ChaRM - Multiple Maintenance Cycles

We now have a Quarterly release cycle; however, we'd also like to have a Weekly release cycle for the smaller break / fix changes that are not true Urgents.  We don't want to use UCs for these since we'd like to move them together on Saturday morning.  How can we prevent leapfrog issues?   For example, if an object is on the Quarterly and Successful Testing is recorded, the object is released.  If the the same object is now changed and included on the Weekly Maint Cycle and moved to production, it will be overlaid when the Quarterly Maint Cycle is moved to production.  I don't think this is possible, but I was asked to confirm..... Is it possible to re-import all of the Transports from previous weeks at the time the Quarterly ones are moved to ensure all Transports are moved in the order they were actually released?  Is there a way to detect / prevent leapfrog issues?  What do other companies do?

If you use normal correction for your quarterly release and SDHF corrections for your weekly releases, the normal correction will move ALL transports for the maintenance project including those which are for the SDHF corrections and even those for which the SDHF correction has not been approved for production import.
If you are only using SDHF variants for your process - then there is a possibility to handle this manually through the maintenance cycle directly. There are mass transport move tasks in the task list of the maintenance projects. However, this will require a manual element to your process for the production import.
But as you may already be aware, either of these options are tricky to implement and you need to have someone with a good understanding of development and transports.
Hope this helps...
Cheers
Pranav

Similar Messages

  • ChaRM: Several maintenance cycles in one maintenance project?

    Hi!
    We are working with urgent correction within ChaRM and thinking about to implement the normal corrections as well.
    Our ChaRM workflow for normal corrections is characterized by:
    a)corrections with different Life cycle (those who will be processed within 1 week, other with 2 week, etc.)
    Questions:
    1) Is it possible to have several maintenance cycles for one maintenance project to handle condition u201Ca)u201D?
    2) What will happen with all the normal corrections and urgent corrections that have a long life cycle (status: in development, test, etc.) when the charm manager set the status of maintenance cycle in u201CGo liveu201D?
    Thank you  very much!
    H. Thomasson

    Hi Holger,
    Maintenance cycle and SMI project is a 1:1 relationship.
    In status GoLive you will be able to continue developement/work on normal corrections but you will not be able to release any transport requests/create transport of copies so your testings in QA will be limited.
    In phase GoLive you are able to import requests into production.
    Normal Corrections which have not been released yet are not lost. Depending on your scenario you may switch phases back to "in dev with rel." after you imported into production. It is not necessary to close and recreate maintenance cycles if you use one project for daily/weekly maintenance.
    /cheers

  • ChaRM and Maintenance Cycles

    All,
    I am just starting out with implementing the ChaRM functionality on Solution Manager 4.0 SP12.
    I have activated the BC Sets and can see how to customise the Change document behaviours but am struggling to understand and prototype the integration of transports & Maintenance Cycles. 
    I am planning to implement SP15 but until then, I wondered if you could point me in the correct direction for understanding how they work and how to customise the settings for them?
    Ideally, I would like a reference site to view this in an operational sense.
    Any help is appreciated.
    Simon

    Simon,
      Here you go - there is more on the SAP Service Market Place and e-Training, but this link below is also a great source of information on how to get everything working.
      If you have any more specific needs, please don't hesitate to ask - if this answers you question, please set this thread to answered.
    http://help.sap.com/saphelp_sm40/helpdata/en/0c/5b2160f6fa4b83a3674a210b1cdeb0/frameset.htm

  • CHaRM tasklist (Maintenance Cycle) activation problem

    Hi ,
    When activating a tasklist for maintenance cycle I get the following error message:
    Phase change from 'Created' to 'Development w/o Release' is not possible.
    Details: Change transiton is incorrect.
    Any ideas anyone on how to resolve this.
    Thanks

    Hey Sniper,
    Try this note: 93398: Status Change from Created to indevelopement is not possiible
    let me know whether it works.....
    Reward points or usefull answer....
    Regards,
    Anand....

  • SDTM Maintenance cycle - little help needed

    Hi all
    I am following the blogs of Dolores Correa (thank you for the blogs) and I have become a little stuck - I am hoping you can help me out.
    I have created an SDTM (test message) during my Test Phase.  In the blog there is a way to assign the project for the test phase (and therefore the MC) - I cannot find where to do this, how do I assign my test message to the correct maintenance cycle?
    Many thanks
    Marina

    Perhaps I am thinking this is more complicated than it is .... if I only have 1 maintenance cycle does the test message get automatically assigned to that maintenance cycle?  and only if I have multiple maintenance cycles do I have to assign  a cycle??
    I guess that there is also no way to have a test message associated with a particular change request - that would be helpful because then the developer would know what the test message is in relation to, but I can't see a way of connecting a SDTM to a SDMJ.
    Any ideas or musings are welcome

  • Multiple system maintenance cycles are not shown in pop up for selection

    Hi,
    In change manager, when we create a change document from a change request, we dont get a pop up for selection of maintenance cycles with multiple systems in it.
    The change document is getting created by taking the only available maintenance cycle with only that system.
    Is there any configuration for this?
    Regards,
    Dipti Sawarkar.

    Hi Christian,
    Thanks for your reply.
    I know the pop up will come only when there is more than one maintenance cycles for that production system.
    I have done configuration for Normal correction.( SDMJ) and customized it (ZDMJ).
    When I try to create a CD* from CR* for a particular production system ( CCP) , it just takes up a maintenance cycle for CCP system and doesnt show up any pop for selection of maint cycles whereas I have created 5 maintenance cycles for this system CCP.
    The other 4 maintenance cycles have multiple landscapes (CCP and EAP )in it whereas this one (which gets selected by default) just has CCP landscape in it.
    The strange part is that when I try to create a stand alone CD ( without CR ) , it will give that pop up showing all 5 maint cycles. But this is not happening when I create a CD from a CR.
    I have never done/ seen configuration for the pop up of selecting maint cycles in ChaRM.
    Looking forward to ur help,
    ( *CD - Change Document  and * CR - Change Request)
    Regards,
    Dipti Sawarkar.

  • Not able to closing the maintenance cycle of charm

    Hi Team
    I am not able to close the maintenance cycle of charm.
    I had already tried with the phase utility report, I had checked my all authorizations and it is fine.
    I had gone through most of SCN queries for same, current phase of project cycle is completed however. Not able see the any error logs in SLG1.
    Regards
    Harsh

    Hi Rishav,
    We had resolve the issue as now we are able to close the cycle successfully,
    But new CTS project is not being generated, Any idea, should we need to check this with SAP again.
    B R
    Harsh

  • Inconsistency with maintenance cycle and task list phases in ChaRM

    Hi Experts,
    I'm deploying ChaRM with SolMan 4.0 SP09.
    I was testing a scenario where there are more than one maintenance project open for same landscape (different logical components but values are the same). I have been using maintenance cycle document (in crmd_order) to control phase changes both in task list and in maintenance cycle.
    I received an error message stating that the system has reset the status of the maintenance cycle and the end result was that task list phase is one step ahead of the maintenance cycle. This of course causes the situation where certain actions are no longer possible (maintenance cycle in Dev with release but task list already in test => release and import are not possible and reseting phase with task list is prevented by ChaRM).
    My question is how do I restore the inconsistency. I have looked for notes (but of course this is not a notes issue) and the internet for solution.
    I am very greatful for any hints you may give me!
    Kind regards,
    Auli

    Thank you!
    Exactly what I'm trying to do. I'll give it a go and get back to you asap.
    BR
    Auli

  • Charm implementation: No maintenance cycle is open for the current system

    Gurus,
    I'm in implementation project to use charm.
    I've created SDCR using charm_create, and choose transaction type subject "Development (implementation)"
    After approving the change request, so that the status become "Approved", I re-open the request to set into "in development", but there's error:
    "No maintenance cycle is open for the current system"
    I've checked notes and search the forum but not relevant to my subject.
    Please help.
    Regards,

    Hi Cesar,
    I'm facing this issue now. I have followed Dolores blog
    - The IBase is wrong: The IBase/component must represent the production system in the project landscape. RP1 is my production
    - Lack of authorizations: Assign role "SAP_SOCM_ADMIN" or "SAP_CM_ADMINISTRATOR_COMP" (or equivalent) to the user who would like to approve the change request. I have updated all roles and given the users SAP_ALL
    - Project is locked in table /TMWFLOW/PROJMAP: If an error is detected during the processing, then the project might be locked in this table. The customer can unlock it by pressing the refresh button under tab "System Landscape" -> "Change Requests". If there are other error messages shown during the refresh process, the customer must fix those errors beforehand. Refreshed it many times without errors
    I'm on the latest level of Solman 7.1 SP8, I have implemented all the new notes as well.
    I have attached a screenshot
    To me it seems like a bug, but haven't found anything on marketplace. Any help is much appreciated.
    Cheers
    Jimmy

  • Not able to complete Maintenance Cycle in CHARM Maintenance Project

    Hi,
    While completing the CHARM Maintenance Project, getting following error:
    "Error RFC destination
    /TMWFLOW/TL_COMPL_CHK_TR_WO_TL: New Maintenance
    Cycle M000000177"
    Because of this error I am not able to complete  the Maintenance Cycle, i.e. not able to change the status  of Maintenance Cycle to 'Completed'
    Regards
    PK

    hi PK
    please refer the posiblities on
    [cannot close maintenance cycle|Cannot Close Maintenance Cycle in CHARM;
    jansi

  • Assigment maintenance cycle -- system (IBASE) in CharM

    Hello!
    I have the problem to establish CharM functionality.
    When I try to set a urgent correction in status "In Development" I get the following error:
    No maintenance cycle is open for the current system
    My question are:
    - How do this assignment maintenance cycle <--> system (IBASE) work?
    - Is it perhaps possible to execute this assignment manually?
    - Is there some log files that can be analysed for this problem?
    Thanks & regards
    Thom

    Hi,
    About this issue, there is a detail information about this in blog point 6  u201CChanges in the logical components of a project where Charm is already activatedu201D.
    This is the link:  http://www.sdn.sap.com/irj/scn/weblogs?blog=/pub/wlg/15116
    So, you have to change the transport route accordingly and then close current maintenance cycle and generate a new one.
    Following is the steps.
    1: please import all the transport requests which were associated in the current maintenance cycle task list by STMS manually import.
    1: change transport route from DEV > PREPROD >PROD to DEV > USER > PROD on the domain controller system.
    2: close current maintenance cycle.
    3: change the system landscape to DEV > USER > PROD in solar_project_admin.
    4: generate a new maintenance cycle.
    Thanks
    Regards,
    Vikram

  • ChaRM Error - "No maintenance cycle is open for the current system"

    Hello All,
    I am setting up ChaRM in development system after EGI session with SAP support. I have copied standard transactions to custom ones and created Maintenance and Implementation project to run test of all scenarios.
    I now come across error of "No maintenance cycle is open for the current system" after I create a change request and in the change document, I cannot see it link with task list and the error message is displayed. I tried it with custom transaction as well as standard SAP transaction (SDCR) and get the same error.
    What links a document to a maintenance cycle? Where can I see the config of this setup? I am trying to see where it is broken. I am using the correct IBASE number (production client in logical component), I tried to create a new logical component, new projects with correct settings but it still gives this error message. Please advice.
    Thanks and regards,
    Nischal

    Hi
    did you also unlock the maintenance cycle and open for changes in solar_project_admin by right click
    do check this blog
    /people/dolores.correa/blog/2009/07/23/change-request-management-scenario-working-examples
    /people/dolores.correa/blog/2009/07/23/change-request-management-scenario-working-examples-final-points-and-appendix
    Question no 17
    /people/dolores.correa/blog/2009/07/22/change-request-management-scenario-usual-questions-and-known-errors
    Hope it solves
    Regards
    Prakhar

  • Cannot Close Maintenance Cycle in CHARM

    Hi,
    I'm testing CHARM and I'm trying to set the Maintenance Cycle (SDMN) to "Complete", but it's giving me an error.
    Error: "Move to Next Maintenance Phase Rejected"
    I was able to go through all the maintenance phases successfully as part of my testing, but for some reason the system will not let me close the maintenance cycle.
    How can I find the problem?

    Hi,
    Follow this note to 1134993.
    This should solve your problem.
    Feel free to revert back.
    -=-Ragu

  • Maintenance cycle - Charm

    Dear All,
    I am in process of implementing CHARM and i am facing issue in the process flow for maintenance cycle.
    In normal changes - we create change request and a maintenance cycle (MC) is attached to it. Once we change the status to Dev with release then changes are moved to Test system (transport of copies) and after successful testing (actual transport request is released) we change MC status to Test then changes moves to Test system. Then MC moves to Go live and then changes are imported to production. Now when status of MC is go live then we need to change the status back to dev with release which is not working instead it gets insync with the project phase. Kindly let me know if anyone has faced the similar situation.
    Can you someone please clarify how mc status should work in case of normal changes.
    Regards
    Sushant

    Hi Sushant,
    1. try to change the phase of the project cycle without assigning any Change Document to it .
    2. Number Ranges
    "Before you can begin using Change Request Management transaction types, you must ensure that a number range is defined for these transaction types. The number range interval determines the sequential numbers assigned to newly created transactions. "
    To do so you can use transaction SNUM and enter CRM_SERVIC as the number range object.
    The number range interval which the system uses is defined in the transaction customizing in the Transaction Numbering section.
    Please check the below link for more details in 3.2.7
    https://websmp208.sap-ag.de/~sapidb/011000358700001056012011E.PDF (3.2.7)
    Rg,
    Karthik

  • Object to change the SCMA maintenance cycle phase in CHARM

    Hi Everyone,
    Can anyone let me know what is the Object which can perform the activity of changing the Maintenance cycle phase in SCMA Tcode in CHARM? i know only the change manager will have authorization to do that. i want to know the Role name and the particular object which will perform this activity.
    thanks,
    Guru

    Hi ,
    You can follow the below steps.
    -> Goto Tcode SUIM
    -> Roles -> By authorization object
    -> object name : B_SMAN_WPL
    -> Execute
    This will give you the list of roles that are holding this object.
    Cheers!
    Veena BJ

Maybe you are looking for

  • Diff b/w Data warehouse and Business Warehouse

    Hi all, what is the Diff b/w Data warehouse and Business Warehouse?

  • Db connect no data found in the table

    Hi Gurus, I want to extract data from the oracle database, through db connect, when i edit the datasource and press the button display table contents, it says no data found.   What could be the problem, i have created the source system properly, give

  • Removing comma (,) from string

    Hello Friends, I have a string something of this nature Sting : ',3456,45454,,45454,' Need to have just comma seperated value : '3456,45454,45454' Tried with replace but getting - '34564545445454' select replace ( ltrim(RTRIM(replace(',3456,45454,,45

  • Multiple record insert thru PROCEDURE - Urgent

    All, My requirement is, I have to invoke a procedure which accepts two input and 1 out variable. The operation of the procedure is to insert the data to two tables(head_tab and line_tab-accepts multiple record). I used %rowtype for the two inputs i.e

  • Find a field in CMPWB component

    Hello, I am using ICCMP_BTSHEAD component in ..CMPWB. I copied the configuration to mine one and I want to add the field SORT1 to the view. I can't find the field . I don't know how to find it in the BOL. Is there any summary report on the views? TIA