Copy std wbs element in operative project & copy material components to SO

Dear Friend's
As i know following things not possible in std. sap ps. Still i would like to know is there any possibility to acheive same in std. sap ps.
1) I have created one std. project template, which is made for standardise Projects. Here we can copy same template for operative Projects. But my client having a requirement like they wanted to just copy a Single Std. WBS Element of any level from that std. project template to create operative project...can is it possible in std. sap ps.
2) Can is it possible in std. sap ps to copy the material component (like fert, halb, roh, hibe, hawa etc.) which we have planned in Project Builder to Sales Order.
3) In std. sap ps we can handle projects through multiple plants & multiple business area's. In my scenario cross plant & cross business area material's is supplied to any particular project. so same way can we create Sales Order for multiple plants & multiple busniess area's.
Thanks & Regards,
Sandeep

closed.

Similar Messages

  • Appropriation Request Plan Info Copy to WBS Element

    Hi,
    I understand that the Plan information specified in Appropriation Request will be copied into WBS elements specified in Measures/Assets section.
    I would like to confirm if this happens for both cases below:
    - If I put exisitng WBS element under Measures/Assets section (will this overwrite my original plan for WBS element?)
    - if I create a new project via Appropriation request, will the plan of the AR be copied to my WBS element (which means I will see updated plan if I check CJ40)?
    Thanks!
    Regards,
    Vivian

    Please check the below specified link, which is very much similar to u r requirement
    http://help.sap.com/saphelp_46C/helpdata/EN/fd/45add69d6411d189b60000e829fbbd/frameset.htm
    Regards
    Suresh

  • How to do budgeting at activity level and WBS element level in project syst

    Dear GURU's,
    Can any one please suggest me how to do budgeting at activity level and WBS element level in project systems, friends please I required set by step process.
    I need how to do this configuration to map this scenario.
    Regards,
    Bhanu

    Hi Bhanu,
    Use this link :
    http://help.sap.com/saphelp_45b/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm
    after page opens , click on BUDGET MANAGEMENT , There you will find each and every step you want .
    Thanks ,
    Dhruv Kumar Malhotra

  • 1 project definition with several wbs elements or several project definitin

    Hello
    I need projects as account assignment elements in CO (when entering vendor invoices for costs). Should I have 1 project definition with all projects /wbs elements underneath, or should I have 1 project definition uniquely defined for each project/wbs element? Some projects are not settled to assets und construction, some projects are settled to assets und construction.
    kind regards
    Arjan

    Arjan
    I don't think you can have Projects as account assignment objects. You can have WBS element as account assignment object.
    One alternative I can suggest, if you want to see project costs at higher level instead of breaking down the project into many WBS elements. Create a project with one WBS element only and use that WBS element as account assignment object.
    It is only possible to have a project with one or more WBS elements. I don't think you can define projects within projects.
    letus put it this way assume WBS elements are projects within a project. But make sure all the WBS elements are related to one project
    Hope you are clear now.
    Thanks
    Prasad

  • Report to get WBS elements based on Project Type

    Dear Experts,
    Is there any report exists in Project Systems to get WBS elements based on Project Types.
    This we can check in the table PRPS-PRART.
    But i need to know the availability of T Code.
    Thanks in advance.
    Regards,
    Srinivasareddy Y

    Hi,
    If its a one time requirement using CN43N might help in meeting the requirement. However, first it has to be executed for a certain range of projects and then the layout will have to be changed accordingly. Instead of doing this if a custom report is developed with the input parameter as "Project Type" it would make it much more easier. You can even have the F4 search option for the input parameter. Doing this will help if the report is going to be used frequently in the future.
    Take your call and proceed accordingly.
    Regards,
    Gokul

  • How to Find PS GUID with WBS Element (POSID) or Project Definition (PSPID)?

    Hi all,
        I am creating the custom Extractor similar to 0CO_OM_WBS_1 (WBS elements: Costs) to load into 0PS_C041 (Project System - Controlling (New)). I have the WBS Element (POSID) & Project Definition (PSPID) and I how can I find the GUID (UUID in X form Binary) so that I could map it into 0PSGUID InfoObject in the Transformation. We have WBS Element & Project Definition (PSPID) as Navigation Attributes of 0PSGUID instead of under some Dimension in 0PS_C041 Cube and that's why I am trying to find the GUID with WBS Element (POSID) or Project Definition (PSPID), PLEASE.
    Thanks,
    Venkat.

    Hi Bala
    Yes, you have put it rather correctly.
    We use WBS elements for booking and posting time (client requirement). So what I am looking for is WBS Elements with the system status TERL (Time and Expense Released).
    I talked of the deletion flag also, because a WBS element flagged for deletion can't be used. It's one of the criteria to screen the WBS elements.
    I hope it's clearer now.
    Vinitha.

  • Standard WBS Elements v Operative WBS elements as templates

    Hi
    I am considering the use of Standard WBS elements however one of the limitations that I have identified is that it is not possible to enter the any default settlement parameters into the WBS elements.
    As our Work Breakdown structures are a combination of both operative as well as capital WBS elements (for accounting purposes) it is not possible to enter the default Settlement Profile in the project profile.  ie: Mulitple settlement profiles are used across the WBS elements for a single project profile, depending on the required accounting treatment.
    Ensuring that users enter the correct settlement paramters for each WBS element cannot be gaurenteed and it does not appear possible to use sustitutions to populate these parameters.  Month end settlement is often problematic and the correct accounting treatment is essential so I am looking for alternatives.
    One alternative that comes to mind is to set aside a range of operative WBS elements for use as templates.  This would then ensure that all required fields in the operative structures are pre - populated including the settlement parameters.
    Has anyone used operative structures in this way and if so are there any potential issues?
    Thanks in advance.
    Ian

    Hi Hermant,
    Thanks for your ongoing input.  I am still not sure my original message was clear.
    The key point is that I am talking about using a range of operative structures as templates.  "lets just say the first 200 operative structures will be designated as templates."  These operative structures to be used as templates, contain different settlement parameters for each WBS element.
    In your first post you mentioned.
    "2. But this will not solve your purpose as copied projects will not have the settlement profile "as it is" in the std. operative WBS elements. Settlement profile gets defaulted from project profile... hence you will have to mainatin it manually again in the copied projects."
    and in your second post.
    "That is what I mentioned in my earlier post... although you maintain different settlement parametes in project which is to be copied.. it won't be inherited in new project. You will have to maintain it manually..."
    This is not the case, you actually do not need to maintain these settlement parameters manually when you copy an operative structure. (used as a template)  This is exactly why I am considering using operative structures and NOT standard structures as templates.  I agree, when using standard structures no settlement paramaters are inherited.
    As I mentioned in my first post the Project Profile will not contain a settlement profile.  Hence when the operative structure with pre populated settlement parameters is used as a "template" and copied to create a new operative structure all settlement parameters are copied / inherited to the new operative structure.  This is the result based on my prototype.  Try this, copy an operative structure that has pre populated settlement parameters and you will see that all these settlement parameters are copied.....at least in my system that is the way it works.
    I hope this helps clear up any misunderstanding.
    Regards
    Ian

  • Automatically PO creation from WBS element in a project

    Hi,
    Is it possible to create Purchase Order automatically from the project that has only WBS element (no network)?
    My project has only WBS element and my client want to trigger PO creation automatically for prorements to projects.
    I appreciate your replies.
    Regards,
    Ja

    Hi Ja,
    Sorry, but you cannot create a PO automatically for a project that has only WBS elements and no network or acitivites. Since materials can only be attached to activities in a project it is mandatory to have an activity to trigger a PO automatically from the project.
    You may have to create a PO manually and then assign the WBS as account assignment.
    Regards,
    Gokul

  • WBS elements related to project definition

    Hi all,
    I need to extract all the WBS elements (PSPNR) from PRPS related to the project definition (PSPID) in PROJ. Please help me with the query.
    For Example:
    For project definition: 6HU-000000120
    There are 2 WBS elements: 6HU-000000120(top level) and 6HU-000000120-1(second level)
    Thanks,
    Netrey.

    Hi
    Join the tables PROJ and PRPS using the field
    <b>PROJ-PSPNR = PRPS-PSPHI.</b>
    select af1 af2
             bf1 bf2
         into table itab
    from proj as a join prps as b
    <b>on apspnr = bpsphi</b>
    where a~pspid in s_pspid.
    Reward points if useful
    Regards
    Anji

  • WBS element deletion after project release

    Hi,
    getiing an error ,scenario is after deletion of WBS element  if i try to add same wbs..throwing an error that WBS element XYZ version RELEASED already exists.
    thanks

    Hi,
    You can refer this thread for more details;
    Re: Restoration of original WBS code
    Regards,
    Kabir

  • CJ9B - error message when copy locked project or wbs element

    Dear Expert,
    Tcode CJ9B is for copy planning wbs element/project and every month i need to unblocked all the project or wbs that not use (locked) one by one to make CJ9B able to run without any error.
    Is there any way to do mass change on wbs element or project as i unblock one by one in tcode CJ02?
    Please advice what is different between CJ9B and CJ9F? Is it same doing copy planning wbs or project?
    regards,
    ng chong chuan

    For the locking and unlocking you can use CJ20n  -->WBS element overview instead of the CJ02 so, you can make mass locking and unlocking of WBS  all the WBS elements of project atleast.
    CNMASS tcode is for the mass changes in PS but same will not work for hte system status change.
    One workaround is that you write BDC via SHDB txn and user that BDC to change the status of all the WBS for which you wanted to  lock/ unlock .
    You can also use LSMW also.
    Regards
    Nitin

  • Exit for replacing WBS element characters while copying from Project

    Hi All,
    While copying a Project from other Project/template in CJ01, we are getting only first 10 letters of a WBS element are getting replaced.
    The requirement is to have replacement of letters even after 10th character in WBS element.
    The SAP Note 502322 suggests to have user specific (custom) replacement logic in the user exit CNEX0033.
    Anyone has worked around such requirements?? If so can you share it,,,?????
    Regards
    Pavan

    Hi,
    While creating a Project in CJ01 by giving a template, the new Project will get created with all WBS elements from the template Project.
    In standard system, the WBS Element which has more than 10 characters will get copied till 10th character only.
    Now we need to work on user exit CNEX0033, so that entire WBS element name should get copied in the new Project.
    Anyone has worked on such requirement???
    When i create new Project in CJ01, the exit CNEXX0033 will trigger..
    If so can you suggest me how to move further??
    Regards
    Pavan

  • CADO Report - Missing Project Definition and WBS elements

    While running CADO (time sheet data) report for employee, data is not being pulled up for the WBS Element and Project Definition. What could be the reason? Here time is entered against a network activity but for some entries WBS element and project definition is dispalyed and for remaining it is not.

    Yes....these activities are assigned to the WBS element in the project. As I mentioned earlier for the same activity in some cases WBS element is populated.

  • Creating projects and wbs elements

    I am running a conversion and for the upload portion I need to create projects and the relevant wbs elements in the system.  I have been looking over the forums etc and have seen many notes regarding BAPI_BUS2001_SET_STATUS, BAPI_PROJECTDEF_CREATE, and BAPI_PROJECT_MAINTAIN.
    My problem is this.
    I need to update the APPR and PREP system statuses of the projects I create and I can find no way to do this with a BAPI.  I also need to update the location of the project (stort) and the only BAPI I can find that will allow me to do this is BAPI_PROJECT_SAVEREPLICA which seems incorrect to use in this manner.
    in short:
    How do I update project system status of PREP and APPR?
    How do I update project location (stort)?
    Having no luck finding solutions so any help is appreciated.

    Hi,
    I've used these BAPIs but not for your fields. But maybe I can help you. There is no field LOCATION in the project definition but there is field LOCATION on WBS level. So have you tried to change this field on all WBS elements for your project?
    Unfortunately your system statuses are not supported by this BAPI. All supported statuses are mentioned in BAPI documentation. There is a FM STATUS_UPDATE_PROJECT which might help you but you need to be careful what you do. There are some additional FM STATUS_* for generic object status modification but again, you have to be sure that you can set up that system status without any additional checks.
    Good luck

  • Standard network assigning various WBS Elements

    Hi,
    I am using Standard network and Stand WBS Element for creating actual project.
    There are Std WBS Elements, using the same Standard network. As i know, we can assign Std WBS Element in Std network. How can i make it using same std network for various Std wbs element to create actual project as Std network is same for most of the WBS Elements.
    I donot want to copy Std network for actual project once we create copying Std Project in CJ20N.
    Regards
    N.Raju

    create more standard wbs - there is no other way