Checking the Allocation of General Ledgers to Cost Centres

Hi Gurus,
Can anyone help me to find out that how to check the allocation of General Ledgers expenses to various cost centers.
Since in production concern , one GL might be getting allocated to various cost centers . I just wanted to know that a particular GL a/c is getting allocated to this , this and this Cost Centers in my system.
Please tell me the way to counter check it as well so that I will be of sure that there is not Cost Center left behind.
I am hoping that I have put my question correctly.
Thanking you all in advance.
Yasir Shaikh.

Thank you Ali,
Dear All,
I was taking one GL (Salary) as an example from a closed month and noted the following:
1) Total amount booked as per HR lets say $100,000.
2) The same amount was allocated to Production Cost Centers (i.e. all 100,000$ got allocated to production cost centers. Noted from this code S_ALR_87013611)
3) Again the same amount is getting as the balance of G/Ledger Account when I am extracting the Trial Balance of that period.
Isn't there should be nil balance after the close of the period, as the same has been allocated and charged to cost centers and ultimately has become part of the inventory cost. ?
Thanking in advance.

Similar Messages

  • Costing Report to Check the Result of MR21

    Hi all,
    I have tried to change the Sales Order Material Value with MR21. The results can be checked with MB52.
    However, I want to check the actual results in accounting and costing aspect.
    Could suggest any costing reports that can trace and analysis the costing Sales cost?
    Cheers,
    Simon

    Hi Simon
    Use T code CKMPCD and you can see the Price Change docs... You can filter the docs based on Mat No / Period/ etc
    It will show you the desired acc/CO docs
    Br, Ajay M

  • Cost centre in the accounting document

    Hi all,
        Can any one please let ms know, how the cost centre in the accounting document for a physical inventory adjustment is being retreived. In my scenario, the busines want to post the gain / loss from the physical inventory adjustment to different cost centre on the basis of valuation class and plant.
        My understanding is that the cost centre will be retrieved from the OKB9 entry, where the cost centre will be assigned to a cost element. The same cost element will be assigned in OBYC configuration in the combination of the transaction key, val grp, account modifier and Val class. Can you please confirm my understanding and let me know the std account modifier that will be triggered for phsical inventory differences.
    thanks & regards
    Chaitanya Rayaprolu

    Hi
    As far as my understanding, cost centre will not be attached to inventory gain/ loss account. We assign GL account for physical inventory differences in GBB - INV in OBYC which do not require a cost centre. Scrapping process requires a cost centre as it is a process loss but PI differences do not require cost centre assignment. We assign GL accounts (which are set up as cost elements) in OBYC settings for some postings like VNG, VBR etc which requires CO object assignment.
    Thanks

  • Order settlement to G/L instead of Cost Centre.

    Dear All,
    My client has following scenario:
    1. Cost centers are created as sections of the plant.
    2. G/Ls are created with respect to activity (i.e normal consumption, project consumption, turnaround consumption).
    In general maintenance order is settled to cost center that is copied from equipment master to order settlement rule. But, in above scenario cost should be settled to combination of "Cost Center + G/L" i.e. if mechanical section creates an order for any of the above said activities, the order should be settled to mechanical cost center and respective G/L account.
    "One way around to this issue can be accomplished by settling the order directly to G/L defined in combination with section and activity."
    Is this a correct practice if we settle maintenance order directly to G/L and do not use cost centers?
    Your expert opinions and any other solution if you can suggest in this regard will be very helpful.
    Thanks.

    Hi,
    Maintenance Orders are generally settled to cost centres as maintenance activities are nothing but Expenses. Please note that Cost Centers are meant to capture costs through GL accounts which are to be created as a Primary Cost elements in CO and the costs are passed to the cost center through account assignments.
    The settlement will require an assignment to a CO object which may be a cost centre,order,WBS etc.  If you are trying to simply assign the settlement receiver as "GL account" in Order, system will ask you for asignment to a CO obeject. Hence it is imperative to use cost centres.
    For your scenario, you need to specify the range of cost elements to which settlement is allowed in the "Allocation structure" configuration. Tick on settlement by cost elements.Allocation structure is linked to your settlement profile.
    When settlement process runs, your order cost will flow to the respective cost centre(from settlement rule) and the corresponding cost element will be affected. The details of debit and credit can be checked through the CO document which is generated.
    Hope this throws some light on your query.
    Regards,
    S.Basu

  • GL account posting error with cost centre

    Hi experts
    I am trying to post Goods issue with the combination of GL account and cost centre...
    The system throwing an error message saying " GL account XXXXX not valid for cost centre XXXXX or order entered"
    what could be the mistake i have done... kindly reply
    Thanks
    Alex

    Hi
    Z message means you have a custom validation in Place
    Go to OB28 and check which validation is causing this issue..
    you need to either change it so that this posting goes through or use a proper GL account in accordance with the validation
    Regards
    SAPFICO

  • Actuals postings to Cost Centre Accounting

    Hi,
    We have a Z field created in SPL and added the same in BSEG table. The same field does reflect in Cost Centre Accounting document but with incorrect values (Transaction MIRO).
    Any pointers towards any standard SAP user exit / program would be useful.
    Regards,
    Amar

    Hi,
    Use check table while defining the Z field or check the update field.
    if not solved, explain in detail.
    Thanks,
    Sujai

  • Cost Centre Splitting

    Dears
    I am not very much conversant with Controlling.
    Still I am supposed to do the period opening activities in Controlling.
    I need a clarification on the Cost Centre Splitting.
    Cost Centre 300001 is having 3 activity types : MACH001, LAB001, FIN001
    In our case, there is a Split structure Z1 and there are 35 assignments to this structure.
    When I go into the individual assignment, say, first assignment (defined as 10),
    I see that the selection criteria is Cost element group : AB0001 (5 cost elements) & ActivityType : MACH001.
    What does this imply ?
    I understand that the total plan cost for the cost element group AB0001 will be allocated to the Activity type MACH001 for this Cost Centre 300001.
    This cost will not be available to any other activity type in the same cost centre.
    Is my understanding correct ?

    Hi,
    Please look into the following to know the concept of splitting:
    Here I am providing the necessity and importance of splitting structure,
                        Expense Analysis and Splitting in Manufacturing Cost Centers
    Introduction In SAP Cost center work as a cost responsibility center, where all the expenses and cost are stored and analyzed for the purpose of management decision making.
    The cost could be fixed or variable in nature. The difference between variable and fixed costs can be made in various ways in product costing in CO module.
    Fixed costs represent the static costs incurred by the organization, which doesn’t change on the basis on manufacturing activities, which remain constant irrespective of production activities like rent for the premises, salaries of office staff etc.
    On the other hand, variable cost varies based on the level of production activities; if production activities increase then variable cost also increased like electricity consumes raw material charges etc.
    However all the variable cost doesn’t vary in direct proportion by quantity of goods produced.
    In this document will try to define; how the Expenses analysis and splitting of cost done in manufacturing cost centers.
    From controlling prospective, fixed cost remain constant regardless of operating activities, but if these factor changes, variable cost will fluctuate.
    Basically raw material costs represent variable cost, but in this document main focused will be given to distinguish fixed and variable activity cost.
    The segregation between fixed and variable cost is optional and is derived from the configuration and master data configured in cost center accounting and overhead accounting.
    Activity Price:
    There are different methods that could be used in cost center accounting to determine the activity price. The simple way is the manually enter “Fixed” and “Variable” Activity cost (KP26).
    However there are other methods used in Cost center Planning and Budgeting that automatically calculate the fixed and variable activity price.
    Here the focused will be given on Planning and Budgeting activity and automatic calculation of plan activity rate in cost center.
    This method aggregate planned costs by cost element and capacity by plan unit to calculate the activity price.
    Activity independent costs are segregated among different activities based on Splitting Structure, while activity dependent cost directly used for the purpose of variable activity rate calculation.  
    Fixed Activity Cost:
    In product costing all those cost, which doesn’t vary based on the activities in manufacturing cost will represent fixed cost.
    In a manufacturing cost centers there may be two or more activities performed.
    To calculate the activities rate, the fixed costs are distributed to various activities on the basis of Splitting Structure defined for cost center. 
    Variable Activity Cost:
    Variable activity cost, which directly depend upon the activity type and fluctuate based on increase or decrease in manufacturing activities. In SAP variable activity cost are directly linked to the respective activity.
    Activity Prices: Fixed and Variable Split
    In Cost Center Accounting dividing the cost between Fixed and Variable requires appropriate split to be made in the cost entered for the activity. The process is described below:
    i.  Variable cost would be planned at activity level and expenses should be maintained at cost element in the manufacturing cost center by assigning activity and cost element combination.
    In other word, the expenses should be planned on Activity type at the time of primary cost planning (KP06).
    Then the variable activity rates are calculated on Total cost planned at Activity divided by Total number of activity planned at that cost center (i.e. capacity in KP26)
    ii. Fixed cost would be planned at independent of activity type. These costs are maintained in KP06 at cost element level on manufacturing cost center.
    Then the fixed costs are distributed on various activity types on the basis of Splitting structure defined at OKEW.
    In Splitting Structure we define the rules, how the fixed cost will be distributed to Activities. For the purpose of this document, considering split of fixed cost on the basis of Capacity maintained in KP26.
    Regards,
    Pavan kumar Arvapally

  • Usage of Activity types under Cost Centre.

    Hi
    I would like to know the usage of activity types under cost centre.
    How to do direct and indirect activity type allocation.  Please explain indetail from scratch to finish with necessary t.codes at the earliest.
    Appreciate your cooperation at the earliest.
    regards.

    Hi,
    as far as usage of activity types under cost center is concerned it is addressed by ist reply to your query by another SAP Guru.
    with respect to Direct activity allocation,
    When we know the source cost center and target cost center then we allocate the activities from source cost center to Target cost center (T.Code KB21N)
    The cost is picked from the planned price given at KP26.
    Withe respect to Indirect activity allocation:
    We do not know the Traget Cost center in this case.
    First we need to enter the activity consumption in the sender cost center (source cost center).
    Then we need to allocate then indirectly to the target cost centers on some allocation basis using distribution cycles
    I am sure this will clear your query.
    Please assign points suitably
    Best Regards
    surya

  • Concurrent users reporting, by cost centre or group

    hi, does anyone know of a way to report on peak numbers of
    users across a cost centre or group, rather than just per meeting?
    I can't find a way to do this, hope someone else knows how, it's
    driving me nuts!
    the scenario is multiple depts per cost centre, or group
    (don't mind either way, whichever works will be acceptable!!!),
    multiple groups in company. Groups are cross charged for concurrent
    licences, so I need to report on how these are being used.
    Thanks in advance,
    J

    Hi Barbara
    I have been in this situation a couple of years ago. We ended with a solution where I made a report for generating the roles based on the responsibility area, and where the user assignment where done manually. Not a very elegant solution, but it worked.
    I can see that your requirement are a bit more sophisticated though. And if you do not want to generate a lot of roles I think you will need to develop your own concept for this.
    But again, as authorization check are implemented directly in the source code, this is not a small task ~ at least my guess is that you will have to limit the number of report etc used by managers to very few, perhaps Managers desktop or Manager Self Service could help here ? Otherwise I guess my suggestion would be to develop my own reporting application, or try to convince the customer to give up some of the requirements.
    The bottom line is, that SAP Finance really can't handle this in an elegant manor, So Yes  -  a finance version of structural authorizations would be a great Idea

  • Cost centre accounting

    Hi,
    We have a requirement for reporting the costs on the basis of 3 criteria: Location, Industry and divisions. Can someone tell me what is the best option in which our cost centre standard hierarchy can be structured so that, it meets all the criteria. The problem is one particular division will be providing services to all the industries. And if i create a seperate node for each of the criteria, location, industry and division, then cost can remain only in one of the nodes finally. That means if cost is allocated from location node to industry node or division node, location cost centres will be having zero balance. Can someone tell me if there is any alternative to have the cost analysis on the basis of all the three criteria i have mentioned?
    Expecting prompt support as always.....
    Regards
    Suresh

    You can have a separate cost center series for each loaction e.g. 1* for location 1, 2* for location 2 and so on. For each location, maintain the same sequence for individual cost centers e.g. maintainence dept for each location will start with location code and next number is same.
    As regards reporting of expenses after allocation, you can use functionality of assessment cycle, wherein cost gets apportioned to under secondary cost element. Hence if you excluse secondary cost element then you still will be able to get expense report on the service csost center.
    Regards
    Rakesh Pawaskar

  • Resrticting Goods receipt based on cost centre in EBP Version 2.0

    Hi,
    I am working with EBP2.0 version & I need to know whether I can restrict the GR with ref. to cost centre in EBP. (ie. Receive any order functionality. We have not defaulted any cost centre & the user will enter the cost centre & GL a/c at the time of creation of shopping cart only.
    Is it possible to restrict the Goods Receipt with ref. to cost centre in EBP2.0 version. If so then please let me know how to go about it.
    Your immediate response is very much appreciated.
    Regards
    Raghu

    Hi  S.R.P.         
        There is no control  between GI and GR, you have to make a control using UDF
    for example
    1.Add UDF in GR called GI Number
    2.and make this field mandatory using SP
    3.Ask the user to enter GI number
    4.If user enter GI number in GR then choose the item code in GR means,using FMS you can also do automatically load a Warehouse,price,Account code what ever in GI.
    5.using sql query report u will get control
    Edited by: Prasanna s on Sep 16, 2009 10:33 AM

  • GL account and Cost Centre Info

    Hi All
    Where does the GL account / Chart of accounts / Cost centre information gets stored in SRM System?
    Are there any specific tables for this..
    Thanks and Regards

    Hi
    All the data that you mention is held in ERP. SRM uses RFC connections to validate if the data that a user enters is correct.
    The cost centres that a user can select can be maintained in the org structure or the search help functionality (that requires a dialog rfc connection) can be activated.
    The default GL account for a product category can be maintained within the SRM Server -> Cross-Application Basic Settings -> Account Assignment -> Define G/L Account for Product Category and Account Assignment Category img activity.
    Hope this answers a couple of your queries.
    Keith

  • Add cost centre name field or description in line item reports

    Dear all,
    How can the cost centre name or description be added in a report's lines (i.e. FBL1N). These fields (columns) are not included in the reports and need to add them. I have tried through special fields to include them but the table CSKSZ and fields KTEXT (Cost Centre name) and LTEXT (Cost centre description) are not included.
    Regards,
    George

    Hello,
    You must use business transaction event 1650 for adding special field to FBL*N reports.
    Please refer OSS note below.
    Note 984305 - Line item: Definition of special fields (T021S)
    I hope it helps to you.
    Regards,
    Burak

  • Cost centre and GL A/c is not getting picked up for tax expenses

    i have  incoice from vendor for $ 106 and i pay $100 to vendor and $6 in tax
    i want to use the GL A/c and cost centre to pay $6 in tax. we want to use the same GL A/c and cost centre related to that PO only for tax expenses. and for another PO  another GL and cost centre related to that PO for tax exp
    What configuration i need?

    Hi,
    your tax expense is a liability a/c which is not supposed to be booked in cost centre.
    what is the purpose of bringing it to the cost centre..
    Regards,
    Divraj

  • Difference between master cost centre and sender cost centre

    Hi All,
    could you please tell the difference between master and sender cost centre.
    I want this information very urgent.
    Thanks rakesh

    Hi!
    The master CT is a default Ct in your system.
    In this case the logical pair for master is the "child" cost center -> primary and secondary cost centers..
    The sender CT is a different thing logically -> this will be credited while posting. The sender is the one who claims money.
    To this type the logical pair is the receiver cost center. While posting the receivers cost center will be debited.
    Hope this helps!
    Best regards,
    Zsolt

Maybe you are looking for

  • Status report template activation and assignment

    Hi,    when I try to create Status report after selecting the Document folder and clicking the New Status report in  Status Report tab of cproject,  an error message is appearing as 'No templates for status reports have been entered for the project t

  • File fetch from external souce...  http adapter, file adapter, or...

    Hi - Hopefully this is a straight-forward question. I need to fetch a file from an external source (vendor) using a url that they provided us. Secondly, the url and file change each run. Here is the scenario: #1. - our side (PI 7.11) calls their webs

  • CROSS COMPANY POSTINGS

    Dear All,      I am having a doubt regarding the cross company postings. The issue what i am facing is I am having two company codes let it be A & B, now that co.code A had purchased from the vendor V and the payment to vendor V has to be made throug

  • Essbase studio export

    I want to deploy a cube design from development to production and I am using the file -> export feature of studio. when I export a cube, i just have the cube selected with "include associated essbase models with cube schemas" ticked. when i import th

  • How do i remove the settings and preferences of the iCloud Control Panel?

    I had problems with my Office 365 (Outlook 2013) and making it work with iCloud. I repaired the install of my office 2013, but the iCloud Control Panel keeps giving me an error as it thinks the icloud integration for Outlook 2013 is still installed..