Capacity cumulation in work center hierarchy

Hello
Does anyone uses workcenter hierarchies to cumulate capacity requirements ?
I've created a hierarchy but in the capacity evaluation transaction cm01,
the capacity requirements are not cumulated from the underlying work center.
Instead a capacity requirement of zero is shown on the hierarchy work center.
Is there any specifics to cumulate the capacity requirement to work center hierarchy header
Best regards
Pascal

Hi,
  In the transaction CM01, choose the pull-down menu Settings-> General. In the pop-up screen, under the "Herarchy" tab, select the check boxes "Cumulation of reqmts" and "Dyn. capacity cumulation", choose the "Hierarchy" and "Plant" and click on "Continue".
Now the "Available Capacity" will be as per hierarchy setup and Rem. avail cap = Reqmts-Available capacity.
Hope this solves the requirement.
-Thaila Shree

Similar Messages

  • Capacity planning at Work center Hierarchy level

    Hi,
    I have created Work center Hierarchy, now want to see the cumulative capacity of subordinate work centers at Superior Work center level, but using cm01- std overview, i can't see.
    Can anybody tell me , what-ever is missing?
    with thanks,
    Rasika
    9869028103

    HI Mangalraj,
    Thanks for your reply. I had tried that , even though there is no cummulation done.
    System is showing same error ,as 'There are no capacity requirements for the
    selection and settings'.
    what i have given input is Superior Work Center, Plant and Planner group.
    I didn't mentioned the capacity at superior WC.
    PLEASE HELP.
    Rasika.

  • Work center Hierarchy

    Dear Gurus,
    How can I use work center Hierarchy for Capacity Planning.
    I have 5 Lathe machines. How can I use Work Center Hierarchy?
    I also need  Work Center Wise confirmation.
    Please guide me. Also let me know how should I maintain data in work center as well as in routing.
    Thanks in advance
    RG

    Create a new WC (in CR01) as category 0004. This will be the top level WC in your hierarchy. <BR sab="44">Create a hierarchy (in CR21). <BR sab="46">Add your 5 lathes and the newly created top level WC to the hierarchy (in CR22). This can be tricky: the WC you just created must be the top level, the other 5 must be under it. <BR sab="50">Pull the capacity data (in CM01) for the hierarchy: go to settings, hierarchy, check the cumulation of requirements and capacities and type the hierarchy name. <BR sab="54">Route things as before, to the original 5 lathes.

  • Work Center Hierarchy and Routing

    Hi,
    I would like to know what exactly Work Center hierarchy mean?. Where is it used. In Routing, we maintain Sequence of operation along with workcenter where this operations are performed . Would like to know does work center hierarchy is linked to sequence maintained in Routing?. Thanks

    Hi,
    Any one can explain me the use of Workcenter Hierarchy?. In Routing, we maintain the sequence of operations. Does Routing and Workcenter Hierarchy has relation?. If Yes, what is the relation between these 2.
    Thanks in advance

  • Work Center Hierarchy and Capacity

    Hello SAP friends,
    Can someone please help me with the following scenario?
    I have 3 Work Centers
    MAQ00 - (Capacity 10:00 x 2)
    MAQ01 - 8:00 -- 18:00 (Capacity 10:00)
    MAQ02 - 8:00 -- 18:00 (Capacity 10:00)
    I have a hierarchy
    HICY01
    MAQ00 - Root of hierarchy
    |_ MAQ01
    |_ MAQ02
    Then, I have a routing
    10 - PP01 - MAQ00 - 1H
    20 - PP01 - MAQ00 - 2H
    If I go to CM01 for Work Center MAQ00 I can see the capacity and requirement, where:
    Capacity: 10:00 x 2
    Requirement: 3:00
    But if I go to transaction CM21 for Work Center MAQ00 the capacity and requirement is not correct. Can someone please help me with this?
    Thanks in advance,
    Adelmo Silva

    Hi,
       CM01 will give the cumulative requirement as 3 hrs but CM21(Gradhical View) shows the individual spread of oprn. 10 and 20 as 1H and 2 H resp.
    Does the above help you?
    -Thaila Shree

  • Regarding work center hierarchy

    Hi all,
    I have 2 work centers liked to a superior work center in a hirarchy.
    Is it possible to do capacity planning at the superior work center level.
    The scenario is like this - I will get planned order at a superior work center level. I will  convert the planned order into 2 production orders with child work centers in respective order.
    Now I want that, when I see the capacity overview for the superior work center, it should be full. That means I want to link the capacities of the child work centers to the parent work center. 
    Please let me know if it is possible ?
    Regards,
    Yogesh

    Hi,
    Work center hierarchies are used in capacity planning to cumulate available capacity and capacity requirements. You can cumulate available capacities from subordinate work centers to a superior work center level in order to determine the total available capacity for the superior work center.
    In your situation, I think you need to create two planned orders with the two work centers and after this you will be able to see the capacity requirements cumulated at the superior WC.
    Regards
    Datta

  • FM for getting the capacity of given work center

    Hi all ,
    1) Is there any function module to get the capacity of the workcenter .
    2) how to know the number of hours that work center works .
    Please mention the field which represents the capacity .....
    Regards
    Raj

    Hi ,
           You can use .
    CHEeck out Transaction C0R4 .
    Field is BEDID .That is Capacity Id in table KBED .
    BEDID is there in table AFKO or AFPO .

  • Capacity Leveling of Work Center

    Hi all,
    I have a problem with Capacity of Work center (WC).
    I have a Internal Activity, and i assigned a WC for this Internal Activity. WC's capacity is 100H/day for 1 number of element.
    Work of this WC is 250H, duration 5 days, number of element 1. Default capacity of this WC is distributed by Distribution Key define in Activity. . And they are divided equally between factory days in 5 day. That is capacity requirement is 50H/Day
    So, i want to edit this WC's capacity following value:
    Day 1: 100H/day
    Day 2: 50H/day
    day 3: 0H/day
    day 4: 0H/day
    day 5: 100H/day
    How can i do it?? I try to use Dispatch Manually but i cant solve this problem.
    Please help me for this case.
    Thank all.
    NLQ

    Dear
    Capacity leveling depends on some of the basic set up of Capacity Requirement Planning .You need to have proper CRP set up frist .
    Couple of check points : -
    Did you work centre is relevent for finitie scheduling in CR02-Capacity Header and wht is the over laod percentage for work centre ?
    Did you have Capacity Requirement Related Set up like Over all profile , time profile , Startegy Profile -OPD0?
    Did your Capacity Check -OPJK -Order Control at order level are active for availibilty Check 1 and 2 and assinged Over all Profile ?
    Set up :
    1.Please assing a operation control key like PP01 where Details Capacity Check and scheduling is active .
    2.In CR02-Work centre -Capacity Header -You should have Follow check box marked
    1.Releven for Finitie Scheduleing
    2.Can be used for multiple Operation
    3.
    3.OPU3/OPU5 -Define Scheduling paramter -Mark Scheduling and Capcity Check for planned order or production Order
    4.In SPRO -Shop Floor Control-Define Production Scheduling Profile -You need to matian the relevent Parameters like
    1.Schedueling Automatically 2.Scheduling Log 3.Adjust Scheduling -Basic date , Depedent Requirement date 4.Scheduling Type -Backward etc .
    These are all basic level set up beside CRP overall profile and other profile like strategy /time etc which may in place as you are analysing in CM01.
    Please find below some of the useful CRP details : Refer this threads which are self explaintory :
    http://help.sap.com/saphelp_47x200/helpdata/en/8a/a5a3154adc11d189740000e8322d00/frameset.htm
    http://www.scribd.com/doc/17026521/SAP-ECC-60-PP-Capacity-Planning-httpsapdocsinfo
    capacity planning
    http://help.sap.com/printdocu/core/print46c/en/data/pdf/PPCRPSFC/PPCRP_SFC.pdf
    Capacity Planning
    capacity requirements planning
    How to dispatch operation to do Capacity Leveling at Work Centre Level :
    1.Frist Check the  over load at work centre . Goto -CM07/CM05-give plant only -then hit the Stnadard view -You will find weekly or daily baiss load ( Requirement , Avaliable Capcity , Overlaod etc )
    2.Check the week in which days you are tring to dipatch -if you selet the week check box and double clik it will show u all the dataiul load .Basde on the available capacity in other week-days u need to dipatch in CM22/CM31  or CM25/CM21
    While dipatching in CM22/CM31-Select the Stragegy button on the top header -Mark Date entry when dispatching  so that when you select the operation of any production order or planned order for certain work centre , it will pop with window having information of Date , Work Centre , Time .Onec you did this you will receive Scheduling log with certain information .
    Hope this helps
    regards
    JH

  • Inspection time Capacity Updation in work center for skipped lots

    Hi Guys,
                 I am using in process inspection type 03 along with DMR criteria at lot level i have defined the DMR rule and assigned it in routing header.DMR rule is inspection lot 1 in 5 will be inspected i.e when the inspection lot will be created and if there is no quality level exists it will first create the quality level with 1st inspection lot which will not be skipped lot and then it will skip next 4 lots and 5th will be inspected again.Quality level is updated during lot creation level.
                 what i am looking is when you have the skip inspection lot he capacity which has been planned for inspection for that work center should not be considered since there is no inspection done because of skipped inspection on that work center although it's the part of Routing/production process.
    please let me know if any more inputs required.
    your inputs/feedback is really appreciated
    Regards
    Ashutosh Shende

    Hi Krishna,
    It is distributing unevenly because of the Int. Dist. key maintained for "Labour" capacity category.
    Following are the available dist keys.
    I think for your scenario, you should select SAP020
    SAP000     Overall load for latest start date
    SAP010     Overall load for earliest start date
    SAP020     Equal distrib. earliest dates, fact.cal.
    SAP030     Equal distrib. latest dates, fact. cal.
    SAP040     Equal distrib. latest dates, discrete
    SAP050     Equal distrib. earliest dates, oper.time
    SAP060     Equal distr. latest dates, operat. time
    SAP070     Overall load at latest finish date
    Please let me know if this works for you.
    Regards,
    Abhay Kapase

  • Capacity planning for Work Center

    I programmed time for a Work Center on internal activity, for 40 hr using 100% of one resource, the work center it has  a capacity of 8 hr each day, the activity gets a duration of 5 days and I indicated that it has to begin the first day of the next month.
    When I executed transaction CM01, I notice that the 40 hours are planned for the actual day and don´t respect the dates of the internal activity, I think it is a problem with the work center but do not find the error.
    Any suggestion where to look for?
    The data used for creating the Work Center on Capacities:
    - Capacity Category : 002 Person
    - Other formula: SAP008
    The data used for capacity:
    - Base unit of meas.:H
    - Start: 08:00:00
    - Finish: 17:00:00
    - Capacity utilization: 100
    - No. of indiv. cap.:1
    - Unit: H
    - Relevant to finite scheduling: active
    - Can be used by several operations: active
    - Long-term planning: active
    The data used for creating the Work Center on  Scheduling:
    - Capacity Category: 002 Person
    - Other formula: SAP004
    - Work dimension: Time
    - Work unit: H
    Best Regards...

    Hi,
    Please activate the capacity requirement in Capacity tab in CNR2.
    Thanks..

  • Why ist Pool Capacity from PP work center automatically involved

    Hi, All
    i use PP work center to create a PM Order.
    this PP work center has machine-, labor- and pool capacity. and I add "SAP008" into field "other fomula" for labor capacity in Tab capacities.
    now after I create a PM Order, when I check CM50, I can see for this PP Work center also  Pool Capacity involved.
    Question:
    1. where comes this Pool capacity, even though I didnot set  any formula in field "other formula" for pool capacity in Tab capacities?
    2. for creating PM Order, do I also need add "SAP008" into field "other fomula" for machine capacity in Tab capacities?
    thanks&regards

    Hi Shrithar,
    Do you means the time Profile in CM50.
    when I check this time Profile, I see differant time interval, -Database read period
                                                                                    -Evalution period
                                                                                    -plannung period
                                                                                    -Dispatching of backlog
    is it also influencing work center capacities?
    thanks&regards

  • Capacity evaluation in work center which has number of indivisual capacity.

    Hi. guys.
    Work Center(WC01) has 2 indivisual capacity.
    and available capacity is 16H.  (8H * 2)
    I made capacity requirement(production order)  with 26H.
    Capacity evaluation displays the result as below.
    Entries        Rem.cap.reqs      Avail.capacity   R
    Total                       26 H            1,632 H
    2009.10.09               0 H               16 H     0
    2009.10.10               0 H               16 H     0
    2009.10.11               8 H               16 H    50
    2009.10.12               8 H               16 H    50
    2009.10.13               8 H               16 H    50
    2009.10.14               2 H               16 H    12
    2009.10.15               0 H               16 H     0
    I don't know why the requriment capacity is only 8H per day.
    I think that the requirement capacity should be 16H per day.
    can anyone explain the reason?

    Thanks.
    But  It's not what i want.
    I'll explain my problem more detail
    Work Center(WC01) -  Available Capacity: 16H   ( 8H * 2 (No. of Indivisual capacity))
    Caracity Requirement -  production order 1000001 (Start date: 10/10,   Excution Time:  24H)
    Capacity Evaluation (CM01)  <NOW.>
    Day        Requirements    AvailCap. CapLoad 
    2009.10.10         8.00        16.00    50%
    2009.10.11         8.00        16.00    50%
    2009.10.12         8.00        16.00    50%
    So, I don't understand 'capacity load(%')
    I want to product the material using two capcity
    but capacity evaluation calcuate only one capacity now.
    I think the below result is right.
    Capacity Evaluation (CM01)  <NOW.>
    Day        Requirements    AvailCap. CapLoad 
    2009.10.10        16.00        16.00    100%
    2009.10.11          8.00          8.00      50%
    2009.10.12          0.00          0.00        0%
    Is it impossible??

  • Capacity categories in work center

    Dear PP gurus,
    I have a work center where i have maintained 2 capacity categories in capacity tab screen. One m/c and other labour. Now when i assign this work center to a routing.....in the routing operation details screen, i see only the formula from the 1st capacity category showing up. How/Where can i see the formulas from the other capacity category, maintained in the work center?

    Hi,
      For the capacity category say:Machine, in the "capacity header" in workcenter, you assign "no. of individual capacities" as 2. Also, you can create the capacities in CR11 and assign the same to the work center.
       In routing you can just enable the check box "Required splitting" and assign no. of splits =2. you cannot assign the individual capacities you have created in CR11 in routing.
      In Production order, in operation details, "Cap. reqmt assignment", you can assign those two individual capacities and assign qty to be processed in those capacities.
       Hope this clarifies you..
    -Thaila Shree

  • Upload/ download Work Center Hierarchy

    Hello All,
    I need your help with this one. Therefore thanks in Advace:
    Is there a way to download and upload work center hierarchies?
    The idea ist to download a complex hierarchy to a file and then upload it to another system/ client.
    Thanx
    Raf

    Hi Daniele,
    I just tried  the way you suggested:
    - RCRAPDX1 downloaded a txt to presentation server with data.
    - changed only the plant in file.
    - run RCRAPDX2
    unfortunately result is that ths system try to maintain the work centers within the file,
    (which are already maintained).
    The hierarchy structure won't be maintained.
    So what I look for is a manner to transport the complete hierarchy structure...
    regards
    raf

  • Capacity category in work center

    Hi All,
    please clarify me on this,
    capacity category under scheduling tab in work center creation is showing as mandatory, but i do not want to maintain this field because iam not putting anything under capacity tab to avoid capacity planning.
    is there anyway to take off it as mandatory under scheduling tab?

    Dear Sprint,
    Goto OPFA and select the scheduling and click on influencing and mention the work center category in the field contents and
    press enter and for the field capacity select the radio button for input or else display (remove it from the radio button mentioned
    under required) and press enter and then save the data and now create a new work center for the changes made work
    center category and revert back.
    Regards
    S Mangalraj