Costing affect with MRP at planned order level and after production order

Dear all,
How the costing affect with MRP at planned order level and after production order completion?
Edited by: Maulik on Jun 24, 2009 1:59 PM

Dear Maulik,
check Mr. Vinod's inputs abt costing
1. Maintain following master data:
MM01 Material Master with Costing and accounting view. Make sure all the cost Std, Moving avg etc is maintained along with valuation class in Accounting view 1. In costing tab pls make sure "with qty structure" and "Material Origin" are ticked.
CS01 BOM with components marked with costing relevance in Status/Long Text Tab. Also check all the qty are correct.
CR01 Work Center in Basic data tab maintain standard value key sau SAP1 and in costing tab maintain the workcenter, activity type and formulas (Usually standard formulas like for Machine Hours SAP006, Labour SAP007, Setup Activity SAP005 is used).
KL01 Cretae activity types, in basic data tab maintain ATyp Category AS "1" and cost element (as provided by your FI Guy).
KP26 Activity pricing, here with the combination of Activity type and the cost center you assign price to the activity.
2. SPRO Activity
Maintain Costing sheet IMGControllingProd cost controllingProd Cost PlanningBasic settingoverheadsdefine costing sheet.
OKKN Define costing variant, you define costing type (In the costing type, you define the purpose of a material cost estimate by specifying, for example, which field in the material master record the costing results can be transferred to like std price, moving avg etc), Valuation Variant (defines how the prices are prioratized), date control and transfer structure.
3. Costing Process Flow:
1. CK11N CREATE COSTING RUN
2. CK24 CREATE PRICE UPDATE (You Mark and release the prce to be updated)
4. COSTING VARIANT WRT PP
1. OPL1 DEFINE COSTING VARIANT WRT PP
2. OKK4 or OPN2 DEFINE VALUATION VARIANT
3. OKK1 or OPM1 DEFINE COSTING TYPE
4. OPL8 ORDERTYPE DEPENDENT PARAMETER (assign the above creted costing type for both planned and actual)
Hope this will throw some light on product costing.
Regards
kumar

Similar Messages

  • Controlling Level At The Production Order Level

    Hi,
    I want to set the ML controlling level to the production order level because I want to see the actual BOM used for each production order at the production order level. Since a different BOM may have been used for each production order (although the FG is the same) i must be able to see the actual BOM for each production order at the CKM3N screen.
    However in the controlling level setting there is no way to set the controlling level up to the production order level. May i know why?

    hi
    check this link
    http://help.sap.com/saphelp_470/helpdata/en/b2/6d118acb0a11d28a150000e83234f3/content.htm
    check whether production order level is possible. i dont thinks so.but it highly affects your system performance.
    krishna

  • After production order settlement, where does the cost go?

    Dear Experts,
    I understand after we did the "order settlement" for production order, the cost will be settled to material manufactured from the said production order.  Say, the total cost is $10,000 to produce 1000 units of finished goods (FG), then the cost settled to each individual FG at $10 each, am I right?  Where can I see the settled cost in the material master?..
    I checked in the cost center report, S_ALR_87013611, I can see the cost Credited from "production" cost center with a breakdown in settlement cost element such as machine hour, setup and personnel hour.  I understand the other side of Debit was to the production order, and only after order settlement, I'm not sure which cost center will be Debited.
    That would be the CO side, how about the FI, would there be any cost posted to the GL side after production order settlement to the material?
    Please advise..
    regards,
    Abraham

    Hi Abraham,
    It's not the button i mentioned. I was just trying to take u to the accounting document from the settlement screen. well just drill down the settlement screen and u'll get it. No big deal.
    But more important is the concept. I'll share my understanding here. (cost by production order)
    Any value that flow into controlling module should have a cost object. Here production order is the cost object.
    First u create a production order (cost object) for say 1 unit of X with a std price of Rs. 10
    Std price comes frm material master as a result of std cost estimate
    U start production - Raw materials are consumed - 2 qty x Rs.3.
    Entry RM Consumption Dr Rs. 6    Inventory Cr Rs.6 (Prod order is debited with Rs.6)
    Activity (Let's say machine hours - 3 Hrs x Rs.2) According to the routing it was  2 hrs but actual production took 3 hrs.
    Entry - None - But production order is debited with Rs. 6.
    When production is complete for 1 qty of X, entry flows
    Finished Goods Dr Rs.10    Change in Stock  Cr. Rs.10  (Production order is credited with Rs.100
    Abraham, now visualise both sides of the production order. It will have debit of Rs.12 and credit of Rs.10.
    Now accountant sees the production order and confirms the values are ok and puts the status of TECO to the order. which means the order is technically complete.
    Now when u run the order settlement, this production order is picked up by the system (due to it's status). System sees difference between debit and credit of Rs 2.
    So it cedits the production order with Rs. 2. Now both debit and credit of production order is equal (Rs.12)
    Entry Price diff A/c Rs,2     Change is stock A/c Rs.2
    Now this rs. 2 is settled to COPA. It does not flow to material.
    Reason:  in a std costing system materials are valued at standard cost and
    Hope this helps. Do revert in case of doubts.
    Best Regards
    Vimal

  • Route not determing automatically at sales order level for some sales order

    Dear All ,
    Route not determing automatically at sales order level  for some sales orders.We are using automatic route determination without wt group,eventhough we have configured the required settings
    I have checked all the forums but didn't find any solution for the same.
    Looking for your inputs .
    Thanks inadvance
    Regards
    Venkat

    Hi
    1. Copare the Routes which are Automatically determined and which are not automatically determined
    2. Have you mainted this route to be RELEVANT FOR TRANSPORTATION without this check route will not get picked up.
    SPRO > Logistic General > Shipping > Basic Shipping Function > Routes > Define Routes > Define Routes and stages > Select the Route and check for it's settings > CHECK MARK Relevant for Transport. Without this check the route will not get picked up as of my understanding.
    Thanks
    RB

  • In the iMovie 11 event library, how can I get the iPhoto video clips to combine with my camcorder pics listed below and in chronological order?

    In the iMovie 11 event library, how can I get the iPhoto video clips to combine with my camcorder pics listed below and in chronological order?

    Try forcing iPhoto to load the Library on the External Hard drive by launching it while holding down the Option key. Choose the Library on the External HD, and quit iPhoto, see if iMovie can see the Library with the iPhoto Videos contained inside.

  • Is it possible to have different pricing procedure at sales order level and

    Hi SD Gurus,
    Is it possible to have different pricing procedure at sales order level and invoice level?
    if is it possible to have different pricing procedures at sales order level and invoice level could you please tell me the steps how i have to do?
    Thanks & Regards,
    Nivas

    Hi,
    Yes you can able to map two different pricing procedure for order and invoice level
    You can achieve it through by document pricing procedure and assign it in document type
    In VOV8  assign document pricing procedure A for order type
    in VOFA assign document pricing procedure B for billing type
    Keep customer pricing procedure common
    Then in OVKK assign pricing procdures
    Kapil

  • Bapi or FM or tabel or any standard transaction code for Production order linking to get child production orders based on parent production order

    Dear Guru's,
    we have a requirement i.e. user can convert planned orders in to production orders (CO41) based on those production orders we can get Route card( Z Smart form)  presently we are using manual input for that Route card. recently we got requirement for this i.e. make to automatic generation of route card for this requirement we need to get the list of child's production orders based on parent production order
    so as per my requirement i need to get all child part numbers production orders based on parent production order number and quantity i tried in MD4C and CO46 but those transactions codes are picking multiple lines also so for this requirement please give your valuable suggestions
    Regards,
    Venkat 

    Dear Friends,
    Thanks for your reply,
    My business process is MTS purely strategy 10, for route card all components with production orders we can give input as like bellow these production orders are converted from planned orders,between few components are don't have production orders those are F-30 materials,because of this reason i need link for production order to child components orders
    01
    IND1
    IND1
    A1CE2003520103-005
    55685815
    02
    IND1
    IND1
    A1CE2003520103-010
    55685814
    03
    IND1
    IND1
    A1CE2003520103-015
    55685813
    04
    IND1
    IND1
    A1CE2003520103-020
    55685812
    05
    IND1
    IND1
    A1CE2003520103-025
    55685811
    06
    IND1
    IND1
    A1CE2003520103-030
    07
    IND1
    IND1
    A1CE2003520103-035
    55685810

  • Difference between Configurable and varinant production order

    Hi All,
    1) What is difference between configurable material production order and variant  production order?
    2) What is difference between configurable material and variant material?

    Hi All,
    1) What is difference between configurable material production order and variant production order?
    Ans:
    the only difference i can see is the Account assighnment - the configurable material needs to have a sales order order or Customer independent requirment since the stock when gets produced has to be placed inanyone of the account assignment.Which in simple terms is a make to order producton order
    the Variant material production order can be a make to stock scenario also
    2) What is difference between configurable material and variant material?
    a.Configurable material - Inthis the characteristics can get any or specified values based on the requirement
    Ex: car - is configurable material
        colour is a charctertisc - red,white are the values
    b. Variant material - It will have ONLY one config material attached with it and the charatterstics would ahve the vallues prefixed
    ex: CAR_RED as a material - which means the colur of thecar is red -it is fixed
    does it clears your doubt are still require any more information..
    sap s very intresting part  is VC

  • How to identify difference between Configure To Order (CTO) and Engineer To Order (ETO) items

    Hi All,
    We are working on Oracle Database 10g
    We have to develop a code which involves Configure To Order (CTO) and Engineer To Order (ETO) items.
    Can anyone advise is there any table and the corresponding column in the database which will help identify if an item is a CTO or ETO.
    Regards,
    Shruti

    Shruti,
    Have you checked eTRM website? -- http://etrm.oracle.com
    Please also see (How To Find the VIEW or TABLE That Populates a Form So That a 'Custom Report' Can Be Created Using Same VIEW or TABLE (Doc ID 604772.1)).
    Thanks,
    Hussein

  • Is possible to create a TO automatically after production order confirmation?

    Hi all
    I have just a question in order to know if we can configurate a procedure to a Production Order, so my question
    is possible to create a TO automatically after production order confirmation in a standard enviroment?
    Thanks in advance for all your comments

    Hi Gurus,
    Thank you for your help in this case.
    Process:
    The customer create a production order in CO01 and then they confirm the order in CO15, after confirmation TR is created ( we can see this in LB10 ) and negative stock is created (  we can see this in LS24 ).
    Requirement:
    They are asking to create the TO automatically after the production order confirmation. Negative stock is afecting the process.
    Workaround:
    They are creating the TO in background in LB10. ( negative is fixed )
    Question:
    Can we create the TO automatically after confirmation in standard configuration?
    if no ,  how can we confirm this TO .using a JOB option?
    TR created after confirmation
        TR header
    LS24 negative units.
    Regards!!
    Ronald

  • I would like to cancel my order, order no: AD001440537EU. Products ordered: Adobe Export PDF, Annual.

    I would like to cancel my order, order no: AD00144537EU. Products ordered: Adobe Export PDF, Annual. What do I have to do?
    Regards,
    Lányi Péter Pálné (Mrs)

    You are at the wrong forum; this is the Reader one. In any case, this may be helpful: Cancel your membership or subscription | Acrobat.com online services

  • How to get the ammendment sales order number and original sales order no?

    Hello sir's,
    Please tell me the table for ammendment(revised) sales order number and original sales order no.
    Thanks in advance,
    vikram

    Solved

  • I was wondering what student plan included Premier and After Effects

    Hi, I was wondering what student plan included Premier and After Effects? It seems not to say anywhere...
    Camilla

    The Cloud has three plans:
    Full (all apps including Premiere and AE)
    Single App
    Photography Plan
    The Full Cloud includes the software listed here
    Explore Adobe desktop apps | Adobe Creative Cloud
    So you can either subscribe (at student rate instead of full rate) to 2 x Single App plans (Pr + AE) or a full Cloud plan and get all apps

  • Copy of Attachments at Item Level and Replicate the order with Attachment

    Dear Frnds,
    Here i have two questions ,
    1) I want to copy the attachments from Quotations to Sales Orders Item Level , it is possible at header level.Is there any way i can copy from Document to Document at Item Level.I tried copy control of item level its not working.
    2) After Sales order replication from CRM to ECC i should be able to see that Attachment in ECC.
    Please give your valuable inputs.
    Thanks in Advance.
    Regards
    RR

    We have been trying to do this for about 6 months now. I am told that you can not replcate an attachment from CRM to ECC, the best you can do is send an email from CRM with the document attached.
    Karin

  • Extending material with MRP (no planning file update)

    Hi,
    When you extend a material manually with the MRP-view , the planning file will be automatically updated after saving.
    Apparently this is not the case when doing mass change via LSMW. the planning file isn't updated.
    Can anybody confirm this ?
    Is it possible to make sure that the planning file is updated when executing the lsmw ?
    with regards
    Erik

    Hi Rupesh,
    Yes, but i would like to create receipts for the new requirments coming outside of the planning time fence (PTF). Let me explain with an example below:
    Product Structure: Header product (Currently in ECC MRP Type: P1) and 3 BOM Components (Currently in ECC MRP Type: P2)
    After CIF'ing all the materials to APO, we have the following dates in APO (giving just as an example)
    Today's Date: 1st Feb, 2015
    PP/DS PTF: 10th Feb, 2015 (10 Days)
    PP/DS Horizon: 10th Feb, 2016 (1 year from PTF)
    Scenario 1: If there is a new requirement coming on 5th Feb, 2015, i do not want the heuristic to plan/create new receipts (PReq's) even after the PTF. This is how currently it works with MRP Type 'P2' in ECC
    Scenario 2: If there is a new requirement coming after PTF (for e.g. on 20th Feb, 2015), I want the heuristic to plan for the new receipts based on the requirements date. This is currently working with this above settings, so i do not have to worry about this Scenario 2.
    Please let me know any other idea or work around for the Scenario 1 above. Basically all i want to see the heuristic is to ignore new requirements falling within PTF, but consider new requirements coming in after PTF.
    Thank you
    Regards
    PK