Capacity planning: capacity available at all workcenters

Dear all,
We have configured all the requirement for capacity availability check. the planned order is showing overload of capacity. but while doing conversion and checking in production order i am getting "capacity available at all work centers, which is actually overloaded.
Can anyone suggest how to resolve this?
Regards,
Sharmila

Sharmila,
I will assume this is a new implementation.  Have you calculated the basic load yet?
http://help.sap.com/erp2005_ehp_06/helpdata/EN/60/13e30b133a11d3bf550000e83235ee/frameset.htm
http://help.sap.com/erp2005_ehp_06/helpdata/EN/60/13e314133a11d3bf550000e83235ee/frameset.htm
Best regards,
DB49

Similar Messages

  • Capacity availability check

    Hi All,
    I need to check the capacity availability for a person who assigned to workcenter which is assigned to the activity in the network. I maintained the cap.planning profile for network order type.
    I have created 2 activity under the same network and assigned the same person to those activities. If i do check the capcity it always saying ALL THE CAPACITIES ARE AVAILABLE.Eventhough there is a capacity overload.
    PLease tell me what i shall i do...
    Thanks

    Hi ALl,
    I want to do capacity availability check for network. can you please explain waht are all the steps to be followed.....
    Thanks

  • HT4623 why does my ipad kick me out of FB and sometimes to the 'settings' page or sometimes to the desk top, for what reason?     I have 50.8 GB of capacity available; it is version 5.1.1 and model MC497LL.   it is WIFI and internet via AT&T???  Can you h

    Can anyone help me?  Why does my ipad kick me out of FB?  Sometimes to the 'settings' page and sometimes to the desk top?  I would like to know why this happens and what I can check or change to make it stop.   I have 50.8 GB of capacity available; it is version IOS 5.1.1; model MC497LL.  It is WIFI and internet via AT&T?   Can anyone give me some clues on what to do; or change in settings???  Thank you very much! 

    Please read this whole message before doing anything.
    This procedure is a diagnostic test. It’s unlikely to solve your problem. Don’t be disappointed when you find that nothing has changed after you complete it.
    The purpose of the test is to determine whether the problem is caused by third-party software that loads automatically at startup or login, by a peripheral device, by a font conflict, or by corruption of the file system or of certain system caches.
    Disconnect all wired peripherals except those needed for the test, and remove all aftermarket expansion cards, if applicable. Start up in safe mode and log in to the account with the problem. You must hold down the shift key twice: once when you turn on the computer, and again when you log in.
    Note: If FileVault is enabled, or if a firmware password is set, or if the startup volume is a Fusion Drive or a software RAID, you can’t do this. Ask for further instructions.
    Safe mode is much slower to start up and run than normal, with limited graphics performance, and some things won’t work at all, including sound output and Wi-Fi on certain models. The next normal startup may also be somewhat slow.
    The login screen appears even if you usually login automatically. You must know your login password in order to log in. If you’ve forgotten the password, you will need to reset it before you begin.
    Test while in safe mode. Same problem?
    After testing, restart as usual (not in safe mode) and verify that you still have the problem. Post the results of the test.

  • Reg Capacity used and capacity available

    Dear all,
    How can I see the capacity available and capacity used for a particular resource for previous month , is there any standard report available in standard SAP.
    Regards
    madhav

    Try transaction MCP7

  • ATP based on material and capacity availability

    Hi Experts,
    Is there a way to implement ATP with finite capacity availability and material availability in a Make to stock (MTS) environment in R/3? In other words, when a sales order is created for a material, the confirmation date that is recd. should be based on Capacity and Material availability. What planning strategy would you use?
    I understand that this can be implemented in assembled to order environment (planning strategy 82 or 83), but my question is more related to MTS environment.
    Regards,
    Praveen

    Hi Praveen,
    SAP recommends APO as a solution for your scenario.  Check out their documentation on Capable to Promise (CTP) under
    http://help.sap.com/saphelp_scm2007/helpdata/en/64/7294375960a42be10000009b38f8cf/frameset.htm
    This is not a trivial implementation.  You need to be sure that this is what your business wants before you embark on the change.
      Regards,
      Bruce

  • Capacity availability check during prod order creation

    When i create many  production order for a particular material with different huge quantities , while doing capacity availability check system issues a message *" No reqmts/caps exists or not relevant to finite scheduling*
    Here as per the message i have checked all the possible errors and everything is fine.
    As per actual requirements, work centers are overloaded. But here system displays that all work centers are available.
    Any help regarding this.

    Dear Nandi,
    Please refer the below link,
    No reqmt/capacity exist or not relevnt for finite scheduling: Mesage: CY298
    Regards,
    Sundhu

  • Auto Material & Capacity Availability check when releasing Production Order

    Dear Experts,
    Is there any configuration in Production Planning that will automatically check material availability and capacity availability automatically when a Production Order is released?
    Meaning to say, users will not need to manually click on the Check Material Availability and Check Capacity Availability button.
    Please advise.
    Thanks in advance.

    Hi,
    I've solved the problem. Just maintain the config in transaction OPJK.
    Thanks

  • Capacity availability

    HI Friends,
    i am facing a problem in capacity planning, while checking capacity for an order i am receiving the following error. i have given SAPSFCG015 (SFC: Evaluation, standard overview) as the overall profile in production schedular profile and in availability check, checking control. please give solution  
    The profile entered for the capacity availability check is not suitable
    Message no. CY297
    Diagnosis
    The control profile for the overall profile in the capacity availability check has not been correctly defined.
    Procedure
    Correct the control profile as follows:
    presentation: 4 (capacity availability check)
    layout type: 1 (display per period).

    Check your settings in transaction OPJK
    Note 160613 explains them.
    best regards

  • System status for capacity availability in Process order

    Hi,
    I have activated the capacity availability check in SPRO to have a capacity check while process order  creation.
    But system doesnt provide any status in the process order for this. No status is appearing even  if I do a manual capacity check in process order.
    Is there any system status for capacity is available?.
    Thanks in advance
    Prathib

    Hi Prathib
    System will be give any status if capcity is available, but it will give a status MSCP if there is Capacity shortage.
    Rgds
    UK

  • Need a program that will save the capacity settings for all storage bins

    Hey all,
    I would really apprecaite any help with a program I am trying to come up with.
    What I need to do is create a program that:
    1. Will save the capacity settings for all storage bins to
    a file
    2. Then update them all to allow unlimited capacity BUT be able to revert back to the
    original that was saved.
    Any suggestions about possible existig reports that I may be able to modify to suit my needs, or where to start from if I have to do this from scratch?

    I know I'm talking about expensive apps, but having been in prepress for about 30 years now, I really don't look at anything other than Quark XPress or InDesign for page layout apps. Your printing vendor will also be much happier with you when you use these products. Some areas of the U.S. tend to be mostly Quark oriented; others, InDesign. Ask your vendor what they would prefer, and if there are any free or cheap alternative apps they'll accept documents from.
    Apple's Pages app (part of iWork) is a decent page layout program, but hasn't been updated in four years. It also doesn't support CMYK. If you place a CMYK image in the app, it will export out an RGB version of it. Not good! You can work with RGB images if you prefer, but your CMYK translations will be left to the skill of the print shop you use to do the conversions.
    Don't even think about using Word. It has what it calls a page layout option, and does pretty much work like one, but there's no good way to import it into a real layout app such as InDesign. You end up paying the printer for their time to rebuild your entire project in either XPress or InDesign so they can actually do something with it.

  • Query of capacity availability

    hi experts,
    I am testing capacity availability check when release work order,
    I have done configuration to active this function by T-code:OIOI,
    but when release the order, a dialogue pop up
    No reqmts/caps exists or not relevant to finite scheduling
    and the help text is that:
    No reqmts/caps exists or not relevant to finite scheduling
    Message no. CY298
    Diagnosis
    In the capacity availability check either no capacities were found or none were found that were relevant for finite scheduling or no capacity requirements were found.
    The possible causes are:
    no capacities have been assigned to the work centers checked
    in the capacities at the work centers checked the indicator Relevant to finite scheduling is not set. Thus the capacities can have an unlimited load.
    no capacity requirements exist for the order checked
    System Response
    The capacity availability is checked.
    Procedure
    Assign capacities to the work centers affected by the order.
    Set the indicator Relevant to finite scheduling at the capacities in the work centers affected.
    Find out why no capacity requirements exist and, if possible, solve the problem.
    Carry out the capacity availability check again.
    I have checked my work center, I have assigned capacity to work center, and marked the finite scheduling indicator in capacity head screen.
    can anyone give some suggestion?
    thanks

    Hi,
    Did you maintianed the Release order condition in OIOI transaction? Pls maintain one of them. And the No check in capacity window of OIOI must be un selected.
    And in work center did you maintain the number of capacities. If so it should work.
    Regards,
    N.Nagaraju

  • ECC Plan Resource Availability is Considered before Component is Available.

    Hi All,
    We have an issue with GOP and ASCP Resource Availability.
    We are using ECC plan with 'Calculate Resource Requirement' option enabled. Current version is R12.1.1
    Issue:
    Component and Resource together are required to make a subassembly.
    Component is available on 31st August. For example, resource will be used only after 31st of August as component is not available before that. GOP/CTP is considering resource availability before 31st of August (before the component is available). Resource availability is being calculated from plan run date.
    What we expect:
    Since component is available on 31st of August, resource (which is available 8 hours per day, 6 days a week) should be used from 31st of August and thus should give us completion date somewhere in first week of October (for 207.816 hours requirement of resource: 26 working days, after 31st of August) for subassembly.
    But the resource capacity availability is being considered from current date and since there is no other demand, the resource availability from today is being considred. We want the capacity to be considered from the component availability date.
    Did anyone encounter this problem before or this is an intended functionality?
    Your help is highly appreciated.
    Thanks.
    Vijay
    Edited by: user10836534 on Jun 1, 2010 5:50 PM
    Edited by: user10836534 on Jun 1, 2010 5:51 PM

    Hi Partha,
    Thanks for the reply. The resource availability is not just visible but also used by ASCP in calculations.
    For example in our case we have resource availability of 8 hours per day and inverse usage is 100 items per hour for a subassembly, there is no other demand, no supply. Subassembly lead time is 1 day. The component for the subassembly is available 12 days from today. For ATP inquiry of 8000 qty of the subassembly, the available date should be 23 days from today (Component available on 12th Day, and starts processing 800 qty per day for the next 10 days for a total qty of 8000 + subassembly lead time of 1 day).
    The ATP inquiry is suggesting availability of subassembly as 13th Day from today. Pegging shows resource requirement of 80 hours and this is shown available 10 days from today. Component is available on 12th day and it takes 1 day for the subassembly completion.
    ASCP is using resource availability from current date even if this resource cannot be used until the component is available.
    Any thoughts on this?
    Thanks.
    Vijay

  • My IPad 2 16 GB is showing only 3.4 GB available, but all my APPS only total 3741 MB.   Any ideas?

    Why is my ipad2 (16 GB) only showing 3.4 GB available when all of my APPS only total 3741 MB?

    iPhone, iPad, and iPod: Understanding capacity
    http://support.apple.com/kb/ht1867
    How much space is used by your Other? You may be able to reduce.
    How Do I Get Rid Of The “Other” Data Stored On My iPad Or iPhone?
    http://tinyurl.com/85w6xwn
    How to Remove “Other” Data from iPhone, iPad and iPod Touch
    http://www.igeeksblog.com/how-to-remove-other-data-from-iphone/
    With an iOS device, the “Other” space in iTunes is used to store things like documents, settings, caches, and a few other important items. If you sync lots of documents to apps like GoodReader, DropCopy, or anything else that reads external files, your storage use can skyrocket. With iOS 5/6/7, you can see exactly which applications are taking up the most space. Just head to Settings > General > Usage, and tap the button labeled Show All Apps. The storage section will show you the app and how much storage space it is taking up. Tap on the app name to get a description of the additional storage space being used by the app’s documents and data. You can remove the storage-hogging application and all of its data directly from this screen, or manually remove the data by opening the app. Some applications, especially those designed by Apple, will allow you to remove stored data by swiping from left to right on the item to reveal a Delete button.
    What is “Other” and What Can I Do About It?
    https://discussions.apple.com/docs/DOC-5142
    iPhone or iPad Ran Out of Storage Space? Here’s How to Make Space Available Quickly
    http://osxdaily.com/2012/06/02/iphone-ipad-ran-out-of-available-storage-space-ho w-to-fix-quick/
    6 Tips to Free Up Tons of Storage Space on iPad, iPhone, and iPod Touch
    http://osxdaily.com/2012/04/24/6-tips-free-up-storage-space-ipad-iphone-ipod-tou ch/
    Also,
    How to Clear Message/iMessage Cache on iPhone & iPad And Reclaim Lots of Free Space
    http://www.igeeksblog.com/how-to-clear-message-imessage-cache-on-iphone-ipad/
    What is Stored in iCloud and What is Not
    https://sites.google.com/site/appleclubfhs/support/advice-and-articles/what-is-s tored-in-icloud
     Cheers, Tom

  • Distribution of Available Capicity at Workcenters

    Dear Guru's
    We are facing problem when issuing Production Order on the basis of Current Date.
    The proposed date is calculating on the basis of only 1 shift & 1 machine. While we
    have 5 machine at a same workcenters. for e.g capcity of 1 machine is 30,000 units
    & we have 2 machine so available capicity is now 60,000 units. When we issued production
    & check the capacity avail & req qty. It shows like this ..
    Date Req Qty Avail Capicity
    15.09.08 30,000 60,000
    16.09.08 30,000 60,000
    We want to utilize full available capicity in a same day. The distribution % of capicity is 100%.
    Can any1 answer plz?
    Regards,
    RM

    Hello Rasid,
    What i have understood is you have created two production orders, the second order scheduled in next day, even though the previous day have enough available capacity.Since u have assigned no of spilt , lead time of order  should have been reduced. Now u have to reschedule the second  production order to previous day.
    In that case do the  capacity leveling for second order at Cm21/CM25. Before that activate finite scheduling check box at capacity header of the workcenter  for which  Prod order created.
    Then check with  capacity overview at cm01.If  i am wrong   please explain with examples
    Regards
    Pradeep

  • Explain plan not available in dba studio

    Hi, guys,
    Why the explain plan not available in my dba studio with a message like this "explain plan not available for this sql statement. ora-02195: attempt to create permanent object in a temporary tablespace"
    Another question: I can use "set autotrace on" to trace sql statement in sql*plus window. But the final execution plan come up without those thing like cost, cardinality but only the steps
    Thanks for your help
    jim

    Was this a trace started on an already running task? Was the trace stopped before the task completed? Did the trace file reach its set size limit before the task compled?
    In all three cases above you would have cursors that were not closed and stats information not written to the trace file resulting in incomplete data for some SQL.
    HTH -- Mark D Powell --

Maybe you are looking for

  • IChat no longer connecting to Jabber server after Leopard upgrade

    Just upgraded to Leopard yesterday, and the only significant glitch I notice so far is that iChat is now getting stuck in the "Connecting..." step when I try to get onto our Jabber server (which was working fine before the upgrade). Am now getting a

  • BDC- problem in uploading more line items

    Hello friends, I am using BDC to upload data for TXN ME31L. At item level I am able to upload only 15 records. After that it gives error. While doing recording i have entered items only for two material  So can anyone help me? What i think is after 1

  • Question on QoS for File-- SOAP synchronous high volume interface

    Is it possible to have a File to SOAP (sender file adapter --> receiver SOAP adapter, synchronous - response needed by sender ) scenario with FIFO (first in first out). This is a high volume interface (about 8 messages/second). If FIFO possible, will

  • Date pick calender error

    Dear Experts, We are using SAP B1-2007 PL 42 and occurred following error. When I click the date picker in any form (window) [ex:-Sales Quotation, SO, etc....), it shows only 4 days of the week. It hides rest of 3 days (Friday, Saturday, Sunday) in e

  • Gamers Club Unlocked activation problem

    I bought this membership card from ebay few days ago. On the back it says "Redeemable through 1/31/2015". Though today I went to a Bestbuy store and tried to have it activated, but they said it's the "older version card" and their machine can't scan