Changing basic finish date in Preventive maintenance orders

Hi Experts,
My requirement is to block PP work centre when maintenance schedule the equipment for preventive maintenance. I am making system condition as zero in generated preventive maintenance order but basic finish date is not changing in the order automatically. Can anybody please explain how to bring this? Finally my requirement is system should change basic finish date and time as time given in operation of task list.
Thanks in advance.
best regards,
Srinivas M

Hi Praveen,
I have done all setting and tested but there is no change.
My client requirement is like this - whenever maintenance plans are scheduled, for the scheduled dates, production capacity should not be considered by production. We could do this for breakdown orders but not happening for PM orders unless we change the finish date.
The issue is to get the finish date automatically when scheduling maint.plans with respect to values given in operations. Please suggest how to get the  basic finish dates automatically.
best regards,
-Srinivas

Similar Messages

  • Change of Basic Finish Date for a Maintenance Order

    Hi Experts,
    I have a requirement where I need to change the Basic Finish Date of an order. Currently in config for order type and plant combination, scheduling parameters are set as:
    Adjust to Basic Finish Dates
    Automatic Scheduling.
    If in an order, I remove the tick for Automatic Scheduling, I am able to change that but I am not supposed to do that.
    Can you suggest me how thisissue can be resolved. Remember, changing the Config is not an option.
    Regards...

    hi
    Since you have done the adjust basic dates ,kindly change the operation dates ,which will automatically change the dates specified in the operation dates
    regards
    thyagarajan

  • Basic start date and basic finish date in the maintenance sub-order

    Hi guys,
    when I create a maintenance sub-order by the transaction IW36 are the Basic start date and the Basic finish date taken,inherited from the principal Maintenance order?And if it is in this way,is there the possibility to put these two dates as a current day only on the  maintenance sub-order ?Thanks in advance...
    Maximilian

    Here is my code
      DATA : lv_date_diff TYPE i.
      lv_date_diff =  caufvd_imp-gltrp - caufvd_imp-gstrp.
      caufvd_exp-gstrp = sy-datum.
      caufvd_exp-gltrp = sy-datum + lv_date_diff.
    This is a 4 year old answered message. Please open a thread for your specific query.
    -Paul
    Moderator
    Edited by: Paul Meehan on Nov 24, 2011 8:42 AM

  • Want last date of the month as default basic finish date for the Proc order

    For forward scheduling type in process order, irrespective of the start date i want last date of the month as my  basic finish date.
    Ex start date can be 01/10/2009 or 15/10/2009, but the basic finish date should be 31/10/2009.

    Hi Sam,
    sorry to say , its not possible in standard SAP.
    1) If, on order creation, a planned order exists for the production order/ process order, the basic dates are copied from the planned order.
    2)If no planned order exists on order creation, you must specify at least one basic date.
    The scheduling type determines the basic dates that you must specify. and it useses timings from routings for scheduling.
    so may be you need some work around.
    explain your requirement why do you want to fix it for the last day of month and other constraints, may be we can find some way.
    Regards
    Ritesh

  • Basic Finish Date in Service Order

    Hi Gurus,
      I want to change the Basic Finish date in the service order. The
    system is allowing me to change it in the change mode of service order
    (IW32), but after saving when I come back and see the order again, it is
    showing the old date only. I want to change the Basic Finish date as
    10.09.2007. Could anybody please guide?
      Prassee

    Hi Thyagarajan,
    Thanks, I have already checked the same. For the order type and palanning plant, the date adjustments set as " Adjust basic date.......", but still it is not allowing me to change the basic date.
    Prasanth
    > hi prasanth
    >
    > check for you order what scheduling parameters are
    > you maintained.if the Adjust shchduling is set as" DO
    > not adjust basic dates:, then i think your problem
    > will occur.
    >
    > regards
    > thyagarajan

  • Material Availability Date and Corresponding Basic finish date

    Hi experts,
    I have one requirement from my Business for updating Basic Finish date based on the Material availability date
    Requirement goes like this, When we enter a Component of 100 qty  in the service order , if stock is not available we get system status as MSPT and IWBK we can see how much quantity confirmed
    But i dont see any table or report which shows when this material can be available for further delivery. Based on the next available material date i have to change the basic finish date in the service Order
    Please let me know if you any report available for this or any standard approach. I want to know if any exist to leverage this functionality and logic how to get this accomplished
    thanks
    sarvan

    Sarvan,
    You would need to perform this check when saving the work order as there could be multiple components all with differing ATP dates.
    But a development could do something like:
    Read all active/open components/materials on the work order
    Determine the availability data for each component/material
    Determine the latest of the above dates
    Apply this date to the order Basic Finish Date
    You would need to ensure your scheduling parameters do not set this date back to its original value (OPU7).
    You could achiev the above through user-exit IWO10009 (SMOD) or BADI WORKORDER_UPDATE (SE18).
    PeteA

  • Collective orders header order basic finish date is not changing

    Hai all,
    I am working on collective orders. The header order has Basic finish date as 17.05.2011 . Now i have changed this date to 10.05.2011 and re scheduled the order . But again system changing the Basic finish date to 17.05.2011. how to solve this.
    In the outline dates also i have given finish date 10.05.2011 it is remaining the same but order Basic finish date is not changing and schedulded dates are also not changing. can anybody help.

    Hi gurus,
    In a collective order suppose the lead order is having three child orders.  Kindl
    If one of the child order is partially confirmed is the entire collective order can be rescheduled.
    If one of the child order is Fully confirmed is the entire collective order can be rescheduled
    Can any body help me out

  • Work Order Basic Start Date and Basic Finish Date to be changed

    Hi,
    Currently the business creates work orders without specifying the work resulting which the start and fish dates on work order are same. Also we have automatic scheduling turned off. In spite of this If I am trying to manual modify the basic start and basic finish dates on work order it does not allow me to do so. This issue is seen with work orders which are Released whereas orders with status outstanding have no issues. Could anyone please let me know what could be the reason?
    Thanks,
    Vinay

    Please check whether Scheduling type only capacity requirement is configured.
    If yes, choose this scheduling type in order, you can able to change Basic start date & basic finish date.

  • Basic start & Basic finish date in PM Order

    Hi,
    This is related to Preventive Maint. Order Basic start date & Basic finish date.
    I have configured 2 priorities.
    Priority 1 with Relative Start 1 & Rel. end 10 Days
    Priority 2 with Relative Start 1 & Rel. end 30 Days
    PM Plan is created with strategy
    Weekly & Bi-weekly
    Priority 1 is set in PM plan
    Scheduling Period 60 days
    Call horizon 100%
    Scheduling has beed done with start date as 02.09.2014.
    Plan dates are as below.
    09.09.2014
    16.09.2014
    23.09.2014
    etc
    PM Orders have been called through IP30.
    When I checked the Maint. Orders, I found that the Basic start date & Basic finish dates are same as below in all the Orders generated through IP30.
    Basic start date: 09.09.2014 & Basic Finish date: 09.09.2014.
    Actually it should calculate Basic Finish date as Basic start date + 10 days (as per my priority).
    Can I know reason why system does not consider the priority duration in this.
    Thanks in advance.
    Regards,
    CSR

    Greetings Raman,
    To shift the basic dates for the Orders generated by a Strategy Maintenance Plan, you may use the Float (Initial and Subsequent) values defined on the Strategy level in the Maintenance Strategy itself (IP11)
    Normally, the Date Shifts maintained in the Priority do not come into play when you are scheduling Maintenance Plans.
    So the rundown is that you can shift the basic dates in Preventive Work Orders, differentiating on the Maintenance Package, rather than Priority.
    If you require the Basic Dates to be adjusted for generated Orders, you can develop a solution using EXIT_SAPLCOIH_012
    See some more useful info:
    Answer by Pete Atkin in this thread: Maintenance Plan Priority not changing the dates in the Generated Order
    Basic end date does not influence priority from maintenance plan
    Workaround for maintenance plan priorities in work orders?

  • Preventive maintenance order actual completion time and date

    Hey gurus,
    In preventive maintenance order the basic and scheduled start dates are picked from the maintenance plan. Now the actual start and end dates are in display mode. My client wants an overall completion time and date of the preventive order and not of individual operations. Also at the end of the month they want to see the total time spent on preventive maintenance. Can you suggest any way to sort out the above problem.
    Regards,
    Abhishek

    hi.
    the basic start date and end date is coming from maintenance plan. but you can change that dates according to your requirment. For that you have to remove the automatic schduling check in the dates header in maintenance order. Afetr that you can put basic start and end dates as per your requirement.
    Also the actual start and end dates and coming when you confirm the operation.
    When you confirm the first operation, that date the system will take as actual start date and the day you confirm you last operation or fully confirmed the order will be taken as actual end date.
    So i dont think yu have any problem. You can take basic start or basic end dates for this and change the dates as per your maintenace requirments.

  • Process Order Basic Finish Date and Scheduled Finish Date

    Folks,
    I have a requirement from the business to be able to update the Process Order Basic Finish Date and Scheduled Finish Date independently from each other.
    In other words, update the Basic Finish Date and the Scheduled Finish Date cannot change or update the Scheduled Finish Date and the Basic Finish Date cannot change.
    I believe the reason for this is to be able to use the Basic Date to maintain the ATP accurately and keep the Scheduled Date to mark when the order was originally due from the shop floor to be able to measure if orders are being completed on time or late.
    I have worked in tnx OPUZ and had some success with other issues with these dates but I can't seem to make them work independently from each other.
    Or does anyone have any ideas how to measure proces order performance to the production schedule?
    Thank you for your help,
    Greg

    Rajesha, thank you for your reply but it doesn't solve my problem.
    Let me restate my scenario:
    I start a process order and both the basic and scheduled finish dates are the same, June 1.
    At some point, shop floor tells me they will be late and cannot deliver until June 15.
    I need to update a date in the system so the ATP and the MRP planning runs have correct information for promising customers, I will update the Basic Finish date with June 15.
    I also need to keep the original June 1 date in order to measure the shop floor performance to the production schedule to measure how early or late the  order was delivered. How can I keep the original finish date or how can I measure if a process order is early or late??
    Thank you for your help,
    Greg

  • Why the basic finish date is not adjusted in planned orders

    Hi, all.
    Can anybody help me to understand:
    "Why the basic finish date is not adjusted in planned orders during
    forward scheduling, but in production order basic finish date is adjusted?
    It is look like non-coordination between groups of developers.
    And lead to situation, when planner don't see in MD04 when he can really wait material receipt. He must go to planed order and check production data there, it's unusable."
    Am I right, or SAP have it's own logic.

    Hi,
    Production orders are different story. Since production order is a constant element, they are not created in the course of MRP, basic dates can be adjusted. In production order basic finish date is adjusted, but you won't see for the upper level materials', basic dates of the planned orders adjusted according to the prodcution order you create. Production order is consistent within itself in terms of date and is not dependent to other elements of MRP, but planned orders are not like that.
    MRP creates planned orders whose basic finish dates are calculated by subtracting goods receipt time from production start date of the source of requirement. MRP works backwards without changing directions. Meanwhile if any production finish date is calculated different than the basic finish date due to forward scheduling, in order not to violate the alignment between the basic finish date and source of requirement's start date, basic finish date is not adjusted. If it was, dates of all the planned orders calculated so far at the upper levels of the BOMs had to be recalculated, otherwise all the consistency of all the dates is violated. This cannot be done because changes in any level affects all lower levels.

  • Production Order: warning when Basic finish date is before scheduled finish

    Hello experts,
    We will set in config OPU3 (scheduling parameters for prod order) Adjust dates = 2 Do not adjust basic dates, ... Essentially this will allow the shop floor controller to change scheduled date ie. production dates without affecting basic dates.
    With this setup the system may display in the header of an order the scheduling note "Basic finish date is before scheduled finish" as well as generate a scheduling log "Scheduled finish is after basic finish date" (message 36 mess class C7).
    These messages are not enough visible for our planners. I would like to find a way to generate a warning before save. I tried to add a record in OPJB: message class CO no. 533 "Scheduled date & is after the requirements date &" but this doesn't work.
    Note: I tried to add message class C7 no 36 in OPJB but got the error "Please enter a legal value".
    Have you been able to add message in table OPJB ? Is it a good idea or the only option is enhancement?
    Thanks for sharing your ideas.
    Francois P.
    Edited by: Francois Paquet on Sep 30, 2010 5:30 PM

    Hi Francois
    I'm trying to do the same (also for C7 035).
    Have you already found out how to do this?
    Arno

  • Production Orders - Scheduled Finished Date Basic Finish Date

    In production orders, it is being noticed scheduled finished date lies further than basic finish date, what could be the
    reason? what configuration should we need to do in order to make scheduled finish date matches (or) lies before basic finish date

    Eshwer,
    Basic dates of production orders can be made to match scheduled date.
    Config is at OPU3.  Under the "adjust scheduling" section, select either 1 or 'blank'.
    Best Regards,
    DB49

  • Basic finish date exit issue

    Hello Gurus
    I have a requirement to bring the basic finish date based on the priority calculation date from the maintenance plan for auto generated work orders. Since its defaults to the start date, I am trying to use the user exit : IWO10012 Maintenance order: Priority treatment on central header.
    I talked to developer and it seems like he is facing issues on and off using this exit.He cannot figure out when it gets called.  He has a debugging break point in the user exit which will take to the code of the exit whenever it is called.  It gets called in some circumstances, but not in othersu2026 and he cannot find any reason to it.  When it does get called, however, it does its job of updating the Basic Finish Date.
    So what could be the issue in this situation ?
    Mahee

    Mahee,
      On the order side, This exit will only be called during create.I dont think this will be called on change mode or when the priority is changed.
    Regards
    Narasimhan

Maybe you are looking for