Cost Estimate Run

Hi Gurus,
Please tell me why we run cost estimate and what is the use of it.
What are impacts of running cost estimate?
Please revert asap.
Thank You

Hi,
Cost Estimate is runned to calculate the Cost of Goods Manufactured or Cost of Goods Sold for your Materials and Update the prices in Material Master.
You have different ways of Calculating your COGS and COGM in SAP.
The Important methods are
Cost Estimate With Qunatity Structure and Without Quantity Structure.
In Cost Estimate With Qunatity Structure  you will not have the option of entering the lot size for your Cost Estimation. It will be automatically determined from your BOM and Routing.
Whereas In Cost Estimate  Without Quantity Structure you need to manually enter the Quantity at the time Cost Estimation.
With Regard to Impact of Cost Estimates.
While Running the Costing Run you have to Mark or Release your Cost Estimation results inorder to Update the prices in Material Master record.
Hope I have briefly given an idea baout Cost Estimates and its impact.

Similar Messages

  • Cost estimate run in case of PP-PS scenario

    We are having PP-PS scenario at one of our location , BOM is maintained in CS01and activity rate is maintained in KP26, project WBS is created in PS for project monitoring , the project time is normally 6-9 months, It is Make to Order business.
    I want to know whether we have to run CK11n and CK24 for mark and release for standard cost estimate or it will get automatically get calculated on the basis of planned cost after confirmation of production in production order.
    I checked  qbew table valuation was on the basis of planned cost where as in material master MM03 material value was different.

    Hi
    1. You need std cost from CK11N only if you can manufacture independent of the project any time. Else it is not reqd
    2. I dont know abt your 2nd question.. So unable to answer
    3. For each project and production order that you create, system would calculate planned cost and that should cover changes in BOM. However, you can also use MR21 to update the price in QBEW any time...
    In this scenario, you can do a testing as follows
    1. Create a Project and Production Order and to the GR. Check @ what value GR takes place
    2. Change the BOM and create a project and production order so that a diff planned cost is calculated.... DO the GR and check at what value GR takes place
    Regards
    Ajay M

  • Incorrect overhead % , released to material, re-run cost estimate ?

    Hi guys,
    Our costing team found that they are missing to maintain overhead % in Costing Sheet.
    They already did CK40N, Mark and release to material master for April 2011. They want to change
    the Cost Sheet and then re-run Cost estimate, mark and release.
    Can we do CKR1 (we have over 1000 active SKU), and then release and mark again to April 2011.
    If they do not re-calulate the plan cost, it will create a large production variance this month.
    Thanks a lot !

    Hi
    Technically - You can process 1000 materials in one single cost estimate run in Ck40N...
    however, for the sake of easy, create 2 Costing runs with 500 mats each.... it would enable you to handle the exercise easily
    br, Ajay M

  • Valuation using material cost estimate

    Ciao a tutti,
    We have create a material cost
    estimate without standard structure(unit costing) not FOR ALL MATERIALS, but only for ONE
    VARIANT of generic material (retail solution) (because the other variant have the same price, and because we have to reproduced 5000 BOM in unit cost for just
    one variant with transaction KKPA LSMW)
    So, now we have to valuated the material cost estimate when the customer create the billing document and put the split of the cost estimate in co-pa
    Our prolem is : we have calculate standard cost estimate for 5000
    variant not for all variant (because our customer crete the BOM in unit
    costing with transaction KKPA and LSMW, and they refuced the idea to
    calculate 30000 cost estimate with lsmw) so when we crete a billing
    document with a variant that haven't cost estimate created the system doesn't
    valuated the cost estimate (the system works well), but how I can change the variant in the valuation and put the variant that have the cost
    estimate calculate?
    Wiht the transaction "Assign Costing Keys to Any Characteristics" I think
    is not possible.
    I must to use enhance COPA0002?
    Thank you very much
    Paolo Artini
    tel: +393299223804

    Hi All,
    I am also facing the problem for Sales Order Cost Estimate. and the Costing Status is VO(Marked without errors).
    I have done the following
    created the Costing Key (sales order cost estimate)
    assigned costing key to the material type.
    assigned to the respective value fields
    sales order cost estimate,
    Run the RA
    Settlement done.
    But in COPA, cost estimates are not being split up based on the cost component (like Material, Labour and Over head) and it is getting posted to COGS only.
    Do we need to change the costing status to FR, if yes, but how to do ?
    Regards
    Ramesh KR
    +91 9884020411

  • Material Cost Estimate with different lot size.

    What happens if the material cost estimate is run twice using different lot sizes each time  (all other parameters unchanged) for the same period?
    Will the cost estimate run later overwrites the results from cost estimate run earlier (though the lot size is different)? What is the role of lot size in a material cost estimate?

    The costing lot size impacts your cost estimate if you have lot size independent costs (i.e. setup cost).  Those fixed costs are spread over the costing lot sizee to give you a cost per unit..  Larger costing lot sizes can also help you minimize rounding issues.
    You can only have one marked cost estimate in a given period.  However, you can create and save a cost estimate as many times as you want as long as you have not marked it for release.  When you save the estimate it will overwrite an existing estimate.  You also have the option of creating multiple estimates under different versions or with different costing variants.

  • Error during Material Cost Estimate (CK11N)

    hi friends,
    I am getting am error during the material cost estimate run.(ck11n)
    "No control record for the activity type"
    please let me know what is the problem.
    regards
    Ramesh

    Ramesh,
    System is not able to determine activity type price.
    You need to input activity price in transaction KP26 for Version 0/Period/Cost Center/Activity Type combination.
    Regards,
    Prasobh

  • Selection of BOM and Routing in Cost estimate

    Hi
    I have an issue with the cost estimate run. We are using CK40n for cost estimate.
    The selection method in MRP 4 is defined as 3 (only by prod version) and the version indicator is maintained in the costing views also.
    When we run the cost estimate the system is chosing a different BOM and routing other than the ones defined in the prod version.
    Following are the details of the prod version defined.
    0010 Prod version
    Lot 0 to 99999
    BOM Alt 1 usage 1
    Routing Grp 1234 counter 1
    0020 Prod version has
    Lot 0 to 99999
    BOM Alt 2 usage 1
    Routing Grp 1234 counter 2
    0030 Prod version has
    Lot 0 to 99999
    BOM Alt 3 usage 1
    Routing Grp 1234 counter 3
    Ideally system should choose the first prod version.(alt 1 and usage 1 and Routing 1234 grp coutner1). This is not happening.
    System for some reason is choosing the BOM with Alt 1 and usage 1 defined in 0010 prod version but the routing from a different prod version 0020 grp 1234 counter 2.
    I have checked with all the relevant settings but i am not able to understand why this is happening.
    This is not the same when i create a prod order. System chooses the first prod version when i create the order.
    I have checked the priorities defined in the customising, and also the details in the costing varaint using CKC1.
    What settings do i need to check to ensure that it works fine? Can you please let me know.

    Vithal,
    While doing the costing run, SAP checks if you have maintained the "Production version to be costed" [MARC-FVIDK] field in Costing View. It will use this Prodn Version for cost estimate.
    If you have not maintained the prodn version field, then it will use the values maintained in the "Quantity structure data" section on costing view. i.e. it will use the BOM alternative..and recipe information from here.
    If you have not maintained above values then system picks up the first BOM alternative (MAST table) and first recipe information (MAPL table) it finds for the material-plant combination.
    Might be this is what is causing the problem for you. Also according to my knowledge SAP cannot decide the Lot Size for Prodn Version while doing the costing run. You need to tell the system what data to be used for costing.
    Try and revert back.
    Swapnil

  • Cost Estimates taking raw material in CK40N

    Dear Experts,
                 We are running Costing run using CK40n by selecting site & article
    type:ZMTG. (Only Finished Product)
    But Standard cost is displaying for ROH/VERP in CK13n/MM43.
    We only want to carry out std cost run for only ZMTG article.
    In Costing varinat Priority is set for "Valuation Price according to price control" so the value give is correct. But the standard price field is getting updated in material master for Raw Material.
    I want to know usually whether it used to take like this, if not where i need to make changes so that it should not take while costing the finished product.
    Please reply asap.

    Dear Abhisek,
    It does not matter if the standard field updates with cost estimate, coz it does not effect financial results at all, reason behind the price control which is moving average  for RAW materials.
    Secodndly, it is helpful for you to find out the price of material when cost estimate was exucuted, coz it will not change until your further cost estimate run.
    Raw Materials are part of BOM, so system always calculate their prices to reach at price of finish product, but system does not post any price change document for raw materials.
    Further u can confirm using tcode CKMPCD
    Regards,
    M. Tayyab Aslam

  • CK11N - How to exclude assembly scrap factor from Cost estimate

    Dear Experts,
    We have assembly scrap maintained in the material master. We also have operation scrap in the routings.
    During the Cost estimate runs, we just want the system to consider the Routing operation scrap. I know one solution is just to remove the assembly scrap from the material master. However, we can't do this since it can adversely impact our MRP runs.
    Does anyone has any idea on this?
    Thanks and regards,
    Vishal Thakur

    hi vishal,
    if you want to exclud the material fromt the cost estimate here is the short cut .
    go to the material master of the material which you dont want to be costed
    go to the costing views and flag the dont cost check box in that views
    Best Regards

  • CK666 error in cross company code  cost estimate

    Dear All,
    We have activated multiple valuations/transfer prices : legal, group and profit center valuations.
    We perform cost estimate run in ck40n for profit center valuation and get error
    Material 20000035/plant FZ03: Transfer price could not be found.
    Message no. CK666
    Diagnosis
    When switching profit center A ->B (from the material component to the costing object), a transfer price could not be determined for transfer price variant 0 in respect of material 20000035 in plant 1.
    System Response
    If you carry out costing for a profit center valuation, material 20000035 goes into the cost estimate without a value.
    If you create a cost estimate for group valuation, profit from material 20000035 is not transferred into the cost component split.
    Procedure
    Check the settings for transfer price variant 0.
    We have checked this material. Manufacturing plant belongs to  company code A.
    To get cost estimate for plant 2 which belongs to company code B we use procurement types in material master.
    It requires now transfer price variant. But we do not want to use this functionality.
    How can we solve this issue?
    With best regards,
    Kamila.

    HI Kamila.
    There is a difference in the way PCA handles determining costs:
    If transfer prices are activated it's necessary to determine either a transfer price via pricing or to exclude the relevant material
    from the transfer prices scenario via user-exit 'EXIT_SAPLPCRW_003'.
    Please note that the determination of a transfer price and the creation of additional PCA lines are independent of each other. You cannot control the determination of a transfer price by means of your 0KEK settings. So if you want that no transfer price is used for a material please use exit 'EXIT_SAPLPCRW_003' here. Pricing will then not be called and the system automatically uses the current
    material price from the profitcenter view.
    Please have a look at the note [458543 |https://css.wdf.sap.corp/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=0000458543]which provides further information regarding this exit.
    Regards,Declan

  • Order settelement without standard cost estimate

    Hello,
    My Scenario MTS,
    Client doest not want to take Cost roll up (Standard cost estimate run) the price control code 'S' for all the Finish goods, Semifinish
    and raw materials.
    In this how to handle order settelment , variance calculation without standard cost estimate.
    Please provide configuration steps also.

    Hi,
    Can you let us know why your client does not want to update the std. cost price for a material?
    One of the key reasons for implementing SAP or any ERP system is to monitor the cost & value flows within the organization. Unless there is some compelling business need for it, you should strongly advise your client to go for costing of parts / assemblies.
    However if no costing is done & the std. price is '0' then if the activities have prices maintained, then when a confirmation is posted only the activity cost will be posted on the order. The variance calculated will then show only the difference if any b/n plan / target / actual activity costs, while part cost will remain zero.
    Regards,
    Vivek

  • Cost estimate/costing run

    Hi
    What is the difference between cost estimate and costing run?
    Thanks,
    Nivi

    Hello Ram,
    There are 3 steps in Costing Procedure. They are
    1. Creation of cost estimate
    2. Marking of cost estimate
    3. Release  of cost estimate
    Once you release cost estimate, then only system will update the required fields in the database and can be used for transactions.
    Hence, cost estimate means, it is just estimated total cost of the product and Costing Run means which inclusive of all the above three steps to complete the total process.
    Please let me know if you require any further clarifications.
    Thank you,
    Regards,
    Santosh
    Reward points if helpful.

  • In running standard Cost Estimate, System is selecting wrong selection ID

    We have two Process in Production . one we use Process flow(PI), in other we use Production flow(PP).
    Now, while running standard cost estimate for Process industry(PI) as  it uses recipe instead of Routing...But system is searching/selecting for routing than recipe.
    Our issue is that when i run Cost run for Process orders , it should select Recipe not routing. And  when i do cost run for Production order...it should select Routing!!!
    Kindly help...
    Shivraja

    Verify the Routing determination sequence in costing varinat - Quantity Structure determination configuration.
    Change the Priority for the selection of task lists as below
    ID                  SP               Task           Plan Usage        Description  Status             Description of Status.
    01     1     R     1     Production     4     Released (general)
    01     2     R     1     Production     2     Released for order
    01     3     N     1     Production     4     Released (general)
    01     4     N     1     Production     2     Released for order
    01     5     2     1     Production     4     Released (general)
    01     6     2     1     Production     2     Released for order
    This should work as expected.

  • How to Run a Cost Estimate with Budgeted Values parallel to the Std Cost Estiamte

    Hi Experts,
    My client want to run a parallel cost estimate with Budgeted values for each type of cost in a similar process like standard cost estimate(currently only Std business run only the std. cost estimate). Below will be provided to run the said cost estimate.
         1. Budgeted Cost for cost elements against each cost center
         2. Re-posting/distribution will be required run to allocate and apportion the cost from service cost centers to Production cost centers
         3. All Planned(future) Material Cost will be provided. (note that the valuation strategy of costing variant of standard cost estimate has below sequence
         4. Budgeted activity quantities will be provided. (Cost and activity qty for Kp06 and Kp26)
    Based on the above data business need to run a cost estimate with budgeted values parallel to the standard cost estimate(based on planned values), which will be compared with actual then Budget at each months.
    Simply an alternative cost estimate with budgeted values for a given period for all materials.
    Kindly advice the possibility of such a cost estimate in the system and if possible pls. mentioned the Process in order and configuration steps for the same.
    Thanks in advance.
    Aziz

    Hi..
    You can define costing variants which have valuation variant for budgeted values parallel to the standard cost estimate  in Customizing for Product Cost Controlling.
    You can define target cost versions using above costing variants under the customizing transaction OKV6 as below picture.
    When you calculate variances, you can check “all target cost version” flag to calculate variances  for all target cost versions in the controlling area as below picture.
    You can analysis the difference between actual cost and several budget cost using target cost version as below picture.

  • New costing run within same period for relased cost estimate

    Hi All
    Once we have run the costing run. The price is marked and released. Then If we have to again runthe costing run, system says price for the priod has been released and doesnt allow to proceed.
    How to overcome this? Cant we run costing run as and when required and multiple times release it in the same period?
    Please help me
    Regards
    Rakesh

    Hi Rakesh,
    I would like to know what is your requirement of running the Standard Cost Estimate for second or third time in the same period...?
    If you feel that, Standard Cost which was marked and released needs to be updated as per the changes in BOM, Routing etc, you can still do it...
    First, go to transaction code CKR1 (Re-organization of Cost Estimates), select the parameters like company code, plant, material (for which you want to reverse the Cost Estimate), select the radio button for "Current Standard Cost Estimate" and execute.
    Then, Current Standard Cost Estimate will get reversed. You check for confirmation in the respective material master -- Costing 2 View whether the Current Planned Price has become blank or not.
    Then you do CK11N and CK24 again for marking and releasing....
    Try this and pls revert back for further explanation...
    Srikanth Munnaluri