Components assignment to Sub operation
Hi Gurus
I have a situation where i need to assign a components to Sub operations. System is not showing any sub operations to assign to BOM components.
My client wants the sub operations to be created and some components assigned to it. So when milestone confirmation is done for the primary operation all the components and the operations should get backflushed.
Please suggest if there is any configuration step needed for this.
Thanks in advance
Quantum.
Hi,
Refer below link:
[Assigning Material Components to Operations/sub-Operations|http://help.sap.com/saphelp_erp60_sp/helpdata/en/92/91a815a9d511d189090000e8323492/content.htm]
Regards,
Siva
Similar Messages
-
Assignment of material to sub-operations
Hi friends,
Please tell me whether we can assign a item from the BOM to a Sub-operation?
I tried to assign it but it is getting assigned to the main operation only?
please throw some clarity on it.
regards
RameshHi,
A sub-operation is used when a detailed planning of the process to be done in an (main) operation is required. The material component is assigned to the first operation by default.If you want to assign the component to a different operation then you can use component allocation tab.
Hence, there is no need to assign the material to a sub-operation since the main operation is already assigned a material.
Hope this helps.
Regards,
Senthilkumar -
Advantage of sub operations.
Hi ,
Whats the advantage of suboperations.how Is it different in a process?
why cant the sub operation be a regular operation in routing .
what is thebenefit we get by using suboperations technically or is it just a business process.Hi,
you can use sub-operations to assign several people or machine that are required at the same time, to an operation. An sub-operation can be costed, but can only be scheduled relative to superior operation. You can cumulate standard values from sub-operations on the corresponding operation. You can determine whether sub-operations belonging to an operation are copied into the production order.
Example:
When a Object is Passing through A MILLING Machine Or through A AUTO lathe where upon completion the object need to be performed with DE-Burring In this scenario we usually adopt sub-operations
Depending on your requirements, a sub-operation can contain the following data:
1)A control key, which specifies
Whether costs are determined for the sub-operation
Whether the sub-operation is processed internally or externally by a vendor.
Whether, afterwards in order processing, a confirmation can or must be made
2)A wage type for settling incentive wages
3)Standard values, which are planned values for the activities to be performed in a sub-operation.
4)External processing data, which form the basis for externally processing sub-operations
5)User-defined fields with any customer-defined data
Where as You cannot assign material components, production resources/tools nor inspection characteristics to sub-operations, only to operations.
pavan -
Component materials incorrectly assigned to superior operation in process order
One of my manufacturing facilities is having a problem with components not printing on process order output.
In all cases, the master recipes themselves look fine when reviewed in C203. The components are properly allocated to phases (not superior operations). But when the process orders are generated, certain components are being assigned in the process orders themselves to the first superior operation, instead of to the phase that is indicated in the master recipe. Here is an example.
Here is the master recipe operation information as seen in C203:
And here is the material assignment list as seen in C203. Note that component material MM6030 is assigned to Phase 0035:
But when the process order is created, that same component material MM6030 is now assigned to superior operation 0001:
Here is some additional information that I was able to eke out of the folks at the manufacturing facility:
The operations in the master recipe did NOT originally contain operation 0001. It was added to the recipe in C202 after the recipe was initially saved.
Component Material MM6030 was not originally part of the BOM. It was added via C202 after the recipe was initially saved. A different material was originally in its place, and was assigned to a different phase. After the MM6030 was added to the BOM, the assignment field was blank, and the user assigned it to phase 0035.
Has anyone ever encountered a similar issue? If so, how was it resolved?Hi ,
Possibility , in C202 , user may have changes the BOM first and re-assign the phase but in process order level Read PP master did not call
Another possibility manually change the process order component and assign this in Phase in COR2 .Please check whether it has been added manually in order level .
Regards
JH -
How to fetch Routing Sub Operation details
hi all,
I am downloading routing details from tables MAPL PLKO PLPO . But I am unable to find routing sub operation details.
Could you all help me how and from where to retrieve the information
Thanks.Routing
<b>PLPO Routing Operation Details
PLKO Routing Header Details
MAPL Routing Link to Material
PLAB Relationships - Standard Network
PLAS Task List - Selection of Operations
PLMZ Component Allocation
PLPH CAPP Sub-operations
PLFH PRT Allocation
PLWP Maintenance Package Allocation
PLMK Inspection Characteristics
PLAH</b>
Engineering Change Management
AENR Customer and priority
AEOI Revision Numbers
Work Center
CRHD Workcenter Header Data
CRCA Workcenter Capacity Allocation
CRCO Workcenter Cost Center Assignment
CRHH Hierarchy Header
CRHS Hierarchy Structure
CRTX Workcenter Text
KAKO Capacity Header
KAZY Intervals of Capacity
Bill of Material
STPO BOM Item Details
STPU BOM Sub Items (designators)
STKO BOM Header Details
MAST BOM Group to Material
STZU BOM History Records
STAS BOM Item Selection
STPF BOM Explosion Structure
Line Design
LDLH Line Hierarchy Header
LDLP Line Hierarchy Items
LDLT Line Hierarchy Takt Times
LDLBC Takts/No. Individual Capacities per Line
LDLBH Line Balance Header
LDLBP Line Balance Items
LDLBT Line Hierarchy Entry and Exit Takts
PRT's
CRFH PRT Master Data
CRVD_A Link of PRT to Document
CRVD_B Link of Document to PRT
CRVE_A Assignment of PRT data to Equipment
CRVE_B Assignment of equipment to PRT data
CRVM_A Link of PRT data to Material
CRVM_B Link of Material to PRT data
CRVS_A Link of PRT Internal number to PRT External number
CRVS_B Link of PRT External number to PRT Internal number
Thanks
Seshu -
Key Operation and Sub operation PM order
Hi,
What is the key (table - field) which determines the relationship between the main operation and the sub operation?
I mean how can you detemrine that suboperation X is indeed a sub operation of this particular operation Y? You have AUFNR, AUFPL, but i'm missing somethin...
regards,
bertthanks,
APLZL of main operation and SUMNR of suboperation -
Hi, what is the control key used for sub-operations for which we do not want seperate confirmation. when main operation confirms, the sub-operation should get confirm automatically. please advise.
hi,
You can use PP03 or *PP05 * or any other which dont have tick for confirmation required.
only thing is that , other details also you need to check for.
Depending on your requirements, a sub-operation can contain the following data:
A control key, which specifies
Whether costs are determined for the sub-operation
Whether the sub-operation is processed internally or externally by a vendor.
Whether, afterwards in order processing, a confirmation can or must be made
A wage type for settling incentive wages
Standard values, which are planned values for the activities to be performed in a sub-operation.
External processing data, which form the basis for externally processing sub-operations
User-defined fields with any customer-defined data
Check and revert back
regards
Ritesh -
Components required for each operation
Hi Friends,
In production order there are many operations. How can I know components required for each operation.
Thanks,
KiranHi Kiran.
Select the operation in the prodcution order.
Hit component tab below.
You will find the component attached to the operation.
BR
Subbu. -
TIME TICKET CONFIRMATION IS NOT EXICUTING AT SUB OPERATION
Hi,
We are trying to post Time ticket Confirmation at sub-operation level
through standard web service. Up to Operation level,standard web
service is working fine but problem arises when we do posting at sub-operation
level.Web service is not working for sub operation level.
Please find attached step wise details of the process which we
are following.Dear Sir,
As per your reply I have set the Act. Data in OPK4. Screen areas in OPK0 for Dates were already set open. After doing the OPK4 settings if I am setting execution start and finish time for a phase in COR6N as 10:00:00 and 10:15:00 accordingly in the order for that particular phase in the details screen start and finish time (in the Dates tab) is updating but in the Qty/activities tab the confirmed time is not updating to 0.25 hrs (it is showing 0). Even during COR6N after putting start and finish time in the Dates tab the activity in the u201DTo confirmu201D tab is not updating . When I click actual data in COR6N screen, that activity(time) is picking up the value as per the scheduling through recipe. And only if I manually change that time to 0.25 hr, then it is updating in the Qty/activities tab in details screen of that phase in the order. But I want to select the Execution start and Finish time in Dates tab of COR6N and want the system to update the figure in Activities tab of COR6N as the calculated difference between start and finish and the same updated value should be transferred to the Qty/activities tab of the phase details in the order. Please suggest how to achieve this....
Regards,
Sunit -
Operation and Sub operation link in routing -reg
Hi,
In one of our report development we have to seggregate the operation number wise suboperations
which table and fields we have to use ?
we have to down load all the operations and sub operations for a given routing from the system and should be able to display for this operation these are all the sub operations and display their operation timings
please guide
regards,
Madhu KiranHi,
If i go to some operation and add one sub operation for it , i am not getting in the tables both operation and sub operation
i think both are getting stored in the same field
can some one give some logic of fields connection to fetch the sub operatiosn of an operation ?
PLPH table has no entries at all in our system
i try to use PLPO and PLAS
i require basic logic of flow
how to get the suboperations of an operation
pl help
regards,
madhu kiran -
hi sap gurus,
while creatng routing we want to create suboperations for the finished product. pls tell the flow path how to create suboperations with transaction code.
regards and thaks in advance
muralidhar.t1. Create the operation as usual (say 0010)
2. In the next line again give the main operation number & in the Suboperation column i.e. column next to operation i.e. in SOp enter the suboperation no u want i.e. say 0002. The moment u enter Sub operation no and press enter; system will prompt u to enter time for activities and finally it is created...
All the other steps are similar to creating operation
Once it is created; you can see a "check box" under Sub operation for 0010 (before base quantity)
Also u click on that Sub operations and can see the details within it....
Hope it clarifies
Rgds -
Need to confirm production order on operation,sub-operation & sub-sub-operation
Hi Friends,
I've a requirement to confirm order below sub operation level. eg There is operation 100,200,300....and sub operation 110,120,130...further, below these sub operation, there is sub-sub operation like 111,112 for sub operation 110 and 211,212 for sub operation 210.
Requirement is,till sub operation we can confirm the order but below this level we can't confirm.Is there any solution in standard SAP.
Thanks
PankajDear Pankaj,
What is the reason behind creating a sub-operation for another sub-operation?
For meeting what business requirement, this has been mapped so?
In my understanding this is not possible in standard SAP.
Check and come with your further queries.
Regards
Mangalraj.S -
Confirmation for sub-operation
Hi Expert,
As we know that confirmation has to be maintaned for each work order confirmation.
Current condition, we also have to maintained confirmation for each work order sub-operation.
Is there any possibility that only operation level of work order that need to be confirmed? instead of sub-operation level? in assumption that work order created with both operation and sub-operation
illiustration:
Operation 0010 Greasing
Sub operation 0010/0011 cleanning
Sub operation 0010/0012 inspection
Confirmation conducted for operation 0010 Greasing only, instead of all operation and sub operations
Thanks
Pls Help
RgdsLeni,
There is nothing in the standard system that would force you to create confirmations at either operation or sub-operation level (unless you have done something in your system)
PeteA -
Assigning Componets to operation in PM.
Hi All,
While creating task list(tcode IA05), i need to assign Componets to operation activity.Now in the componet assignment, the material deatils(material,quantity etc) are to be picked from different storage location of same plant( as same material is present in more than one storage location within same plant).But here the problem is that the storage location field "Sloc" is uneditable i.e grayed.How to select material from multiple storage location?
Thanks
DebDebrata,
The storage location field is not available for a task list component. One option you may want to explore is to use the supply area functionality for a work center. This is a way of setting the storage location for a component in a work order based on the work center assigned to the operation. You create supply areas in PK05 and then assign them to work centers in IR02.
Hope this helps!
Paul -
Please select an appropriate pay group assigned to this operating unit
Hello All ,
A new pay group is created and assigned to the new supplier site and when an invoice is created against that pay group
its is populating an error message saying that Please select an appropriate pay group assigned to this operating unit.
As result I am unable to complete creation of invoice.
Any inputs Suggested ? Appreciate it !
Thanks,
Deepthi.Hi,
Please obtain a FND Debug log on the issue and upload the log to a free hosting site and provide the link here for our reference.
Meanwhile also raise an SR.
Please see:
How to enable and retrieve FND debug log messages (Doc ID 433199.1)
Thanks &
Best Regards,
Maybe you are looking for
-
Error in the iphone music app iOS7 with dozens of empty genius playlists
Im getting an error in the iphone music app in iOS7 with dozens of empty genius playlists even tho genius is OFF in my account settings and genius playlists are not selected for syncing with my iphone 5. All apps, iTunes and iOS 7 are updated. The o
-
OBIEE: Criterias not appearing in Answers query
Hi All, I am trying to include two criterias based on date conditions in Oracle Answers but when I look at the query generated by BI server, I can't see the criterias included in where caluse.Please can u help! Criterias are something like this: CAST
-
Can anyone help me? I've exported the captions into Word, made modification, then imported them back into Captivate. Now I'm seeing square boxes in the exe file that I created. Is there a way to remove them? I'm using version 1. Total confused
-
Avoiding authentication dialog with Plugin1.4
I need to open a URLConnection to a secure part of a webserver, and I get an login dialog box prompting for a username and password, first from the browser, and then from the plugin. Is there any way of integrating the browser's authentication with t
-
Hello, I´m stucked with this problem for 3 weeks now. I´m not able to configure the EAP-TLS autentication. In the "Certificate Store" of the ISE server I have Installed the Root, policy and the Issuing certificates as "trust for client authentication