Consider preventive maintenance schedule into PP order capacity planning

Hi PP experts,
My client's requirement is that when a preventive maintenance order is created in PM module for a particular work center (used in production) on a given date, NO production order (which is processed on that work center) should get released or confirmed. In other words, the capacity should be blocked at all for the subject work center.
Could you please guide how to make this effective?
We are using discrete manufacturing with capacity planning. At the time of PP order release, system shows capacity situation so as to decide whether go-ahead even with overloaded capacity.
Regards,
HKV...

First, you should assign the PP work center in the location tab of the PM equipment which refers this workcenter.
Secondly you should enter the sytem condition in the task list of the equipment.
During preventive schedule  the work center  will be reserved by PM orders for maintenance and this can be seen from capacity planning from PP side.
regards

Similar Messages

  • Preventive Maintenance Schedule

    Hi,
    The issue is monthly as well yearly function wise preventive maintenance schedule is not generating automatically, Actually we uploaded the data in SAP for specific function wise as per monthly schedule, But right now we are not getting the schedule wise calls.
    Production person put the entries as manually through the t-code IW38,
    So, Where will be the mistake or any configuration setting is missing?
    Please help.
    Regards,
    Althaf

    Hi,
    Hope your maintenace plan,task list and items within plan are in place.Also config is in place with no range,call object type as maintenace order,pm order type you have mentioned in plan etc.
    If all of above are in place then check for following:
    1. Check scheduling parameters for both monthly and yearly frequency jobs.Check scheduling period for monthly job it should be greeater than 1 month..suggest to put 365 days.
    2.For yearly jobs your scheduling period should be greater than year,may be you can put 2-5 years so that system can do scheduling on this basis.
    3.Possibly you can restart scheduling thr IP10.You can check scheduled calls by pressing schedule overview list.
    4.You can lso check scheduling overview and do simulation through IP19.Give period in furture for plans and select maint plan simulation in start mode of maint scheduling overview.
    5.If you are able to see calls in scheduling overview then there is a problem in your deadline monitoring.In IP30 check parameters Interval of call objects and it should be nearer to scheduling period you mentioned in IP19.You can crete two different variants for monthly and yearly jobs.So you will able to maintain to differnt IP30 parameters for them.
    Please note unless you give detailed and exact problem we will not able to provide solution.
    People will generally avoid to elaborate like above.So please try to limit and specific to your problem.
    regds,
    atul

  • Regular Preventive Maintenance schedule for xsan volume ??

    hi
    Is there is any weekly , monthly regular Preventive Maintenance schedule which we should perform for xsan volume like defragment , some commands etc
    What are the steps for regular Maintenance for xsan ,servers which apple recommends ?
    thanks

    Hi,
    I do not do such maintainance. However every night a cvfsck -nv is run. This is a readonly file system check. If in the result of this a line exist which says:
    Filesystem would have been modified
    Then a real filesystem check is needed.
    A defrag is only performed on files, not on empty space. It takes very very long, and I do not expect much of it. So I do not do this.
    Hope this helps,
    Regards
    Donald

  • Hardware Preventive Maintenance Schedule

    I'm trying to find a recommended schedule for Sun Server maintanence. If anyone can point me in the right direction it would be greatly appreciated.

    Dear Makarand Gurjar
    The purpose of the report is, every month begining maintenance person will give the list of equipment scheduled for preventive maintenance to production department.  If that list has planned time for preventive maintenance, it will be very useful for them to release the equipment for preventive and plan the production accordingly.  In IW38 / IW39, we will get only the equipment for which preventive maintenance order is created.  Say for Eg. If an equipment is scheduled for every month preventive maintenance and the scheduled date is 25th of every month and call horizan is 90%, then the order will be released only on 22nd.  If we take the report on 1st of the month it will not come.
    In IP24 we can get all the equipment schedule for that month, but in the planned time is not there .
    Regards,
    Babu R

  • Preventive Maintenance Schedule Feature available?

    Hello,
    we want to use CRM on demand as a our service management system. I'm trying to find out if it is possible to create scheduled service requests for assets. I.e. Asset 1 gets a service request created automatically every 3 months, Asset 2 gets one every 6 months, etc.
    Anybody aware of such a feature or add-on?
    Thanks
    Tobias

    Hello Tobias
    I don't think this type of facility is available as of now. But It can be done by developing a webservice application
    Dinesh

  • Maintenance schedule not visible in PAM03 Planning table

    Hi,
    I have read in SAP help that the maintenance planned for vehicles can be seen in PAM03 planning table. But there is no further information about the required customizing steps.
    Who can help?
    Udo

    Hi Dean,
    try this:
    IMG
      > Plant Maintenance and Customer Service
        > Maintenance and Service Processing
          > Pool Asset Management
           > Edit Object Processing
        Application = Pool Asset Management
        Notification Type = M1
        Order type = (blank)
        Dir. Sched = (selected)
    That should give me 10 Points
    Regards and good luck
    Udo

  • Make To Order - Capacity Planning - CM22

    while using transaction CM22, the planning board takes very long time or some times time out. I think that it checks even the planned orders during run. We need to use only production orders. Is this issue relates to sort key? If yes, How can I modify the settings?

    Hi,
    In customization for capacity levelling you must create a new selection profile where you can axclude planned orders by unchecking planned orders indicator. Then you must assign this selection profile to the overall profile called by transaction CM22. You can learn which profile is used behind which transaction from the SAP help link below.
    [http://help.sap.com/saphelp_erp60_sp/helpdata/en/1a/f2f33419ec8d44e10000009b38f844/frameset.htm]
    It would be wise not to make changes on a standart profile and transaction. You can copy the overall profile and create a Z profile with your selection profile as well. This time you can select this Z profile when running transaction CM25. This transaction is designed for working with the overall profile of your choice.
    Regards.

  • How to change duration of Preventive Maintenance cylce in strategy plan?

    Hi,
    How one can change duration of Preventive Maintenance cylce in strategy plan?
    e.g. In IP11 we set Preventive Maintenance schedule as monthly and we want to change it as quarterly i.e. every 3 months from starting date.
    With Best Regards,
    Rajkumar

    Hi Mr Ramesh
    Thanks for reply .
    Kindly guide us about as what steps /Tcode need to be used to perform the following actions as suggested by you :
    a) Delete orders.
    b) Go to IP10 and Do a 'manual call' by entering the planned date to create orders for the deleted packages.
    Or
    Reschedule the Whole Maintance plan by entering appropriate dates.
    c) Also please clarify , that how the new Orders will get generated against the Deleted Orders .
    With Thanks and Rgds
    Sonia

  • Maintenance Schedule Approval

    Hi Experts
    There is a particular requirement at my client side wherein a preventive maintenance schedule has to be approved by maintenance incharge. How can this be mapped into system?
    I tried exploring user status for maintenance plan. In SPRO maintenance plan is being shown as object type for user status, but for some reasons which i couldnt figure out, it (User Status) wasnt assigned to the maintenance plan.
    Please share if somebody has worked upon such requirement before.
    Regards
    Ruhail

    Hi Joey and Balachandar
    Thanks for the response.
    In some industries it is a common practise that maintenance supervisors prepare the preventive schedules and thereafter it is sent to maintenance head of department (Incharge) for approval. Its more or less a formality but it has to be carried out.
    In SAP if approval is sought after scheduling there is no way that it can be changed (Ofcourse schedule schedule can be restarted but calls with status 'called' remain as so). And moreover if it is rejected then it will lead to creation of junk data in the system.
    Maintenance schedules are as such prepared in Excel and approval in form of signature is sought from deptt head.
    Thats why i was interested in knowing if somebody has come across such a requirement before and what could be possible solution be?
    Regards
    Nalin

  • Preventive maintenance and calibration process flow

    Hi Experts,
    I am totally new to Plant Maintenance. My client has the below requirements.
    1) Machine preventive maintenance schedule.(monthly/yearly)
    2) Measuring instruments Calibration.
    3) Maintenece schedules of PRT/Test equipment.
    How to manage all the above requirements. Would be of great help if expalined the entire process flow in detail.

    You can refer following SAP help link to get intro idea about same topic:
    [http://help.sap.com/saphelp_erp60_sp/helpdata/en/b0/df293581dc1f79e10000009b38f889/frameset.htm]
    SDN discussion:
    [Claibration in sap;
    [Calibration Order Process]

  • Not scheduling on manual creation of planned order

    Creating planned order through MD11 and noticed there scheduling not done and capacity planning not done and on doing scheduling manually dates altered and capacity planned which are appearing in CM01 for the respective week
    Planned order created through MRP are fine with scheduling an capacity planning .
    Please let us know what could be a reason for not updating on manual creation.

    Hi
    This is standard behavior of SAP as when you create the planned order through MD11 manually , you need to do the detailed scheduling manually by executing schedule in Edit>Schedule.
    Check this thread:
    Need Automatic Lead-time scheduling in Planned Order using MD11
    Regards,
    Anupam Sharma

  • Machine capacity planning and efficency

    Dear Guru,
    I have number of machines and i want there individual capacity and efficency can we see that by any report or any tcode to see all capacity of machine.What is capacity leveling.
    Is thee any configuration for capacity planning.
    Thanks in advance

    Hi, the following configuration steps involved in the capacity planning: SPRO --> IMG --> PRODUCTION --> CAPACITY REQUIREMENT PLANNING Capacity Requirements Planning: 1) Define time units 2) Define Capacity Category 3) Set up Capacity Planner. 4) Define parameters 5) Define Standard value key. 6) Define Move time matrix. 7) Define Setup matrix. 8) Define Control Key. 9) Define Shift Sequence. 10) Define Key for performance efficiency rate. 11) Define Formula parameters. 12) Specify Scheduling type. 13) Set up Production scheduler group 14) Select Automatically. 15) Define Scheduling parameters for Production orders 16) Define Scheduling parameters for networks. 17) Define Reduction Strategies planned/ production orders. 18) Define Reduction Strategies for network/process orders. 19) Define Control Profile. 20) Define Selection profile. 21) Define time profile. 22) Define Evaluation profile. 23) Define Strategy Profile. You can follow these above configuration steps in capacity planning Yes you need to active your all work center for the finite scheduling at the bottom of capacity view. Use all standard SAP configurations, Capacity Leveling Profile. Define time profile in OPD2. Define the strategy profile in OPDB Define the Overall profiles in OPD0. Then only you need to to active your all work center for the finite scheduling at the bottom of capacity view in work center.(CR02) Then run MRP with scheduling- 2 Lead time scheduling and capacity planning.(MD02) You will get your capacity requirement in CM01, or CM25/CM21. In rem you can use MF50. -
    OR refer below steps Capacity Planning Evaluation: Use this procedure to Evaluate the Capacity of a Work Center (Resource). The same transaction will be used for finding out the Capacity Overload on the Work Center Select Logistics -> Production -> Capacity Planning -> Evaluation ->Work Center View ->Load and go to the Capacity Planning Selection screen (CM01) Through capacity planning : Standard overview :System will show week wise overload in Red Color. If there is no overload then system will show in the normal color. Date wise Capacity can be overviewed. If there were capacity overload, system would show with Red Color indication and Percentage overload can be viewed. Through capacity planning : Standard overview: Details: Date wise, planned process order wise capacity requirement. Through capacity planning : Standard overview: Graphical: Yellow Color indicates capacity lying un-used. Red Color Bars is the indication for Capacity Overload and Blue Color Bars indicate for Capacity available Use this procedure to Level / Schedule the Capacity of a Work Center Capacity Planning - Levelling/Scheduling: Select Logistics ->Production->Capacity Planning -> Levelling -> Work Center View and go to the Planning Table (Graphical) screen (CM21) Key Points u2022 This would be used for Shop floor production scheduling u2022 Capacity Scheduling is mandatory for correct results of Master Production Schedule and Material Requirement Planning For settings: Define formulas for resources: (OP54) IMG -> Production Planning For Process Industries -> Master Data ->Resource->Capacity requirements planning->Formulas for resources->Define formulas for resources. For formula parameters for Resource/workcentre:(OP51) IMG -> Production Planning For Process Industries -> Master Data ->Resource->Capacity requirements planning->Formulas for resources->Define formula parameters for resources-> Standard Value u2013 Define Parameters (OP7B) IMG -> Production Planning For Process Industries -> Master Data ->Resource-> General Data -> Standard value -> Define Parameters Define standard value key(OP19) IMG -> Production Planning For Process Industries -> Master Data ->Resource-> General Data -> Standard value -> Define Standard Value First configure the below settings in the capacity Planning. 1) Define time units Path : SPRO ->Production-> Capacity Requirements planning ->Master Data-> Define Time units (OPCF) 2) Define Capacity Category Path : SPRO ->Production ->Capacity Requirements planning->Master Data-> Capacity Data ->Define Capacity category. 3) Set up Capacity Planner. Path : SPRO ->Production ->Capacity Requirements planning -> Master Data->Capacity Data -> Set up Capacity Planner 4) Define parameters Path : SPRO->Production ->Capacity Requirements planning -> Master Data ->Work Center Data->Standard value ->Define Parameters (OP7B) 5)Define Move time matrix. Path : SPRO -> Production-> Capacity Requirements Planning -> Master Data-> Work Center Data -> Define Move time Matrix (OPCN) 6) Define Setup matrix. Path : SPRO -> Production ->Capacity Requirements Planning -> Master Data -> Routing data -> Define Setup Time Matrix 7)Define Control Key. Path : SPRO-> Production-> Capacity Requirements Planning -> Master Data ->Routing data -> Define Control Key(OPCG) 8) Define Shift Sequence. Path : SPRO -> Production-> Capacity Requirements Planning -> Operations -> Define Shift Sequences (OP4A) 9) Define Key for performance efficiency rate. Path : SPRO-> Production -> Capacity Requirements Planning -> Operations-> Available Capacity-> Define Key Performance Efficiency Rate (OPDU) 11) Specify Scheduling type. Path : SPRO ->Production ->Capacity requirements Planning->Operations->Scheduling ->Specify Scheduling Type (OPJN) 12) Set up Production scheduler group. Path : SPRO ->Production->Capacity requirements Planning -> Operations -> Scheduling -> Set up Production Scheduler Group (OPCH) 13) Select Automatically. Path : SPRO -> Production -> Capacity Requirements Planning ->Operations->Scheduling ->Task List Type-> Select Automatically (OPJF) 14) Define Scheduling parameters for Production orders. Path : SPRO -> Production ->Capacity Requirements Planning-> Operations->Scheduling -> Define Scheduling Parameters for Production orders (OPU3) 15) Define Reduction Strategies planned/ production orders. Spro-> Production->Capacity reqirements planning->operations->Scheduling->Reduction strategies->Define reduction strategies planned-/production order 16) Define Reduction Strategies for network/process orders. Spro-> Production->Capacity reqirements planning->operations->Scheduling->Reduction strategies-> Define reduction strategies for network/process order 17) Define Selection profile. Spro->Production->Capacity requirements Planning->Evalution->Profiles-> Define selection profiles Hope clear to u. Regards Alok

  • Setting needed for Capacity Planning.

    Hi PP Gurus,
    I want to know what setting we have to do for capacity planning.
    what I know is:
    1. W/C should be set for finite scheduling.
    2. In scheduling parameters for process order tick "Generate capacity Requirement".
    This both setting are made in my scenario, but it is'nt loading the work center fot that week.
    Any other setting nedded?
    Thanks, in advance.

    Dear ,
    You need to have following set up at basic level frist before you perfomr the capacity requirement planning  :
    1.In OPKP-Define Production Scheduling parameter -Availability check -Confirm Capacity and also Finite Scheduling chekc box ticked .
    2.In OPU3/OPU5-Define Scheduling Parametesr -you should mark the following
    1.Automatic Scheduling check box should be marked
    2.Scheduling Log check box should be marked -generate in case there is a scheduling error due to capacity over load .
    3.Scedulinga and Generate Capcity should be ticked .
    3.In OPJK Imaintain check capacity with SAPSFCG013 overall profile and set indicator -1 -Release Order -by user decision if capacity is insufficient
    4.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
    5.Routing - enter the values for the standard values. Use control key with scheduling and CRP activated .
    6. OPD0 and have the following set up  : Overall profile : SFAPSFC015 --Inside the over all profile I have the following set up
    1.Selection Profile -SAPSFCS013 SFC: Order view, standard overview
    2.Control Profile : SAP___C004 : Gen Capacity Availability Check for 1.5 months
    3.Time Profile : SAP___Z006 : Gen Capacity Availability Check for 1.5 months
    4.Evalution Profile : SAPSFCA013 : Gen Capacity Availability Chek =3.0D
    5.Strategy Profile : SAPSFCVER1-Gen Capacity availability Check
    6.Period Profile : SAP___P001 -Weekly period
    7.List Profile : SAPSFCI001-Production Planing
    Check all of them in place .Then you can go ahead with Capacity Req.Planning -Evalution and Leveling -CM21/CM22/CM05/CM07  etc.
    Refere the below theread for farther reference :
    Capacity problem in production order
    capacity planning
    Hope this will be useful .
    Regards
    JH

  • Re-order Point Planning -- PR

    Dear Team,
    I have created a Purchase Requisition manually. Same is not being considered for MRP run for re-order point planning.
    System is creating new Purchase Requisition when i run MRP.
    Where we have gone wrong?
    Thanks and Regards,
    RC

    Dear Chakrapani,
    MRP is considering Manually Created PR for one plant. And not considering for some other plant. If Manually created PR are not considered then you will end up in Procuring More material than required.
    RC

  • Problem in rough cut capacity planning

    Hi,
    I am facing following problem in rough cut capacity planning....
    When the capacity is overloaded in a particular month then capacity requirement is getting passed on to previous month as shown below....int the month of MAY 2014 capacity is getting overloaded then capacity requirement is transferred to Previous month APR 2014... I don't want this...what can be done to avoid this....I want to see overload in month wise....Plz help
    Thanks
    Kumar

    Hi Rupesh,
    Thanks for your help...finally issue is resolved...making the changes in OPU4 done the job...in OPU4 we need to remove the indicator of scheduling for rough cut capacity planning ........now getting the results as desired...

Maybe you are looking for

  • #*$!%! Can't figure out how REALLY to set the printing defaults so they STICK for everything

    PLEASE DON'T REPLY HERE.  PLEASE REPLY TO MY IDENTICAL POST AT  http://h30434.www3.hp.com/psg/board/message?board.id=Software&thread.id=5348 On our 6-month old HP OfficeJet Pro 8500 Wireless A909g, we can't seem to figure out how to set the DEFAULT p

  • 2 Reference monitors for Waveform/Vectorscope

    CS3 - Is there a way to add a second reference monitor? The first for waveform and the second for vectorscope? I don't care for the combined ones because they are too small. Also, is there a way to make it default to waveform every time PP starts ins

  • ChooseFile not working to open a directory ?

    Hi all, I am creating an installer for my scripts and need to get an istall directory from the customer. It seems that ChooseFile ( ) with the ChooseOpenDir parameter is exactly what I need. But this does not work: there is no dialog and the return v

  • Tree drag-drop function

    hello all, there is one single tree component in my application. XML is dataprovider of that tree. e.g <node name="Cars" id="1" isparent="true"> <node name="Audi" id="2" isparent="true"> <node name="A4" id="3" isparent="false"/> <node name="A6" id="4

  • EWA reports generating Twice

    Hi, In my solution manager EWA reporting generating twice for all systems ( 3 times for few systems) and also scheduled twice (3 times for few system ) for next week. Request you to help me on this issue. Thanks for you valuable help and support Than