Clear inspection lot for defect items

Hi All,
What is the process if i found the inspection lot have defect
how do i create the notification .and result. after moved it to blocked stock.
how can i close the nodification and change the result and do the ud for the lot.

Hi
What is the process if i found the inspection lot have defect
If inpsection lot have defect then,You can go to defect recording & record the defect against operation or nspection lot or against a MIC.
Every Defect has defect class which will decide whether the notification os to be kept open or close after UD is taken.
This is part of customization.
how do i create the notification .and result. after moved it to blocked stock.
While creating inspection type in customization through QCC3--> Inspection lot creation >Idefine insp types->say 01 inspection type here maintain F2 type of defualt notification which will trigger after defect is recorded.
You can record the results.Then from UD stock posting screen in QA11/QA32 you can post material to block stock.This is also possible through action box of notification.
how can i close the nodification and change the result and do the ud for the lot
Once Defect are reorded you can go to notification.Assign the Tasks to Users.Complete the tasks ^ sucessfuly close it.Check the status of all task must be TSCO TSSC.
You need not to change the results recorded again after material is OK as this is First yield of the lot.
Then move material form Block stock through notification. & close the notification.
I hope this will help
Regards
Sujit

Similar Messages

  • GRN With 2line items(material,batch same)one inspection lot for 2line items

    Dear Experts
    As and when we make a GRN with 2 line items and same batch number we enter no. of containers differently but only the number from the first line item is flowing into the Inspection lot origin.We are creating only one inspection lot for 2 line items as the batch number is same for the items.
    1. In material master i have given 01 inspection type ( with control inslot.. Each material document,batch, storage location) :---
    this is the reason system is creating only one inspection lot.
    i am entering manually same batch number for 2line items...
    Here my problem is ... while giving UD... SYSTEM IS PICKING ONLY FIRST LINE ITEM NO.OF CONTAINER... IT HAS TO BE BOTH LINE ITEMS CONTAINERS.... IT IS PICKING BOTH LINE ITEMS QUANTITY... NO.CONTAINER ONLY IT IS NOT PICKING....
    Waitting for  experts reply

    Hi,
    As per your query if you put in MM forums then you will get the reply immly.
    Anil

  • Inspection lot for defects

    Hi friends,
    If during inprocess/final inspection, inspection lot is generated for 30 nos. now i record 5 nos defect,5 nos scrap,20 nos ok.
    so can i post the 20 nos into unrestricted use.
    Now if i want to do rework on the 5 nos defect,  and the 5 nos are ok, how is the inspection lot generated in this case.

    Dear Nandi
    so can i post the 20 nos into unrestricted use.
    Yes, you can post 20 into Unrestricted, 5 into Blocked, and 5 into Scrap.
    now, if you want inspection lot after rework, you can go with "Inspection lot for material Movement".
    Assign, 08 inspection type in Material master, Create inspection plan with Usage: 09.
    and transfer that material from Blocked to Quality using 349 movement.you will get Inspection lot.
    Regards,
    Amol.
    Edited by: Amolbook on Dec 1, 2011 7:59 AM

  • QM Lot for Defect Items

    hi guys,
    Inspection lot for FERT were created, results recording was done for the lot qty (20 Nos), and 18 nos were accepted.
    For the balance 2 nos defects recording was done and notification was raised (q3), then qm order was raised via notification.
    my problem's are
    when will be new lot created for balance 2 nos?
    how to confirm the qm order?
    i.e, some consumbles and activity (Lbr hrs) were used, i need to confirm the same and close the order,
    pnts will be given
    tks
    murali

    Are we talking about an 04 lot?  If so, you would post the 18 to unrestrcited and the other two to "Other material" where you would post it to another batch.
    Craig

  • How to create an inspection lot for each line item of the Purchase order?

    Hi,
    How to create an inspection lot for each line item of the Purchase order ?
    In detail if possible.

    Hi
       please check this
    [thread|Create Inspection Lot;

  • One inspection lot for multiple materials of purchase order line items

    Hi All,
    My client requirement is one inspection lot for multiple materials of purchase order line items.
    Please share your thoughts.
    Thanks in advance for early reply.
    Regards,
    Jishu

    I totally agree with Amol.
    I don't think I would touch that development nor would I ever tell a client it could reliably be done through development.
    Knowing what I know about the table structures, I don't think you could create any development for this that could use a significant amount of the existing tables and functionality.  I think you'd have to create all your own Z tables and basically rebuild the functionality.  Tying it back in with SAP data will be difficult.
    You're even looking at all custom screens for your results recording and UD as well.  And if you have follow-on functions like batch classification requirements, batch determination, COA publication, results copy functions, use of DMR and sampling procedures, physical samples, quality notifications, etc. etc.. you could be looking a whole lot of development.
    Craig

  • Unable to clear Inspection Lot

    Dear Sirs,
    I have a material with Inspection Type - 0101
    The inspection lot of this material has the following status -CRTD,PREQ,CHCR,SPRQ,IRCH
    Unable to clear inspection lot
    in qa02 - insp specications tab -- while using Tasklist / Spec --> following message is coming
    No Inspection Plan could be found
    In samples tab -- sample size could not calculated
    Please help

    Dear
    -In this case you create one inspection plan through QP01 for material code.
    -Assigned the inspection plan through QA02 (At the time of assignment Key date should be current)
    -Calculate the sample size by clicking over Sample tab and then Save the document.
    -Status of inspection lot will get changed to REL.
    -Proceed for the further transactions like QE11 to QA11
    AYK

  • Enhancement-One inspection lot for early lot and serial profile

    Hi,
    I have a requirement shown below.
    Can anyone guide me to proceed this Enhancement from the start?
    Inspection lot for production order is created at production order release, when the finished good has a serialnumber profile assigned in the materials master and the serialnumbers are captured in the handling unit assigned to the production order, the system will create another inspection lot.
    <i>Required system enhancement:</i>
    Only 1 inspection lot per production order should be generated.
    <b>NB.</b> Without this enhancement both inspection lots created for the production order have to be closed to be able to close the production order.

    Please try with sub-routine: userexit_move_field_to_lips or userexit_save_document of include: MV50AFZ1.
    I guess clearing LIPS-QPLOS for specific conditions would do the trick for you..
    <b>Reward points</b>
    Regards

  • Block goods receipt if open inspection lot for source inspection (SAP QM)

    hello!
    i would like to block the goods receipt for a purchase order item, if there is an open inspection lot for source inspection. i know how to block, if it rejected, but not what to do in this case.
    thanks!
    matthias

    Hi matthias,
    can you tell me how to block GR if inspection is rejected in source inspection??? as you said u know. please let me know.
    Thanks!!
    vinay

  • Inspection Lot for co-product & By Product

    Dear Friends,
    How to manage inspection lot for Co- products in production
    Is there any specific inspection type
    Thanks & Regards
    Raj

    Hi raj
    531 Goods receipt from by-product from the order
    The goods receipt of a by-product usually refers to an order, but it can be entered without a reference.
    If a component is entered with a negative quantity in the order, a reservation item is created with 531 (instead of 261). The receipt of a by-product can be entered when the component for the order is withdrawn from stock or it can be entered as another type of goods receipt.
    Possible special stock indicator: E, Q
    Acivate 05 inspection type for Co-product.
    You can also try this by MB1C transaction.against producton order
    Also check the mvt type 545 and 581
    Check this will work
    Regards

  • MFPR - Processing Inspection Lots for Production versions issue

    Hello,
    User are not able to seeing line item to create inspection lot for a specific part number.
    I checked inspection set up in  material master, rate routing, and compared with similar part numbers.It all looks good to me.
    Any help would be greatly appreciated!!
    Regards,
    Owais

    In REM Inspection lot for Inprocess is generated for header material for which you actually define "production version".
    Line items can not be seen in MFPR.

  • In QA16 i given material doc no ,i am not getting inspection lots for UD

    iam using QA16 for quality inspection .
    Iam given material doc no in QA16,but iam not getting inspection lots for UD(usage decession).its comming empty screen in QA16.
    iam using multiple UD at a time.

    Dear check this below points.
    1. Check if Material Master Auto usage decision has been checked.
    2.All characteristics should be optional if not make all the char as "Optional " through control indicator This can be done for next lots only.
    3.All chracteristics must be calculated and status should be 5 completed and no defect recording done.
    4. Check mic indicator activated in material master and you have to do RR for this inspection lot or u can force fully complete all MICs and male IL status INSP and check again in QA16
    5.Did you selected releavant UD selected set for inspection lot in QA16.
    Cheers
    KK

  • Customer number not in the inspection lot for a make to order scenario

    Hi All,
    I know that standard SAP will get the Customer number into Insp. lot only for insp. types 10/11/12.  I am wondering if someone know a way to get the customer no. into insp. lot for insp. type 04 where the material is make-to-order scenario and the Production/Process order has the Sales order and customer no. without activating User-exit.  The quality users want to be able to see the customer no. in insp. lot without having them to go to process order. 
    It makes no sense to me why the customer no. is not brought into insp. lot when that is available in the Prod/process order, which can further be used to select the customer specific insp. plans for 04 insp. type Insp. lot without using Variant configuration.
    Any light on this topic is appreciated.
    Thanks.

    Hi Srikant,
    I guess.........
    Normally the inspection lot refers the triggering document that are the trigger cause for them.
    - Inspection type 01: - Purchase Order and GR material document.
    - Inspection type 03: - Pro. Order Number
    The same way...
    The inspection type 10\11\12 are purely related to the SD, and directly integrates QM and SD. Hence in the inspection lot for the inspection types directly integrated to SD, it will furnish the Sales order number \ Customer.
    But the inspection type 04 is purely have it's relation to Production process. So it will have the details related to integrations it has i.e. the "Pro. Order." Hence it integrates QM-PP, it have the data related to PP (Pro Order), not the SD's one.
    But I think one way you can achieve it,
    Assign the Customer number also to the inspection plan along with the Material. So I think at the time of assigning the inspection plan to the inspection lot, it will refer the Customer number also and will display the Customer number along with Task list Group\Group Counter, in the inspection specification screen in QA03/02
    Regards,
    Shyamal

  • Automatic creation of inspection lot for Expired Batches

    Hi All,
    I am in one trouble and need some help in above scenario.
    I am able to create inspection lot for batches about to expire, but how to create inspection lots for batches which were already expired or which next inspection date already missed?
    Master data like '09' inspection type, inspection plan is already maintained.
    Second question, is QA07 also affect on special stocks like vendor stock or project stock etc?
    Immediate response will be appreciated.
    Thanks

    Hi
    To meet you above mentioned requirement you have to modify the program RQAAAS10 as per your logic both to create lot for Expired Material and to consider project stock or vendor stock as In standard SAP these stock are not considered.
    regards
    Manish

  • Creation of one inspection lot for more than 1physical sample

    hello SAP,
    we have one common question.I have created 3 physical sample 20000006,2000007,2000008 and now i want to create one inspection lot for these 3 physical sample through QPR5 Transaction but system is generating each inspection lot for each physical sample which is wrong process. this is common scenario for most of the industry.SO please clarify and provide the solution

    Hi,
    I hope this solution gives some way out for you to solve your problem . I assume the sample is for  the same material , phy. sample type and category
    Create a new physical-sample drawing with refernce to :
    Using this function, you can create a new physical-sample drawing (with one or more physical samples) that references:
    An inspection lot
    A production order or process order
    A production version
    You use this function to create physical samples that have not been planned in a sample-drawing procedure and which you can draw from a production process according to your specific needs. In an inspection during production, for example, you can draw physical samples from the process on the basis of time or quantity (for example, a physical sample every three hours or for every 1000 liters of material produced). You can freely specify the inspection-relevant operations in which you want to inspect the physical samples for the new physical-sample drawing.
    please do let us know wether you were able to create one inspection lot .Or else please ellaborate the question step wise t-code and functions Will try to find a solution .
    cheers
    kp
    source of information : SAP

Maybe you are looking for