Delivery not created in Merchandise distribution - WF30

Hi Experts,
I am came accross an issue wherein delivery not created for merchandise distribution.
It is automatically created at the time of goods receipt.
We are using flow through process.
On same day, three PO created via allocation table. Each PO had its STOs linked to it and same article in it.
For two POs, merchandise distribution happened automatically on goods receipt.
For third PO, it failed for same article.
I can see in WF30, there is FT qty populated in adjust button.
That means qty is adjusted per STO.
But then delivery not created.
I am wondering why is is not created for one PO but processed successfully for another two POs.
Article master is not chenged.
Can anybody please advice, what could be the possible reason for it.

Sagar,
For the article in the third PO, please check what storage location is being picked up. Check the cumulative ATP quantity for this article/storage location (use Co09 with checking rule B). There maybe a shortage of stock.
Thanks,
Suhas

Similar Messages

  • Delivery not created in cash sales

    Dear Gurus,
    I am facing an error while processing a cash sales scenario.I am creating a sales order for cash sales and trying to save it.After saving system shows error as orders saved ,delivery not created.(message no V1261)
    I have checked all the configuration in document type.
    Immediate delivery is maintained as X
    Shipping condition - 03 immediately
    Lead time - 0 days
    The system is showing sufficient stock in MMBE. (the material is batch managed)
    still it is not creating delivery document.
    Against the message V1261 I found one SAP note but it is of 1998 and not valid for ECC 6.0
    Please suggest solution on highest priority.
    Rgds,
    Anand

    Hi there,
    I see it in 2 ways:
    1) If you want auto delievry immediately after the SO is loaded, then the order loading prog MV45AFZZ should call delivery prog SAPMV50A automatically if order type is BV after order save . For this you need to customize sothat delivery is created automatically after order is saved.
    2) If there is a manual delivery involved, check what error you are getting when creating a delivery. Pls refer to my  comments above to check the possible errors.
    Hope this helps
    Regards,
    Sivanand

  • Outbound delivery not created automatically

    Good Day,
    A STO posted from a supplying plant to a plant creates an automatic outbound delivery.
    When creating the STO with the same supplying plant and plant but a different material the automatic outbound delivery is not created.
    What settings should apply to the material as this seems to be the only different input between the two STO.
    The config settings seem correct as the automatic outbound delivery does happen when a different material is used.
    Thanks
    Lindsay

    Hi Lindsay,
    Check this note:
    1069448 - Outbound delivery not created automatically in ME21n for
    STO
    Also, note that this thread should be moved to Logistic Execution space. This way you can get more helpful answers.
    Kind Regards,
    Mariano

  • Outbound delivery not created

    Hi,
    I have the following scenario in STO:
    Planned delivery time for a material =2days
    When material delivery date is on wednesday , system proposed delivery creation date as monday-that is ok.
    When material delivery date is on thursday, system proposed delivery creation date as tuesday- that is ok.
    When material delivery date is on tuesday, system proposed delivery creation date as friday(2day minus as Saturday but since saturday is holiday , it take Friday)- that is ok.
    Problem is in situation:
    When material delivery date is on monday, system proposed delivery creation date as Friday(2day minus as Saturday but since saturday is holiday , it take Friday). Systematically this is ok but not physically as other plant has holiday on saturday and sunday , so if it get delivery on friday , they can't ship before tuesday.
    Please suggest, how this issue can be resolved.
    Regards
    Sandeep Kumar

    Hi Lindsay,
    Check this note:
    1069448 - Outbound delivery not created automatically in ME21n for
    STO
    Also, note that this thread should be moved to Logistic Execution space. This way you can get more helpful answers.
    Kind Regards,
    Mariano

  • ERP Delivery not created when triggered from TM

    Hello Experts,
    I have a OTR & Freight Order created in TM successfully. Could also assign a carrier to it. From the Freight order Management screen when the Send Delivery proposals to ERP, the system sends a XML message that is successful in TM. But in ERP there are no deliveries created. I could not see any error in the Queues or the XML messaged.
    My observation is there is no XML message in ERP system for the delivery creation.
    Could anyone throw some light on why the deliveries are not created?
    Regards,
    Vasu

    Thanks Marcelo,
    I missed to check the PI system, the message was stuck there since the mapping was missing in PI.
    Regards,
    Vasu

  • Automatic delivery not created

    Dear All,
    When i am making the the cash sales so in that case automatic delivery should be created even though the settings are fine....So when i am making the sales order some time it create the automatic delivery and some time it say that delivery is not created for same material.....so please throw some lights on it....
    Thanks & Regards,
    Mohsin

    Hi ,
    Check whether the material is relavent for delivery . coz some materials are relavent for delivery and some are not and check the material any blocks are there.
    that is also one possible reason.check the status of the sales order before u going to save . Also check the Copy controls of the sales document sales order to delivery.
    if its not let me know any thing information u required .
    Reward if Helpful...
    Regards
    Praveen Kumar.D

  • Single STO Outbound delivery not creating for different lines in PO.

    HI ALl...
    1... I  have 2 different ST PO which raised by other plant(plant is same), and it contains different line item.
    When try to do outbound delivery in VL10B, it is creating seperate outbound delivery doc to each item, but not created single doc for all items.
    Please let know, if any thing needs to be done, to get create single outbound delivery for all the items in PO.
    2... Is it possible to pick the Price automatically ( MAP of the supplying plant material), while create Billing in VF01.
    Regards
    Chandradhara...

    HI..
    I have checked and corrected Delivery date/ loading group and Transportation group, now it is coming single delivery document.
    OTHER REQUIREMENT IS;
    We need MAP of the Supplying Plant to be picked will do billing for PRICE condition. What settings should be done
    Regards
    Chandradhara

  • Delivery not created immediately after SO is saved

    Hi All,
    I created a document type ZB01 by copying from document type CS (cash sales). I tried to set the shipping conditions to be "immediately" and "as soon as possible". But after the sales order is saved, no delivery is created. Only after I changed immediate delivery from "X" (create immediately, if quantity can be confirmed) to "A" (create immediately), the delivery is automatically generated. But the problem shouldn't be related to the amount of goods in stock. I checked the goods in the specific plant, it has more than enough to confirm. And in the sales order, the quantity of schedule line is also confirmed. Can anybody help to explain this issue?
    Thanks, Jerome

    Hi,
    Irrespective of the shipping conditions, as long as the Immediate delivery (X or A) is set, the system should generate a delivery doc automatically. May be you can try this:
    Set the Immediate dely indicator back to X and then create a SO. If it does not create a delivery, open the SO in the change mode and then save again. Check whether it creates a dely doc this time.
    can you pls confirm whether this is working for you?
    Thanks,
    Siva

  • Delivery not created in make to order cycle

    Hi
    i am in the make to order process scenario and facing problems while creating a delivery after production order has been confirmed. The steps followed are
    1. i create an order with M1 and quantity 100 - T code : VA01
    2. i create a sales order BOM for the sales order created above and using material M1 - T cose : CS 61
    3. This is followed by a production cycle - planned order, production order and confirmation with lot size of 7.
    4. as one production order of size 7 is confirmed, the stock is generated of quantity 7 for the material M1. using MMBE i can see the stock being created.
    5. Now as i go and try and create the delivery against order created in step 1,  i get the error and that "No schedule lines due for delivery up to the selected date".
    6. When i check my order in display mode, under schedule line it shows M1 with order quantity as 100 and confirmed quantity as 0.
    Could you please advise if after the confirmation of production order, the schedule line in order will show quantity 7 and if i can delivery against it. Or is there any other way of creating the delivery.
    Thanks

    Hello,
    In MTO scenario the following happens:
    1. Sales Order is created - standard requirements type determined is KE which fetches requirements class 040. The requirements class 040 has controls for MTO & special stock indicator will have entry as "E-orders on hand".
    2. After MRP is run the system will transfer the requirements to PP, a planned order will be created which is then converted into a production order.
    3. After running the production cycle the goods will be transferred to the finished goods storage location.
    4. Now when you check in the transaction code MMBE the system will show the material stock & under the sales order stock only.
    5. But when you check the sales order -- line item schedule line, the system displays the confrimed quantity as "zero".
    Explanation:
    You created sales order for item A - 100 Quantities. Production was completed for 20 quantities. System shows sales order stock of 20 quantities only.
    When you had created a sales order for item A the system after running the availability check would have determined a delivery date by way of which it would have shown you say 2 different schedule lines as under
    Delivery Date.............Order qty............Rounded Qty...........Confirmed Qty
    01/05/2009...................100......................100............................0
    15/05/2009.....................0.........................0.............................100
    The second date the system determines taking into consideration the inhouse manufacturing time specified by you in the material master (MRP2 screen) & the other settings which aare applicable for the checking group specified in the material master.
    On 15/05/2009, if you create a delivery, the system will allow you to create the delivery irrespective of the stock in the plant. But at the time of post goods issue you will face a quantity deficit error.
    If the goods are received in the finished goods storage location before 15/05/2009 say on 10/05/2009, the system will not update the schedule line automatically & when you try to create a delivery the system will display the error "no schedule lines due for delivery".
    Solution:
    Transaction code VA02 - select the sales order number - double click on the line item - go to schedule lines - here click on the button "Item Availability" or press "Ctrl + F5" to run the availability check. As you have stock of  7 quantity, the system will display 7 quantity on the curretn date. Select the option delivery proposal to continue. Now the system will show 2 schedule lines as under
    Delivery Date.............Order qty............Rounded Qty...........Confirmed Qty
    01/05/2009...................100......................100............................0
    10/05/2009.....................0.........................0..............................7
    Save the sales order & then create a delivery. The system will not give any error.
    Note: You have to manually confirm the quantities for a make to stock sales order in case if the goods are received before the delivery date specified by the system.
    With best regards,
    Allabaqsh G. Patil
    Idhasoft Ltd.

  • Delivery not created for subcontract PO

    Hi ,
    I am getting following message while trying to create Delivery forsubcon PO. I am using the development client hence no question of transferring delivery type.
    Delivery type was not transmitted
        Message no. VL564
    Diagnosis
        The delivery cannot be created because the delivery type was no
        specified.
    System Response
        The system needs the delivery type to control further processin
        delivery creation. The delivery type must be transmitted by the
        transaction that creates the delivery.
    Procedure
        Check the Customizing settings in the transaction if necessary.

    Check the following steps carefully:
    First Create BOM in Transaction code: CS01, for your Finished product which you want to procure from the SC Vendor........in items you can give the Raw materials you are providing to SC Vendor.....Very Importanly, for the component you want to send to SC Vendor also should have the Sales view....then only the Shipping point determination and all takes place...
    Then in Transaction code ME11, create Sub Contracting Inforecord
    Then in OLME-->Purchase Order>Set up Sub Contract Order--
    > For your Plant from where you are shipping the material to SC Vendor, Assign Delivery type LB....
    Then for your Suppling Plant Sales Area, Create one Customer master and in that customer master assign your SC Vendor in General Data->Control Data Tab>In Vendor Field and In Sales Area Data-.> Shipping Data tab--
    >Maintain entries in Delivery Priority,Shipping Conditions,Delivering Plant fields.
    Then Create SC Purchase Order with Item catogary "L"....In Item details--->Material Data Tab--
    .>Components, you can view the details of the material you have to send to SC Vendor.... then save the PO
    Then Goto, Transaction Code, ME2O, choose the component and choose create Delivery....then Delivery no will be created.....then you goto VL02n and do the PGI...The components will be automatically transferred to SC Vendor in 541 movement type...
    After completion of work, you can do GR Normally...
    Hope I have explained in detailed manner
    Reward if useful

  • Delivery not created in background  for VL10 or VL10BATCH

    Hello,
    My client is using ECC6.0.  When I schedule a job in background for VL10 or VL10BATCH, only the delivery due list appears.  No deliveries are created.  Also referred to OSS note '310022 - VL10: Schedule batch job/variant creation' and changed the fcode profile to '5001' for the user role being used.  Still no deliveries are created.  Require your advise.
    Thanks,
    Thomas

    Hi,
    We also faced the similar problem so I would suggest you to put the program of respective transaction(for e.g VL10A/VL10B) in background and it will work fine.
    Regards
    Karan

  • Vl02 delivery not created

    hi all
    i am trying to do an intra company sto
    in vl10b purchase order shows up but when i am trying to create the delivery system gives message "see log for information about creating deliveries" when i am seeing the log two errors are there but i am not able to see detailed error description,
    stock is there in supplying plant with batch number and also valuation type trading stock is also available'

    Dear polly
    enough stock is available material is batch managed and having split valuation i am also checking considering both these requirements
    still the delivery is not getting created
    now when i tried to do delivery system says
    At least one order was blocked and could not be delivered
    4500000865 000000 At least one order was blocked and could not be delivered
    echnical data
       Tech. data details
        Client                                 101
        Group Number                           0000000308
        Sales Document Number                  4500000865
        Item Number of the SD Document         000000
        Schedule Line Number                   0000
        Counter in Control Tables              00
        Message Identification                 V50R
        System Message Number                  024
        Output Type                            E
        Message Variable 01
        Message Variable 02
        Message Variable 03
        Message Variable 04
        Group Type                             L

  • Plant proposal , delivery not creatd for rush order setting created

    Dear SD Gurus ,pls note the following problems  with IDES system and answer me
    -  Order with reference,the  quotation tab is missing ,pls advice .
    -  Even though i have created  customer -material info record the plant from this record is not getting proposed in sales order for this material .
    - I have created a sales doc typ zaaa which contatin the same settings as that of Rush order namely , delivery -immediately , lead time -0   but when i create a rush order it gives message delivery not created as scheduline confirmed is after 2 days .
    - as there any source to get latest ides data and export it to the ides data base and how we can do it .

    Hi,
    -Go to VOV8 and check settings there for reference.
    - While for rush order just check the Item Category settings. More importantly SLC settings.
    Regards
    SD

  • Delivery notes against STO

    Hi all,
    Is there any standard report to see the list of delivery notes created against Stock transport orders.
    Regards
    sappy

    You can see that in PO item detail history tab.
    For many POs you can execute ME80FN and then choose the history view

  • Need list of delivery notes delited

    Hi,
    I am new to MM and SD.how to get list of delivery notes created and which one got delited or processed in past with username who deleted and material no qty and Sales Order no.
    Thanks,
    Bipin Singh

    you asked the question already twice yesterday.
    Remember, there is a button to report abuse...

Maybe you are looking for

  • Formatted External Hard drive won't work

    I formatted my external hard drive using the MS-DOS(FAT) in Disk Utilities so I could use it on my windows and on my mac. After the formatting finished, I copied some folders to my hard drive from my macbook and ejected it, then plugged it to my wind

  • Fire wire external disk fails to mount

    Hello, I've been trying to work out how to access my LaCie external disk on my macosx 10.4.6. At first it worked well on both servers. After a while, the mounted icon simply disappeared. Try as I may, neither server mounts my external LaCie or any US

  • Oo4o-- error 429

    I have made a Excel macro command which uses OO4Ο automation to connect with a database(Oracle 7). In my PC(Windows NT) runs O.K but in other PC's where I tried,I got an error message (error 429: ActiveX can't create the object). Whitch references sh

  • SAP Agricultural Contract Management

    Hi, We are about to implement sap agricultural contract management in ECC6.0. Could someone please help me in links for best practices documents like configurations and business scenarios documents related to that. Thank You

  • My compiled program will not execute on my PC.

    I am new to Java so is there anyone out there who can help me with a problem. I have a compiled Java program, the basic Hello World beginner's file. The file will compile, but not execute. It will execute on other computers, but not mine. Can anyone