Employee cost should hit to Internal order

Dear Friends,
We started new plant and  hired employers ,cost center profit center not ready yet( we created one Internal order as over head order ).
Employee Cost through Payroll  so HR People has already created a new Organizational Unit and we have tagged it to an Internal Order.  We have hired some test employees and have run payroll for this newly hired employees.
So the system is throwing the following errors.
Error 1)*Account assignment objects are incorrect. No substitution is possible.*
*Message no. 3G209*
*Diagnosis*
*The account assignment object check showed that, from the point of view of CO, the specified account assignment is not valid, and cannot be replaced by the employee's master cost center or a substitute cost center. This item cannot be posted.*
Error 2)Internal error: No valid return value for segment found
Message no. 3G330
Diagnosis
No valid value was returned as a result of the segment check. The Customizing settings for the general ledger, however, request a value for the account assignment of the segment.
Error 3)No segment found
Message no. FAGL_ORG_UNITS007
Diagnosis
No segment could be derived for the current line.
However, in the Customizing settings for General Ledger Accounting, you have selected the segment as a mandatory balancing field. This means that a segment must be assigned in each line item.
System Response
The posting is rejected.
Procedure
Edit your segment derivation or make changes to the Customizing settings for document splitting.
Kindly suggest me onthis its very urgent.
Regards,
Sudha.

Dear Raviteja,
Thanks for your Reply ,
Allready i checked the link which you have provided but our case is different.
Actually the Employee Cost should hit to Internal order not  to cost center.(that is our requirement)
While creating internal order i didnt maintain  any profit center bcoz cost center and profit centers are not ready yet for time being we are planning to move Employee cost to internal order later we will settle to Cost centers once its ready.
Thanks & regards,
Swapna.
Edited by: swapnasudha chowdary on Jan 24, 2012 11:59 AM

Similar Messages

  • Sales order cost objective vs OKB9  Internal order cost object.

    Hi All,
    we facing an  issue with sales order cost objective vs OKB9 cost object.
    For IC PO service material, we assigned account assignment category 4.Reasonis Service material was not showing on G\R account.
    The G\L account 7898788, we assigned to Service Item (material type DIEN)  , for G\Cost 7898788 cost element is assigned in OKB9. Combination business + order 3478787.
    Now conflict with sales order cost objective vs OKB9  internal order cost object.
    While posting intercompany IR posting system thronging below error messageu2026
    Enter only one true account assignment
    Message no. KI249
    Diagnosis
    You made assignments to several objects in CO (cost center, order, project etc.). 2 of these have been created as true objects.
    System Response
    You are allowed only one account assignment for each cost-relevant account
    How to resolve this issue.. Do I make any config changes in the system to overcome this issue?
    Or any sub account to assin in VKOA config for internal orderu2026
    Regards,
    Adi

    Hi Waman,
    Thanks for your inputs.
    Issue :  IR failed to post for wax  Sales Order -> ICPO  - Error:  Enter only one true account assignmentu2019.
    Background:
    Original setup  in  Test system   & Productionu2013 account determination for servive (DIEN) account assignment category u20184u2019 was linked to G/L Account  34444444, As part of project orange u2019, account determination was linked to account u201889710100u2019.
    Account u20188970100u2019   34444444 was replaced with 8970100 ,is not linked to any cost center & always post with reference to IC Sales Order as per config in OKB9 based on company code (US99) + cost element (89701100) + business area (9yyy). This caused a conflict while posting IR, system could not determine exact order for posting financial value.
    Conflict:  Actual Sales Order 34789343 is  linked to PO via account assignment category & IC dummy sales order (8014331) is determine via config setting. Two cost objects cannot be linked to one IR G/L account booking.
    Regards,
    Adi

  • Cost center v/s Internal Order

    Hi
    What is the difference between a cost center & Internal Order
    Regards
    Samir

    Hi Samir,
    Cost Center is an Organizational unit within a controlling area that represents a clearly delimited location where costs occur. You can make organizational divisions on the basis of functional, settlement-related, activity-related, spatial, and/or responsibility-related standpoints.
    Cost Center is a CO Object maintained on long-term basis to capture costs related to particular type of cost based on functionality, nature of cost etc.
    An internal order is used to monitor parts of the costs, and under certain circumstances, the revenues of the organization.
    Internal Order is a CO Object maintained to capture the costs of specific purpose (like campaigns, events etc) which is of short-term purpose.
    Let us understand the difference with the following example...
    If you have a Cost Center "HR Department", whenever some expenditure is incurred for HR Dept, that cost will be booked to HR Dept Cost Center.
    Let us assume that your company is about to take up a Recruitment Campaign (like campus placements) for about 3 months all over the country.
    So, you can create an Internal Order "Recruitment Campaign". The Internal Order can be "Real" and "Statistical".
    If you create the Internal Order as a "Real" object, then, at the time of booking the expenses relating to Recruitment Campaign, all costs will flow to the Internal Order and then, costs will be settled to your "HR Department" Cost Center at the period-end.
    If you create the Internal Order as a "Statiscal" object, then, at the time of booking the expenses, you can select your "HR Department" Cost Center as well as your "Recruitment Campaign" Internal Order as CO objects. In this case, real postings will happen to Cost Center and statistical postings will happen to Internal Order. There will not be any requirement to settle the Internal Order to Cost Center. Here, this statiscal internal order will be information purposes only...
    Hope this is clear, pls revert back for further explanation...
    Srikanth Munnaluri

  • Finance and Controlling report in combination with Cost center, GL account, Internal Order

    Hi Members,
    Finance and Controlling report in combination with Cost center, GL account, Internal Order.
    Please provide any slandered report in all 3 dimension.
    Thanks
    Dileep Kumar

    Search this query in FI Controlling forum am sure you will get useful results there.
    This kind of reports related to Controlling are usually created using Report Writer tool.
    In fact majority of reports in Controlling component is created using Report Writer only.

  • Compare the cost element of each internal order

    Hello All,
    How can we compare the cost element of each internal order?
    let me know how can we maintain the budget for each cost element for each internal order.  so that along the year, we can compare budget and actual for controlling purpose.
    Thanks
    Naveen

    Hi,
    I guess you mean comparing plan value by cost element for different IOs.
    If you want to compare those (same as actual), you could put internal orders, ranges or groups into the respecitve columns. I also did this once I think for car costs, where the manager wanted to see 10 cars next to each other and compare them (in this case it was actual figures, but same is possible with plan values).
    You just need to unselect IO on general data selection and use this as characteristic in the columns then.
    hope this helps?
    regards
    Bjoern

  • Cost Break Up of Internal Orders-Overhead

    Hi mates,
    I have created an internal order with an object class: u2018Over Headsu2019, for which costs were pooled and finally internal orderu2019s balances, are to be settled against the FG material.
    I want to see the cost components breakup for the costs incurred in the internal order.
    Can anybody help as how and where to link the cost component structure to the internal order, so that I could see the cost break up and also request to give the areas of integration between Project System and Controlling
    Thanks in advance
    KS

    Hi,
    Report S_ALR_87012996 will be of help to you. For settlements, you look in the config for Allocation structure & settlement profile that your order/order type is assigned to.
    Thanks
    Jagdish

  • Inaccurate JE hitting wrong Internal Order

    Hi
    We got a journal entry posted during the month of February through FI (FB50). The JE got one P&L a/c (debit) and balance sheet a/c (credit). The P&L entry consist of a real internal order..That particular internal order consist  of a budget (KO22) as well JE was posted for February without any errors. Budget also consumed accurately. The internal order was settled (KO8G) during the month end for the month of February and it had hit the respective cost center without errors.
    This month we realized that the JE should not have been used an internal order. It should hit only a cost center. Not an internal order.
    How to correct this entry? Please let me know the steps.. Budget also need to be revised to the original figure
    Thanks

    Hi Srikanth
    Thanks for the reply
    The orginal JV was posted by,
    Debit - Expense (with internal order)
    Credit - Bank
    Internal order was settled during the month end and it has hit the cost center.
    If I do the JV you mentioned, dont you think the cost center value will be double coz the settlement of the internal order has hit the cost center as well?
    What will happen if I reverse the JV through FB08 and put a new JV with correctly..and suppliment the budget through KO24?? I guess the internal order problem will not get sorted if I do that right??
    Thanks

  • Statistical posting to Cost Center using Statistical Internal Order

    We have a delivery transction in SD which used both a statistical order and cost center as account assignment objects.  However, in the cost center report, the amount was shown in the statistical portion of the report.  Why could have happened?  Shouldn't the item be shown as a true posting?

    When you post to an internal order and cost center one of these is statistical
    When you say the internal order is satistical then you have actual cost on costcenters. When the internal order is not statistical the internal order get the actual cost and the cost center statistical.
    In the fieldstatus group from the internal order you can make the field statistical requered. When you want only to have statistical cost on your internal order.
    With CO-PA it is an different case, see the other reaction on this. But then it is better to use profit center accounting for reporting. 
    Note SD is posting sales (sales cost) and there should no reason to post it on a cost center
    Paul

  • Account assignment category for cost centre and statistical internal order

    When issuing purchase order, we use account assignment category u2018Fu2019 for (PM) order, and u2018Ku2019 for cost centre.  What account assignment category to use, when issuing purchase order, if we want to charge to both cost centre (as mandatory) and statistical internal order (as optional entry field)?
    Do you create custom account assignment category for that purposes? 
    I reviewed Note 305385 but do not think it's relevant to us.

    Hi Stacy
    you can create a custom acct assgn category (AAC) in OME9... COPY the K to Z and make changes in it
    However, I feel the Std AAC K should serve your purpose if you want to have Cost Ctr as mandatory and Order as Optional
    Br, Ajay M

  • Is there a way to redetermine the cost center for an internal order on a PO

    When we create a PO for an asset we enter an internal order number and a cost center is determined from the internal order. Sometimes after the po is created the cost center on the IO changes. The po is not updated automatically on the PO and it results in the wrong cost center being posted to during the Goods Receipt and invoice receipt. Is there a program or batch job that we can run that will redetermine the accounting data on a PO?
    Thanks!
    Chris Lintner

    When we create a PO for an asset we enter an internal order number and a cost center is determined from the internal order. Sometimes after the po is created the cost center on the IO changes. The po is not updated automatically on the PO and it results in the wrong cost center being posted to during the Goods Receipt and invoice receipt. Is there a program or batch job that we can run that will redetermine the accounting data on a PO?
    Thanks!
    Chris Lintner

  • To make Cost Center Mandatory on Internal Order

    We want to make the Responsible Cost center Mandatory on the Internal Order. Can you pls let me know the config. piece of it.
    Thanks in Advance.
    Vineet

    In SPRO-Controlling-Internal Orders-Order Master Data-Screen Layout-Select Fields. Select your order type. In the area Master data display select Field selection. There you make the fields you want as mandatory, display or hide.
    pls assign points if helpful as a way to say thanks.

  • PO should not exceed Internal Order Value ( Check Required )

    Hi experts,
    Ideally PO should not be made for more value than the sanctioned amount raised through  Internal Order no ( KO01).
    But we find that users are creating PO for more value than the sannctioned value in internal order no.
    Check is required .  Pl. suggest how it can achieved.
    Regards,
    ( Rajneesh Gulati )

    Hi,
    In SPRO
    Controlling>Internal Orders>Budgeting and Availability Control-->Maintain Budget Profile
    Maintain Budget profile and assign  to the order type.(Controlling>Internal Orders>Order Master Data-->Define Order Types)
    Maintain Tolerances in below path.
    Controlling>Internal Orders>Budgeting and Availability Control-->Define Tolerance Limits for Availability Control
    You can maintain the tolerance limits with which in PO, you can give error or warning message when the value exceeds.
    Regards
    Edited by: Varaghamurthy  Chakravarthy Kannan on Sep 2, 2009 11:14 AM
    Edited by: Varaghamurthy  Chakravarthy Kannan on Sep 2, 2009 11:16 AM

  • Cost and Revenue of Internal Order

    Hi
    The table for internal order master data is AUFK
    but when we assign internal order to sales order and subsequently revenue and cost are booked ,it is accumulated in the same internal order
    In which table do we find the actual cost and revenue for  the internal order
    Thanks and Regards
    Sunil

    hi..
      For internal order level expenses elementwise please use table COEP. Earlier one i mentioned for Material Ledger related cost componant split.
      thanks
      kkumar

  • Change cost center in statistic internal order

    Hello all,
    I have got a problem with the master data of our internal orders. We´ve defined them as statistic objects, and the information of the cost center is an obligatory input within the master data of each internal order. After the first entry has been done the cost center can not be changed anymore. Now we have the necessity to change the cost center in all our internal orders once. Could you help me to find a solution how the cost center remains a changeable input in the master data of a statistic internal order? Or how I may change the cost center just once?
    Thanks for your help.
    Best regards,
    Bettina

    Dear Sir,
    The field is greyed off if the following is applicable:
    -> the order has planned or posted entries
    -> you have created a settlement rule on it.
    If you want to have the field to be changable, please apply the modification note 198036
    regards
    Waman

  • Recover cost element associated with internal orders. Tx KPF6

    Hi,
    I need to recover only the cost element associated with the internal orders listed in tx. KPF6. Can anyone please tell me how can I do this?, do I need to copy the entire tx to a Ztx?? or can i do this through an User Exit???
    Thanks, Fiorella

    Hi Fiorella,
    Try using table AUFK.
    It gives you the Responsible cost center as  well as the Cost center for basic Settlement for a particular internal Order.
    In case you need any other information, feel free to revert.
    Thanks,
    Sonal
    P.S. Would it be helpful if i tell you how to get Internal Orders from an Internal order Group??

Maybe you are looking for

  • Open hyperlinks in html text using StageWebView instead of external browser

    My iPad app downloads xml data from a server and displays it as html text. The text may contain hyperlinks and currently these are correctly displayed as links in my app. However when I click on the link, it opens the link in an external browser. Any

  • Report with stored proc running multiple stored procedures with insert statement

    Hi, I wonder if this is possible in SSRS ... I use the 2012 version (Data Tools). I have a report that triggers a stored procedure. See below. Within this SP there are 2 insert statements getting data from 2 other SP's. When I make a dataset referrin

  • Hiding a column while keeping the data in the TableModel

    Hello I am reading data in from a database and I add the data from the resultSet to a vector of vectors. e.g my table user_id | user_fname | user_lname | prj_id | prj_name I am reading in the above information but I dont want to display the id fields

  • A grumble about Losing Purchased music -relying on Time Capsule to backup

    I am annoyed. Our house has -three ( yes three Time Capsules - an Apple Tv - three (yes three Mac minis) - a mac laptop - A mac desktop - 2 iphones -2 ipod touches - 2 ipads And all my music was backed up on one of the time capsules.The mobile devise

  • Audio mixer volume problem

    I'm working with CS3. My timeline has two audio tracks. Track one is the clip verbal audio, that track is fine. Track 2 is the music that I want to fade in and out at certain chapter intervals. After adjusting all the volumes in track 2, when I go ba