Hello All,
Am trying to configure CHARM in our SolMan system. I referred to the below link for configuration.
/people/dolores.correa/blog/2008/07/26/first-steps-to-work-with-change-request-management-scenario
I am trying to create a project under tcode: SOLAR_PROJECT_ADMIN
while creating project with in SYSTEM LANDSCAPE tab we can see FOLLOWING
SYSTEMS /\ CENTRAL OBJECTS /\ IMG PROJECTS .
But am unable to see CHANGE REQUESTS tab which should be at last in the above mentioned sequence .
can any 1 tell me why its not there. Do i need to configure anything more to get the CHANGE REQUESTS tab
Regards,
Ravi

Hello,
i had the same problem few weeks ago. I couldn't find the Change request Tab in Solar_project_admin
I fixed it by following : SAP note : 802793
The note explain how to re assign the client to manage change request management.
We folow the note, then the missing tab appear
Regards

Similar Messages

  • Change Request TAB Missing in SOLAR_PROJECT_ADMIN  - CHARM

    Hi All,
    We are in process of configuring Chage Request Management(Charm).we created a maintenance project and added the ogical component.but unable to activate charm. because the  CHANGE REQUEST TAB is missing.
    We have followed the steps in SPRO and also followed the NOTE : 903527 except importing the picelist attached but still unable to see the TAB. Our SOlution Manager is at EHP1 sps 2
    Reddy

    Hi
    Have you activated this bc set and performed in the initial basic settings in SPRO.
    SOLMAN40_CHARM_BASICFUNC_001
    check this blog
    /people/dolores.correa/blog/2008/07/26/first-steps-to-work-with-change-request-management-scenario
    Regards
    Prakhar

  • No 'Change Request' Tab in Solar_Project_Admin

    Hi,
    I am trying to implement Change Request Management with SolMan on an  Implementation Project.
    I performed different tasks like:
    - RFC connection creation (client 000 & Other mandant)
    - Logical Component creation
    - Project creation with SOLAR_PROJECT_ADMIN
    - Clients are defined properly
    I am not sure about the TMS configuration
    My issue is that i do not have the tab 'Change request' under 'System Landscape' in the transaction SOLAR_PROJECT_ADMIN
    And i would like to know why this tab is missing ?
    I would really appreciate some ideas, advices, please
    thank you

    Hi,
    I solved my issue with the missing "Change Request" tab by applying the note 802793.
    But, since i performed this action, i faced other issues when trying to create a Task List in the "Change Request" tab:
    - Warning : Probleme occured during synchronization of the system landscape
    Then
    - The project is not released. Hence cycle can not be created
    We checked :
    - RFC connections including Client:000 of all the systems
    - Authorizations on SolMan himself and in Satelites systems
    - I found interesting notes like :Note 883981 - Project consistency check which matched our issue, finally the system (with "snote") told me that it could not be apply)
    - Patch, SP up to date
    We have an error :
    - System cancel RFC destination SM_XX1CLNT000_READ, Call TMW_GET_TARGET_SYSTEMS: Function Module " TMW_GET_TARGET_SYSTEMS not found
    - Communication Error, Check the RFC Destination
    For sure, we checked every RFC Connection, everything is Green.
    That is the problem, check by check everything seems to be OK, but finally i still have blocking errors. i'm a little bit lost
    I think it could be an issue with the Transport Routes....but i'm not an expert.
    If anybody could help me please,
    Thanks in advance

  • Project - Change Management Tab missing

    Hi Guys
    After renaming a test Solution Manager, which is a copy from an existing System, Change Management Tab is not visible in the a Project Attributes.
    Before the SID renaming, the tab was visible, but after chaning the name to SMT, it no longer appear.
    When accessing  SOLAR_PROJECT_ADMIN transaction, under System Landscape, there are only three tabs instead of four
    Some logical relation is missing? Any idea where can I verify why?
    Thanks!
    Copied and Renamed system (SMT) with SOLMAN_ADMIN, client 200
    Original System (SSM), user SOLMAN_ADMIN on Client 200

    Hi,
    as you copied the system, probably there is a missing entry which defines the client in which ChaRM will be active. Check in SPRO below "Change Management->Basic Configuration" the IMG activity "Activate Integration with Change Request Management->Activate Change Request Management and Set-up client". It must have your client 200 specified.
    Regards,
    Raquel

  • Personnel Change Requests option missing in MSS

    Hi everyone.  I hope you can help.
    In Manager Self-Service, under the "Team" workset, there should be an iview for Personnel Change Requests:
    http://help.sap.com/saphelp_erp2005vp/helpdata/en/54/957e40ec66ce62e10000000a155106/frameset.htm
    However, nothing is there; and for that matter, the entire "Services" navigation panel seems to be missing, options like:
    Employee Information
    Working Time
    Competency Management
    Etc.
    Anyone know why these options might be missing?

    Found the problem.  Needed to install "Business Package for Common Parts (mySAP ERP)" too:
    https://www.sdn.sap.com/irj/sdn/contentportfolio
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/webcontent/uuid/f068643e-866d-2910-4eb0-8213d2943872 [original link is broken]

  • Why is the import tab missing under the file tab?

    Why is import missing under the file tab? I want to import bookmarks etc. from Safari into Firefox.

    You can find the Import menu entry in the Bookmarks Manager (Library)
    *Bookmarks > Show All Bookmarks > Import & Backup > Import Data from Another Browser
    *http://kb.mozillazine.org/Import_bookmarks

  • Multiple Change Requests for project cycle

    I have a question.. if we have multiple chane requests/documents for a project cycle , how will the project cycle proceed??
    i have two CRs for my implementation cycle , now how should i proceed my implementation cycle, since all the changes are of type SDMJ and i want all my changes to be imported to PRD together??
    Please help

    Hello,
    i had the same problem few weeks ago. I couldn't find the Change request Tab in Solar_project_admin
    I fixed it by following : SAP note : 802793
    The note explain how to re assign the client to manage change request management.
    We folow the note, then the missing tab appear
    Regards

  • Best Practice to process change request

    Hi All,
    There's a confusion of provided functionality by SAP for Change Request Management. Though, through different blogs/articles/book, we have implemented change request management, but initiation process of change request seems missing.
    What I know is project can be tracked through maintenance cycle, if support message is posted through SAP production server through SAP->Help->Create Support Message. What I'm looking for is user should be able to select few parameters of particular forms from forms' repository, available online. Once its filled, it goes to his manager according to Organogram, then a support message gets created automatically, and rest of the process remains same as provided at current by SAP.
    What you guys know of it?
    Thanks
    Nayab

    Thanks Sammi for your confirmatory post.
    So if we need to use required fields for particular configuration from user, say the requirement to develop new company code, of which all required information is maintained in form, the user should submit the filled form, authorized by his manager, to IT department, we then ask the particular user to raise support message and keep a track of such maintenance activity.
    Is it possible to modify Create Support Message screen, that is, another parameter to upload file, as we can do in solution manager service desk mesage -> documents. This might help as well, but I guess SAP must be providing a tool, may be some different product for aforementioned requirement.
    Regards,
    Nayab

  • Change Request Management Configuration

    We are configuring Change Request Management in Solution Manager 4.0 SR2.
    After we have created the maintenance project, assigned our Landscape components as a logical component and created the IMG project for Development system(ASD-315); we have executed a consistency check in Change Request tab of System Landscape tab of the project, and we receive the followong errors:
    1- No consolidation system found for ASD-315 (project XXXXX)
    2- No track for project XXXXXX with log. system ASD/315.
    3- Message from function module /TMWFLOW/CHECK_PRJ_CONS: No export system for ASP-500.
    Additionally, when we are trying to create the maintenance cycle (goin to to the transaction /TMWFLOW/CMSCONF), the "Distribution Routes" tab doesn't appear.
    Any suggests are welcome.

    no answer

  • Two tasks under one change request

    hi all,
    when two tasks will be created under one change request, when using same user id.
    is there any harm having different tasks under one change request?
    is it better to have  different change request for different tasks...
    Thx in Advance....

    Hi
    There is no problem to use like taht.
    you can create any number of tasks of diffrent users or same user under same Transport Request.
    it won't create any problem also.
    you need to transport those tasks with that Transport request.
    individuval taska won't be transported.

  • Default transport under Local change request

    Dear Friends,
    I am trying to transport objects from dev to QAS. i catch hold of the object, create transport request. By Default they are getting assigned to Local Change Requests instead of being assigned to Modifiable requests under target system. (in SE09)
    how can i change the default from local change request to Quality.
    Regards
    Paddy

    Thanks Edwin,
    this is what i am doing now. But, by default i want it to be set in Quality--> Modifiable.
    Everytime going to settings and changing it does not seem to be a permanent solution.
    Request your earliest response.
    Rgds.

  • Solution Manager 3.2 SP 8- Change Request Management Configuration Problem

    Hi friends,
    We are in process of implementing SOLMAN 3.2 SP8 in our landscape.I am facing  problem in configuring change request management.
    When the developer is working on an urgent correction document we are facing a problem.The steps we are following are here under provided.
    Step 1 :
    Selected Action "In development" - > it created the transport request in the dev system.
    Step 2:
    Action "Log into System" -> made correction attached to the transport request manually and released the task.
    Step 3:
    Action "Release transport requests" -> The transport request in the development was released.
    Step 4:
    Went for action "Pass to correction" -> I am facing exceptions which conveys
    Status was reset by system
    A condition is not satisfied because of an exceptional situation
    Not all transport requests yet released
    And we would be thankful if you provide the authorization required for the different roles in the change request management.I have followed the help file of SOLMAN 3.2 and create the users as under
    User - Role
    SOCM_RQSTR - ZSAP_SOCM_REQUESTER
    (Derrived from SAP_SOCM_REQUESTER)
    SOCM_DVLPR - ZSAP_SOCM_DEVELOPER
    (Derrived from SAP_SOCM_DEVELOPER)
    SOCM_CHNGNGR - ZSAP_SOCM_CHANGE_MANAGER
    (Derrived from SAP_SOCM_CHANGE_MANAGER)
    SOCM_CHNGNGR - ZSAP_SOCM_IT_OPERATOR
    (Derrived from SAP_SOCM_IT_OPERATOR)
    Even then I am facing problems while developer creating transport requests and while logging into development system.
    I tried adding S_RFC,S_RFCACL auth objects to their roles but did not help.
    Pl. suggest.
    Thanks & Regards
    Mrutyunjay
    Message was edited by: Mrutyunjay Rao Dora

    Hi all,
    We are trying to implement the Change Request Management piece in Solution Manager 3.2. 
    We are facing the following issues which I think relate to the same reason:
    1)We have created a Maintenance Project in SOLAR_PROJECT_ADMIN and assigned it a logical component, which consists of our two system landscape (namely DEVàQAS). We have also created the IMG project in the DEV system and have distributed that IMG project to both the Solution manager system and the DEV system. Now we have to make the maintenance cycle and task list for that maintenance project, but as we select the project and click on “create project cycle” it shows the message "The project is not released. Hence cycle can not be created". It is showing the status of project as locked .How can we open or unlock the project to remove the error?
    2) Also after selecting the SMI project when we click on the button “CTS status switches” or “project specific Transport route” it responds with the error "Project landscape not configured; set the project status to "open" first ".
    3)When we click on “synchronize single project” it prompts for the login of connected system (Development System) and after login, it gives an error "Warning, problems during synchronization of the system Landscape".
    For Error resolution, we have checked the system landscape and it does not give us any errors. We have done that, both from the solution manager by going to the transaction SOLAR_PROJECT_ADMIN -->  >system landscape tab>selecting our logical component and doing a check by clicking the "Check system Landscape" button. It returns with "no Errors". We also did a check on the TMS configuration by logging directly on to the TMS domain controller system and checking the Transport routes. We have checked the RFC connections without any errors.
    Any help would be greatly appreciated.
    Thanks
    Abhi

  • Unable to edit the form in Personal Change Request

    Hi,
    One of the manager is trying to edit the employees information. When he navigates to edit form of personal change request, under My Crew tab of Manager Self Service in portal, unable to edit the information but he is able to add notes. in the form.
    In detail, the manager is trying to assign new manager to an employee under him(moving an employee to differen team headed by different manager so trying to replace his name in the employee's informaton). The manage is unable to change the information or unable to edit any information in the form "request for change in position/transfer"
    Could someone help me on this.
    Thanks in advance.
    Regards,
    Ravi.
    Edited by: Ravi Alla on Jun 17, 2010 9:15 PM

    Hi,
    The issue is resolved. This is because of Acrobat JavaScript option disabled in display preferences of the form.
    Once this checkbox is enabled its working fine.
    Regards,
    Ravi.

  • InfoCube Error Message: Choose a change request with target system BWQ

    Hi experts,
    I have a problem when I want to edit an InfoCube created by other developer. The error message received is as follow:
    "<b>Choose a change request with target system BWQ</b>".
    When I click on the Documentation (F9) button, the detailed message is:
    "Message no. TK511
    Diagnosis
    The selected change request BWDK901086 has target system .
    However, the objects you edit can only be recorded in change requests with the target system BWQ.
    The correct target system is determined from the package and transport layer to which the object concerned belongs.
    System response
    The selected change request BWDK901086 is not used to record the objects.
    Procedure
    Either choose a different change request or change the target system of the change request BWDK901086.
    From the prompt window for change requests, you can display all requests you can use by choosing Own requests.
    Alternatively, you can create a new request by choosing Create request.
    For more information, see the SAP Library under BC - Basis Components -> Change and Transport System ."
    Can someone helps me to solve this problem?
    Thanks!

    hi Fullham,
    try se09/10 and find request BWDK901086 (use binocular icon) or se03. then double click that request, go to tab 'properties', hope you will see 'Target System' system there, click 'edit'/pencil icon and change it to BWQ.
    you may need to change the owner (which may not authorized), ask basis help if necessary.
    hope this helps

  • Unable to check in for change request

    Hi,
    We have enabled checkin checkout functionality for ChaRM in solman_directory,
    Once we create change request for a business process from solman_directory,e we checkout structure object for that change request into assigned maintenance project., before authorizing change request.
    Once change request is completed ,we want to check in the structure object, but not getting the option  under Change Request->Transaction Type=>Customer fields->Solution->right click on assigned business process.
    Also tried by changing the phases of maintence cycle but no use, all requests are remained pending in check out,
    Please suggest.
    Thanks
    Sonal

    Dear Anzar,
    What is the error message you are getting. check the CMS logs for the more information.
    Please check n verify location of the inbox folder when you click on checkin tab.
    refer to SAP Notes 872892.
    Best Regards
    Arun Jaiswal

Maybe you are looking for

  • Please help [Realtek LAN NIC problem]

    Hi everyone, this might be a long post but PLEASE read it if you have the time, you might just know the solution to this problem. to begin with, here is my system: Windows 2000 pro sp4 AMD Athlon64 3000+ MSI K8T Neo (BIOS rev. 1.10) 1 GB (2x512) PC35

  • How to reference a parent element in Excel Templates

    I am using an excel template and I have nested groupings of xml that I wish to flatten, for example: <G_DEPT> <DEPARTMENT_ID>10</DEPARTMENT_ID> <DEPARTMENT_NAME>Administration</DEPARTMENT_NAME> <LIST_G_EMP> <G_EMP> <EMPLOYEE_ID>200</EMPLOYEE_ID> <EMP

  • Error: while populating the target.

    While populating the target table gettig the following error: ODI-1228: Task Int_HDM_IND_PRTY_ETHN (Export) fails on the target ORACLE connection ORACLE_ETLDEV_INOVA_3. Caused By: java.sql.SQLException: ORA-01471: cannot create a synonym with same na

  • Field FNAME displayed in german..

    In standard report *RFKABL00* field *FNAME* sometimes display text in german and sometimes in english. What Could be the reason? John. Edited by: JohnMell02 on Feb 9, 2010 2:52 PM Edited by: JohnMell02 on Feb 9, 2010 3:01 PM

  • BLANK DESKTOP APP I AM SICK OF IT HAPPENING

    Is it just me? but I am sick of getting the blank desktop app. I have done the C:\user\appdata\local\adobe OOBE folder to OOBE.oid and it worked for a few weeks. Then out of the blue it's blank again. I have seen that C:\programfiles(x86)\common file