user exit plus execution steps is avaialble to by pass APO master data mentaince.
Appreciate your responses...Regards - Amit

Amit,
We are facing an issue in our system where if a material is planned in ECC, it has all dates in the sales order calculated as expected based on ECC master data.
If the same material is planned in gATP, it simply copies the MAD date to all other dates.
The system where the parts are planned is irrelevant.  The important issue is the system where the ATP is conducted.
My understanding is that gATP gives the MAD date and other remaining dates like transportation planning date, unload date etc are calculated using master data in the calling system e.g. ECC.
I have never seen that statement validated in any SAP documentation.
From online help:
SAP R/3 uses the order type to determine whether shipment scheduling or transportation scheduling should be executed.
If scheduling is activated, SAP R/3 determines a plant for the material for each item. If it is specified in the integration model that the availability check should take place in SAP APO for a material in this plant, transportation and shipment scheduling also takes place in SAP APO.
Standard SAP APO GATP supplies three different methods for shipment scheduling.  If you are conducting ATP in APO, and you have not configured one of the three scheduling methods, then shipment scheduling does not take place, and the system will react as you have described.  
Read up on it here
http://help.sap.com/saphelp_scm70/helpdata/EN/05/f8923945b12c4de10000000a114084/frameset.htm
Best Regards,
DB49

Similar Messages

  • Delivery date and sales order creation date

    Dear all
    Can you please explain the relation between delivery date and sales order date. In my case i can create delivery with delivery date as before the sales order date... how it is possible that i can create delivery before the sales order date.??
    Please explain.........
    Warm Regards
    Inder Pal

    Hi,
    Sales order date: Date on which the customer officially places an order to your company.
    All the commitment and product allocation counting starts with reference to this date.
    e.g. customer says that the goods are required from 20 days of placing order, then from this date the calculation starts.
    Delivery date: Date on which after the system goes through material availability date, replenishment time, calculates the date on which physically the goods can be delivered to the customer.
    e.g. customer orders 100 qty of material X in 15 days, you will hve to check this delivery date through availability check which can be done in sales order and also delivery.
    payment date is based on this delivery date.
    regards,
    Siddharth.

  • Determination of First Date in Sales Order

    Hello SAP Friends, 
    Below is the issue we realised during the testing. The issue is with First date in the Sales Order which is not updated as per Unloading Point Calendar .
    As per details I received, it should refer Unloading Point Calendar for ShiptoParty and populate the next working day as First date into Sales Order.
    How is First Date determined in the sales order?  Is there any config settings which is based on Route to do this? Or Is it controlled purely based on settings done in Tcode: VOV8, Leadtime days? I do not think VOV8 settings is controlling that in our APO system.
    I have checked MAD, Pick/Pack, GI date all are populated correctly, But First Date did not follow the logic Unloading Point Calendar of ShiptoParty.
    Please let know your inputs in this regard.
    Thank you
    Satish Waghmare

    Satish,
    I unfortunately don't have a solution for you.  However, here are a few observations, and a question.
    My experience is that 'First Date' in R/3 is not determined.  In every sales order I have ever seen, First Date is proposed (matches the requested delivery date in the Sales order header) by the system, but can be overridden by any changes that the user may elect to make.
    Generally, then, after First Date is entered, the R/3 system then may be configured to determine certain master data:  Shipping Point, Unloading Point, Route, Route Schedule.  From this master data, if you are performing ATP in R/3, the system will then also calculate various dates (if configured) for the confirmed schedule proposal:  Normally these calculated dates are Delivery Date, Goods Issue Date, Loading Date, Material Availability date, Transportation Planning Date.  If you have configured Route Schedules in R/3, other dates may be determined.
    If you are performing ATP in APO, then any such scheduling must be performed in APO.  Relevant Master data that was determined in R/3 is carried across to APO during the ATP check and is then used to calculate appropriate durations.  This does not happen automatically, you have to configure the scheduling technique you wish to use in APO.
    So, my first question:  Are you performing ATP in APO?  If not, then you should probably close this post, and re-enter in one of the SD forums, since it is an SD issue.  If you are performing ATP in APO, then what scheduling technique are you using?
    Best regards,
    DB49

  • Pricing after change of delivery date in sales order

    Hi,
      When i change delivery date in a sales order prices are not recalculated automatically .
    I want the prices to be calculated automatically .
    thank you.
    Ashok

    hi,
    i have this problem, can anyone suggest me, is there any user exit or anything relevant for the solution.
    When we attempt to remove the Rejection flag (for any Reason) The system is changing Dates in sales order like Delivery date , Shipping date, GR date  to current date this needs to be stopped and client wants to retain old set of dates when rejection flag is removed
    waiting eagerly for this solution. if you find send me mail to my id [email protected]
    bharadwaj.

  • Tax date in sales orders and invoices (Billing)

    Hello Experts,
    I have an issue related to Tax date in sales orders and Billing documents.
    In our environment we calculate taxes at the time of sales order creation and billing document (invoice) creation.
    Currently we modified 'ZXFYTU03' exit to pass tax date which is system date. Our business processes are such that, there is a gap of 3-5 days between sales order creation and billing creation. So for some orders we see tax discrepancies between order and billing.
    Through forums I understand that we can use 'service rendered date' at sales order item level. Solution would be passing date in 'service rendered date', we can pass date in 'service rendered date' field in sales order.
    The problem is to copy same date in billing document 'service rendered date'
    Does anyone have any idea how we can copy the sales order service rendered date to invoice service rendered date?
    Through forum i understand that we can use copy controls, data transfer routines etc...Appreciate if someone can guide me on how i can use these...
    Thanks in advance
    Pradeep

    Tried 2 options...
    1. Modify program RV60AFZC (FORM USEREXIT_FILL_VBRK_VBRP) to pass VBRP-FBUDA = VBKD-FBUDA. But in later part of the process, in SAPLV60A-LV60AA21 (perform fakturadaten_lieferbezogen), VBRP-FBUDA is overwritten by LIKP-WADAT_IST which is goods movement date. So this is not solving my problem.
    2. Modify program ZXVVFU08, to get service rendered date from VBKD-FBUDA based on CVBRK-XBLNR (Sales order) and populate CVBRP-FBUDA. But unfortunately this user exit is being called after user exit 'ZXFYTU03' where tax related data including tax date which is being passed. Somehow tax date in this user exit 'ZXFYTU03' is document creation date which is system date.
    With 2nd option, service rendered date from sales order is copied to invoice doc, but the tax is calculated based on document creation date since the tax user exit 'ZXFYTU03' is being called first...
    Per this, coustom routine did not work...
    Refer: Service Rendered Date (VBRP-FBUDA) for SD Invoice

  • Delivery Date in Sale Order

    Dear All
    Delivery date in sales order should automatically changed or by defalt it should be after 2 days of creating the sales order.
    I have tried with lead time period and the ways given in the forum, but the schedule line/delivery date is by default coming as the day of sale order creation.
    Please guide me how to do it.
    Regards
    SB

    Hi,
    Goto Tcode: VOV8
    select sales document types
    goto request delivery date tab
    remove tick mark or uncheck propose delivery date
    and maintain lead time 2 days.
    thanks.

  • Two Delivery dates in Sale Order against one item

    Dear All
    I need two delivery dates in sale order. one is default at the time of creation sale order. second i need actual delivery date which will be confirmed by production planning department after analysis the order whether material can be ready on that delivery date or it need to change. Actual delivery date may vary from original delivery date and both need to preserve in system. kindly provide solution. best regards.
    Manjit

    You need to select the Availability & Transfer of Req. check box in Schedule Line Configuration.It will transfer the req. to PP.So while creating the sale order , schedule Lines will be confirmed as per the Available Stock.
    System will give you the Default Delivery Date as the Date added after Lead Time in days in the Configuration.Else system will give the Current Date.
    Best regards,
    Ankur

  • Schedule Delivery Date in Sale Order

    Dear All,
    I have an order on 03.11.2009 (today) and its last delivery date is 15.11.2009. It means that I have to deliver the complete order on or before 15.11.2009.
    So where can I put this date in Sales Order?
    Regards,
    Vishal

    Hi Vishal,
    Your Last Delivery Date can be entered in the "Requested Delivery Date" field in the sales order.
    By doing so, the system will give us a confirmation that whether the delivery can be made possible on the Requested Delivery Date or NOT (The status can be seen by going in to the Schedule Line Level of your line item).
    The system also gives us the NEXT POSSIBLE DELIVERY DATE with the confirmed  Quantity as a Second Line item in the Schedule line level.
    The System considers mainly the Material Available Date to come to a conclusion on the Delivery Date of the goods. Also, there are other activities (Loading Time, Transporation Planning Time etc) for which some time will take and that also need to be considered (The same can be seen by going in to the Schedule Line Level of your line item and then click the Shipping button).
    Your Scenario: In your case, the delivery can happen ON OR BEFORE the Last Delivery Date.
    So for that follow the steps:
    Step 1: Put the Last Deliv Date in to the "Requested Deliv Date" field in Sales Order.
    Step 2: After enetering the other necessary details in the sales order then Save it. Now go the Schedule Line level of your line item and look for the Confirmation of the Delivery Quantity on the Requested Delivery Date.
    If Yes: Then its your wish that you can Prepond the Delivery Date by giving the required Delivery date during your delivery document creation.
    If No:
    Then you have look for the Next Possible date. OR Make sure that you can manage all your other activities like Loading, Transporation Planning etc. in 10 - 12 days time and make your material Availabilty today and do the delivery.
    Reagrds

  • How to syatem determine delivery date in sales order

    hi sap gurus
    how to syatem determine delivery date in sales order
    Thanks and regards
    ram

    Hi Friend,
    There are many things which determines the delivery dates.
    01. PICK TIME+ PACK TIME +LOADING TIME
    02. LEAD TIME in days (VOV8)
    03. Shipping point
    04. Scheduling line
    05. Kind of availblity check
    06. If the above things are maintained as blank then the current date will be the delivery date
    However whether it must be proposed by the system or not is determined by one check box there find in VOV8 in requesteed delivery date determination tab.

  • How system determine delivery date in sales order

    Hi, sap gurus
    I am new to sdn forum please help me regarding my question
    1) how the system will determine delivery date in sales order
    2) what are factors effects to conform sales order stock
    3) what is different between static check and damanic check in credit mgt
    Thanks and regards
    nishad

    hi,
    Reg question:1 - System determines the Requested Delivery Date based on the Scheduline assigned to the item category of the item in sales order.the schedule line in the order transfers the requirements trhu MRP (can be individual or collective) . If its ruch order , you configure the order type "Deliver Immediately".
    In Detail:
    The TOR depends on the Requirement Type (MMR), Requirement Class(MMR), Checking group(MMR) and the Sc line category (Line Item). For the TOR to happen u need Plant at line item, scheduline category markd for TOR, Requirement Class marked for TOR and Checking group in MMR (Availability check)
    What all stocks need to be checked during Availability check is controlled by using the checking rule.. for example for AV -02 Ind Requirements a checking rule will be assigned and this checking rule- and then what all stocks need to be considered to determine the delivery can be maintained here.
    Rgds
    Sai

  • Change Delivery date in Sales Order

    Hi all
    I want to change Request Delivery Date in Sales Order. But when I changed Request Delivery Date system appear" The default date is not copied into existing schedule lines"
    And Delivery Date didn't change.Could you tell me how to change Delivery Date ?
    I setup Request Delivery Date - September 21th but Availability Date is September 19th. Could you tell me how to setup loading time, picking time, packing time ?
    Thank and Best regards,
    Thang

    Hi,
    When you change the Request Delivery Date, it automatically changes the schedule line date of all the materials, but by default does not change the schedule line date of the ordered material.
    So just check the ordered material schedule line date and change it manually in the order.
    Similarly maintain the same date in all the resp fieldsi in the delivery, wherever you see the date.
    Regards,
    Siddharth.

  • Schedule line date in Sale order for backward sched.

    Dear Experts,
    In my MTO Scenario, I want to Use Backward Scheduling, so as any change in Schedule line dates in Sale order shall take effect at least in planned order Stage, i.e in output of MRP,
    But not happening so..
    I  have customized OPU5 and checked OPU3 as well,
    Please suggest...
    Regards
    Raghu

    HI Mario,
    Thanks for reply,
    I have not worked in this strategy but will try,
    What i found was, in Planned orders detailed scheduling tab, the Scheduling type appeares to be Forward, but when i convert it to Production order it shows backward scheduling.
    This duel behavior is difficult to understand.
    Regards
    Raghu

  • User Exit for Requested Delivery Date in Sales Order

    Hi
    Which user exit can be used to change Requested Delivery Date in Sales Order.
    Scenario:  Sales Document Type: OR has Lead Time: 7 days.  System always proposes delivery date after 7 days.  We need to change this Lead Time based on plant.
    Thanks in advance for your support.
    Regards
    Uma

    Hello,
      try with USEREXIT_MOVE_FIELD_TO_VBEP or USEREXIT_SAVE_DOCUMENT_PREPARE, of program MV45AFZZ.
    Hope to be useful.
    Best regards,
    Andrea

  • Billing date in sales order should not be modifiable to backwards dates

    hi gurus
    I have a requirement where in few users while creating a sales order , they should not be able to modify the billing dates to previous dates . So that particular field shd not be modifiable . Could use some help here .
    Regards
    JNM

    Dear JaganNM,
    While creating the billing document in VF01 the billing date will be changed manually by the user.
    This change will not applicable in sales order.
    Once you save the billing document you can't change the billing date in sales order ,it will be graded out.
    Before saving the billing document only the date can be changed in sales order.
    Let me know if you have any further clarifications.
    Thnaks&Regards
    Raghu.K

  • Changing proposed delivery date in sales order for one specific sales org

    Hi All,
    I want to change proposed delivery date in sales order automatically for one specific sales org only without changing lead time in VOV8.
    For that can I use MV45AFZZ. But it is asking access key to make changes. Is there any other user exit for the same. And how does exactly change it.
    Thanks in advanced.
    Points will be awarded.
    Regards,

    EXIT_SAPFV45E_001 has nothing to do with this - it is meant to update the purchase order from a sales order. It might not even be triggered if the sales order has no link to a purchase order.
    USEREXIT_SAVE_DOCUMENT is not really good for this either, because the delivery date has to be changed before that. If memory serves, it also influences the schedule lines and probably the ATP check and such. I would strongly advise against it. One of the other routines in MV45AFZZ should do just fine, USEREXIT_MOVE_FIELD_TO_VBAK for example.

Maybe you are looking for

  • Itunes doesn't open now and apparently I need Quicktime 7.5.5 all of a sudden?

    I recently had to replace my hard-drive as my previous one was howing signs of failing.  I formatted the drive and installed all necessary software. As expected the messages 'Updates were found' so I did these updates as I've done many times before w

  • Mac Mini (mid 2011) Display Issues

    Hello. Recently I started having some issues with the display from my Mac Mini (mid 2011, core i7, 8GB, OS X 10.9). During usage the screen started flickering erratically and then went blank. I turned the Mac off and found that it was very hot so I r

  • ODS activation failing with the reason : ODS not built properly"

    Hai,          I have a process chain wherein I have an ODS thats being loaded and activated. The problem is that the load is successful but the activation is failing. When I see the process monitor, it says "DataStore ZXXXX built incorrectly; cannot

  • My top ten requested features for Flash Catalyst Next

    Here is my top ten list of requested features for Flash Catalyst: 10. Rearranging of pages / states in the pages / states panel (also resizing to smaller icons) 9. Menu bar option to Insert Custom / Generic Component. There isn't a  way to create a c

  • Adding a ASP Search to a Dreamweaver Site

    I have just created a basic HTML website using Dreamweaver CS3. It is just a series of link pages with various documents on each page. I used a vertical Spry navigation menu. This is an intranet site for the company I work for and as such will reside