Collective conversion of planned order to one production order

Dear all,
1. I have N number of pld ord for same material so i need to convert as production order with cumulative quantity.
Because to reduce  Issing and confirming and receiving of number of production orders.
2. I need to create Number of production order with diffferent material numbers  in one screen with different production order number.
Because per day i need to create more number of production order with different material number. If i create one by one it will consume more time as well as its not practical possible for our business scenario.
Pls let me know any standards are available in SAP.
Regards,
S.Suresh.

Dear Suresh,
You can convert Planned Orders into Production order collectively as a mass maintanance in CO41 Tcode.
Revert if any doubt in case using above tcode.
Further if you wish to have one production order against multiple planned orders it is not possible as per Standard SAP.
You can convert to each planned order into individual production order not to single production order.
If you wish clubbed production order then better you use Individual / Collective Indicator  as
2     Collective requirements only
Then you will get cumulative planned orders only against each material and you can convert all of them cumulatively to production orders in CO41 as a mass maintanance.
Hope your problem resolves.
Regards,
Tejas
Regards,
Tejas

Similar Messages

  • Field setting when collective conversion from planned order to PR

    Dear expert:
    Is there any way(except ABAP enhancement) to add the field "tracking number" in MD15 when I conduct collective conversion from planned order to PR. Seems in standard config this field in not included in this screen. I have set this field as a mandatory field, but even though when I conduct the conversion, this field still can not be displayed in the MD15 conversion screen.

    Hi,
    There are following T. Codes to convert Planned Order to PR;
    MD14 - Individual Conversion
    MD15 - Collective Conversion
    MDUM - In Background
    Also MD04
    User Exit is LMDZU001 - User exits in additional planning

  • Collective conversion of planned order

    hello experts,
                       i have some planned orders, while doing the collective converison in production order by CO41 i m unable to do so, the system is giving the error message "PLZ MAINTAIN SETTLEMENT RULE" and message number is "ZSD01000", but i can convert these planned orders individually in MDO4, there's no problem in individual conversion in MD04.
    Regards,
    Sarfaraz.

    Dear
    Check ur configuratin settings
    1. U must have maintained Plant Parameters for the Planned Order - Conversion
    In that the profile u have selected, maintain that in the Settlement Profile Customization.
    Use T code - OPPQ for Plant Parameters Settings
    Use T Code - OPKT (Define Settlement)
    Regards
    Samunder Singh

  • Conversion of Planned order into a Production Order.

    Hi All,
             I have one ticket in which I have to change the format of generating serial no.s.This format has to consider
    Basic Start Date while generating it.In our project Serial No is getting generated at the time of Production Order.
    So I have to pass this start date before Prod Order is getting created from a Planned Order.What i want to know is it possible to pass a start date when a Planned Order is getting converted into Prod Order as i think it will be a standard SAP program which will convert a Planned Order into Prod Order.Any suggestions on how to achieve this is most welcome.
    Thanks in Advance,
    Saket

    Hi,
    I am not able to get what is passing the start date.
    Second thing is how you are generating the serial number - manually or automatic?
    If you are generating serial number automatic, then it is not possible to generate it considering the basic start date.
    But if you are entering the serial number manually, then there should not be any problem as system will accept that serial number which you enter at the time of conversion of planned order to production order.
    Regards
    Amit parkhi

  • Partial conversion of Planned orders to Production orders

    Hi all
    I wan tot partially convert planned order to production order. I am able to do this with MD04. Is there a tcode for mass partial conversion. CO41 does not allow a partial conversion. Is there a way I can collectively do a partial conversion.
    thanks

    Hi John,
    To the best of my knowledge there is no t-code to do a mass partial conversion of planned orders.
    You can try with a lsmw recording of t-code co48 & then input your planned order numbers with the qty to be partially converted or alternatively use co41, change the qty & convert the planned orders, but with this you will need to re-run MRP to create another planned order for the balance qty.
    Hope the above helps.
    Regards,
    Vivek

  • Program PPBICO40 for conversion of planned orders to production order

    Hi,
    The program PPBICO40 is for conversion of planned orders to production orders in the background job.But while set up of variant it is asking me for peson who created error folder and recipient.I want to know the significance of these two fields and how these are useful.
    Please throw some light on this.
    Thanks in advance,
    Ravi

    Dear,
    PPBICO40 the non-convertible planned orders are put together in one batch input session and can be postprocessed with batch input tools. It is possible to create a separate error session for each MRP controller.
    Error folder for each MRP controller: creates a separate error folder for each MRP controller.
    Receive folder according to view: If the indicator is set, the error folder is not deleted after processing in batch input.
    Creator of the error folder: User who is entered as creator in the error folder .
    Send mail: Sends a mail to the respective MRP controllers during the creation of a batch input session. If the indicator 'Error folder per MRP controller' is not set, the mail is sent to 'Recipient (alternative)'.
    Express document: sends mail as an express document.
    Recipient (alternative): Recipient of the mail, if no recipient is specified in the material requirements planning master record of the MRP controller responsible .
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Auto conversion of planned order to production orders

    Hi Gurus,
    Few days back I posted a question on; Auto conversion of planned order to production orders.
    http://forums.sdn.sap.com/thread.jspa?threadID=2135568&tstart=0
    There is standard SAP Transaction to run a batch job. no need to use - user exit or a BAPI
    Follow this procedure:
    TCode: COHV
    on the initial screen; select "CHECK BOX" for planned orders and deselect production orders.
    select mass processing tab.
    Function: 210 Convert planned orders.
    On Menu-Programs-Execute in background
    Thanks

    HI Alok,
    I was looking at CO41 and there is only one small problem with that. You have to give an 'Order Type' as a input. And I don't see 'Execute in the background' anywhere. I think I have to create a job using wizard in SM36.
    Please correct me if I'm wrong.
    Thanks

  • Creation of production order from manual or conversion from Planned Order

    Hello Guru,
    i would like to know why does the production finish date differ when we do manual and conversion of planned order into a production order?
    Thanks

    Ryan,
    When a planned order is created it just uses the Inhouse production time defined to derive the dates, whereas incase of production orders, it would try to schedule the operation and based on that the scheduled dates are derived. The other possibility is the different scheduling types are used for Planned order and Production order. Check transaction OPU5 and OPU3
    Regards,
    Prasobh

  • BUG in  Conversion of Planned order to Production Order.

    Dear all,
    I got an error while conversion of planned order to production order are as follows,
    No Default values maintained for op.generation for order type ZFT1(matlPILSF002).
    Can anyone please guide me to proceed further.
    Kumar.

    Hi,
    Root cause behind this problem is, no Routing found.
    First complete below settings.
    - Go to OPJG And create defult Operation creation in case of no Routing found.This setting will generate the default Operation incase of no routing found during Order creation.
    - In T.code OPJF Create automatic selection parameters (Selection ID) for Routing.
    - In T.Code OPL8 Maintain Selection ID for Routing and also maintain type of Routing selection (3 - Automatic Routing selection)
    Regards,
    Dhaval

  • Conversion of planned orders to production orders

    Hi,
    we are doing mass conversion of planned orders to production orders and performing capacity availability check, how system will give log information based on these two things,
    when i perform availability check at time of order creation and will not allow to create if anything is missing (i selected user decides option in configuration), does it show any error log report and where can i see.
    When i perform availability check at time of release, if anything missing it will not allow to release and give a choice for a user to release in normal production order creation process, how it will work in mass conversion. is there any standard report to look at missing planned orders so that users will come to know and then decides whether to convert to production order or not.
    thanks in advance.

    Dear ,
    In SM38-Enter PPBICO40 -Execute -Here you need to Mark the Output log option with Erros only or Error Folder for each MRP controller  .Frist you do it in test mode and then remove test mode , mark the Output log option as per requured field and check the result .
    refer this useful thread : Program PPBICO40 for conversion of planned orders to production order
    Regards
    JH

  • Partial conversion of planned order into production order of AFS material

    Dear Experts,
    I am working with SAP 6.0 EHP4 with AFS add-on. My material is AFS specific material. I am not able to convert planned order into production order partially from MD04 screen as all the fields in the CO48 screen is grayed out. 
    Please help...
    Regards,
    Alok Tiwari

    Hi,
    I am not able to get what is passing the start date.
    Second thing is how you are generating the serial number - manually or automatic?
    If you are generating serial number automatic, then it is not possible to generate it considering the basic start date.
    But if you are entering the serial number manually, then there should not be any problem as system will accept that serial number which you enter at the time of conversion of planned order to production order.
    Regards
    Amit parkhi

  • Bug in Conversion 4m Planned Order to Production Order.

    Hi guys,
    While conversion of Planned order to Production Order i got the below error,
    "YOU CANNOT MAKE AN ASSIGNMENT TO MAKE-TO-ORDER STOCK"
    Message # CO684
    Settings i ve done,
    MRP3 View for this particular Material i have selected Stratergy as 20.
    Please help me to resolve this issue,and what are the settings i need to do.
    Awaiting a positive reply.
    Regards,
    Kumar.S

    Resolved Sucessfully
    Kumar.S

  • Conversion of planned order to production oder.

    hello friends,
    we are making a project,in that we are facing a small problem.
    we made demand management,and mrp run.after we have go
    gone to md04,there we tried to convert planned order to process order, routing is not selected by production order.but if we go to co01,there production order is created.what are the configurations to be made for conversion of planned order to production order.pl help.
    reward points will be given for the best answer.
    regards
    seshagiri

    Dear Seshagiri,
    Tell me after MRP run,for your Finished product,are you able to see planned orders?
    IF so,copy the planned order number and display it in MD13 or directly in MD04 by double clicking on the planned order number and
    click on display button(Press F7).check whether you are able to see BOM components and Detailed.scheduling tab key assuming in
    MRP control parameter you have given value 2 for scheduling.
    IF present and during conversion are you facing the problem?
    Please clear these doubts.
    Regards
    Mangalraj.S

  • Conversion of planned orders to prod orders in background

    hi All
    Is there any program for mass conversion of planned orders in production orders which we can schedule in background.
    Amit

    Hi Amit,
    Try below method
    TCode: COHV (tab selection --- plant and etc...,, tab mass processing --- function - conveted planned order, order type - PP01, collective orders - do not collective orders)
    after Menu -- Program --- Excute in background -- set properties -- to set send SAP spooler --- click button immediate then check box periodic job and periodic values after save
    to monitor and get spool request bcackground this job
    TCode SM37
    or
    you can create background job using TCode SM36
    pls create varient for COHV
    PRG: PPIO_ENTRY with Varient
    Regards,
    Sankaran

  • Automatic conversion of planned orders

    Hi PP Gurus,
    I have a requirement to convert planned orders to production orders automatically. I believe SAP standard does not offer this functionality.
    The possible solution seems to be writing new program which could be a copy of C041 transaction code.
    Did someone ever worked on this functionality?
    Request to share your experience and possibilities on this - Thanks
    Regards
    Seshu

    Dear Seshu,
    In my understanding there is no T Code for making the conversion of planned order into a production order as an automatic
    process.
    But you can use the T code CO41 for converting a list of planned order's into production orders.
    In many cases the planned order is only a proposal and only after converting it into a production order and releasing it then the
    exact shop floor activities starts like Good's issue.This activity is done by a production scheduler.So in case if you develop a
    program to convert automatically,then reservation gets generated for all the production orders, which is not recommended.
    Also check this link,
    http://www.sap-img.com/production/automatic-conversion-to-production-orders.htm
    Check and revert back.
    Regards
    Mangalraj.S
    Edited by: Mangalraj.S on Aug 11, 2009 10:04 PM