Enterprise Work Resource Changed to Material Resource MS Project Pro 2010

Hi,
There is a resource, I believe at some point was an enterprise work resource that changed to a material type resource within an enterprise project schedule. The resource have actual hours booked a while back. Is there a way to change the resource type (from
Material) to work? I am able to search for the user via Server Settings > Manage Users but am not able to find her in the project center (All Resource) in hopes to edit the enterprise resource through the Project Pro Client. 
Thanks.

Hi Paul,
You have to go through the RESOURCE CENTER, since it is a material resource, you will not find it under "server settings, manage users" which only allows you managing users and not resources
Hope this helps,
Guillaume Rouyre, MBA, MVP, P-Seller |

Similar Messages

  • Function works in MS Project Pro 2010, but not in MS Project Server 2010

    I have an custom enterprise text field in Project Server 2010 that uses the "Instr" function and it works fine.  I created a local custom text field in MS Project Pro 2010 that was similar, but uses the "InstrRev" function and
    it works fine.  I then go to project server 2010 and try to create a custom enterprise text field using the "InstrRev" function and I get a message that says, "This formula contains errors.  Correct the formula and try again." 
    It's the exact same formula that I tried in project pro - copied and pasted.  Why is that?  Does Project Pro allow for a wider range of VBA functions in local custom fields than Project Server does when creating enterprise custom fields? 
    Is there some way around this? 
    Thanks,
    Joe

    Hi Joe,
    There is a way around it.
    Logon to MS Project Professional.
    Creat that field there
    Add Field to Enterprise while in MS Project.
    It has just worked for me.
    Please let me know if it worked for you.
    Best Regards,
    Alex

  • Changes in material transferred to project structure.

    Hello,
    It is required to track the changes made in material transferred to project structure alongwith User Name. (eg: Deletion of magterial, Incerease/decrease in qty etc)
    In assignments, we can only see the Username of the person who has  made the last change.
    Kindly help.

    Hi Nidhi,
    Please refer to SAP note : 1127691.
    In this note Point 5  CNEX0026 -- EXIT_SAPLCOMK_005 will help you.
    This user exit is used to check if there are any changes done to the material component in the component overview screen or the details screen of the material component.
    Regards,

  • Configure working times in project pro 2010

    Hello.   Our company has project server 2010 up and running.  I am a project scheduler, and I am needing to schedule 6 hours of work per day (8AM-3PM, for example).  I believe, based on the research I've done, there are a few ways to
    do this, including adjusting resource calendars/changing working times.  My issue is that when I go to "Change working times", then "work weeks", "Details" is disabled, due to the way the server admins have set-up permissions.  
    I think the admins can create me a customized calendar...just looking for any outside-the-box recommendations/ideas out there for how to do this, given the constraints i've mentioned?
    Thanks,
    Ryan

    Pardon me for bumping in.  As you note, there are a couple of options available - one is to drop the calendar for the project (and base calendar for resources) to 6 hours per day - 30 hours per week.
    If you choose to go with that answer, yes, it is best to set the definition of "day" to 6 hours and definition of "week" to 30.  I would also change the default start and end to match the calendar.  All are taken care of in
    File > Options, Schedule.
    There are no real risks of not having the calendar match the working time - just strong possibilities for significant confusion.  For example:  you've change the working time in the calendar (Work weeks) to 08:00 to 3:00 pm - but still left your
    definition of "day" to 8 hours.  You add a single task to the project with the default 1 day duration.  The task will start on Monday but end on Tuesday because you have only allowed 6 working hours per day.
    The order of preference for scheduling and calendars:  Project calendar initially.  Resource calendar when you assign resources.  Task calendars may over-ride resource calendars.
    Another suggestion:  leave the working time and definitions to 8 hours per day.  If you want to indicate that your resources can only generate 6 hours of work on tasks in your project during any given 8 hour day, set the resource's maximum units
    to 75%.  If you assign a resource and enter 8 hours of work, Project will increase the task duration.
    I hope this helps.

  • Enterprise Formulas Disappear After Performing File Save in Project Server 2010 in BCM

    We are in a transitory state with our Project Server in 2010 in Backward Compatibility Mode (BCM) while we wait for users to get their 2010 clients.  We have been having users complain that formula-driven enterprise fields are not updating. 
    When I would look at the field, everything would be fine.  One user then determined that the formula would disappear only after performing a File==>Save while in the client.  If you close the file, then re-open the file, the formula magically
    re-appears.  We then determined that the problem is only effecting some enterprise field formulas. There is also no pattern to which formulas disappear and which remain.  For example, we have two enterprise fields to compute the variance with the
    original baseline date; one for the original baseline start and the other for the original baseline finish. One formula will disappear and the other will remain.  The formulas are almost identical and the configuration settings are identical.  The
    only thing consistent is that it seems to affect the same fields each time. 
    We are already looking ahead to getting off BCM and we have yet to see the problem in our test server where BCM is turned off.  Also, the problem is only affecting clients that are using v2010 and our v2007 users have been spared.  Needless to
    say, these problems are spooking our user community and people are telling their IT people to delay the installation of their 2010 clients.  This puts us into a Catch-22 since we believe the problem will disappear once we turn-off BCM, but we can't get
    off BCM until all the users have their 2010 clients and now the users are resisting getting those clients.
    Does anybody know some hidden configuration setting that will solve our problem? I am really growing weary of these bugs.

    Hi Chris,
    Have you thought about a corrupted local cache for v2010 users? This could corrupt custom fields.
    You might try the following:
    Close and exit MS Project Professional 2010 application (if already open on your machine)
    Click on Start menu -> Run
    Type %appdata% and click on "OK"
    Navigate to the Microsoft\MS Project\14\Cache folder
    Delete all of the folders and files in this directory
    Hope this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • QUERY SQL - Change history between baselines in Project Server 2010

    Hello Guys
    It is possible to identify in a SQL query which changes were made between different baselines?
    Can provide a code example or on the subject. 
    Thank you.
    Obrigado por contactar o fórum Microsoft Technet!

    Hi,
    The MSP_EPMTask and MSP_EPMTaskBaseline table columns in the reporting schema can be used to compare current project schedule against different baselines (use baseline number to filter the required baseline). In the same way different baselines can
    be compared, however, the comparison will make sense at project level as different projects may use different baseline sets (0,1,2,...,10) unless you have an organization level baselining methodology/process (e.g. use baseline 0 in January, 1 February
    etc.) 
    Also, the date when a particular baseline was saved can be found in the published database/schema
    Hope this helps
    Paul

  • Changing "material status" via "project transfer"

    HI,
    I known that I can change the "material status" by transferring an item to a specific stock Locator that I already defined.
    Is it possible to change the material status via project transfer?
    For example my item's status is "active" and it was assigned to a project named "ACTV_PROJECT" I transfer this Item
    to a random locator whose project is "HOLD_PROJECT". while I perform this transaction, item status will become "HOLD" (Hold is a status that I already defined)
    Thanks for your
    Help
    Ceyhun

    Hi
    I assume you refer to Item Status Control.
    You can update the item status code using the designated form Item Status. This will automaticlly update the values of the following attributes -
    BOM Allowed
    • Build in WIP
    • Customer Orders Enabled
    • Internal Orders Enabled
    • Invoice Enabled
    • Transactable
    • Purchasable
    • Stockable
    Project Transfer is a inventory transaction, that moves certain quantity of the item from one project locator to another project locator. Such transaction is not changing the item status.
    Dina

  • Resource Center - Need to change a Local Resource to an Enterprise Resource

    The Resource Record for a resource was accidently deleted.  This resource was still assigned to active project tasks at the time of the delete.  A new Resource Record was created but it has the resource as a Local Resource.  How can I move
    this resource back to the Enterprise Resource Pool?
    As a Local Resource the Assignment Owner field on his assigned tasks are not populating, so he cannot see any tasks on his timesheets.  Also, the resource cannot be assigned to any new project tasks because he cannot be added to the Project Enterprise
    Pool.
    Attempted to remove the Resource Record that was created using Delete Enterprise Objects -> Resources and Users but since the resource is Local and not Enterprise his record is not showing to select it for delete.
    Would the Admin Restore->Enterprise Resource Pool and Calendars functionality put his original record back in place?  I understand only one version of this backup is kept but that should be the version we currently have.  What data might be
    lost using this functionality?  Any chance other users would be adversely impacted?
    We are using Project Pro 2010

    Hi Dennykat,
    As mentionned in your previous post, restoring the resource pool should work, since it is restoring resources with their metadata and with the exact same UID. Thus the deleted and restored enterprise resource should have everything back (assignments, timesheets...).
    Since I never tested such as process, I strongly advice to test it in the dev environment on a simple test case.
    I remember that if also adviced you to recreate the enterprise resource and type in the resource sheet on one of the resource's project the exact enterprise resource name (exact same syntax), so Project should ask you when saving if you want to replace the
    local resource by the enterprise one. Can you confirm that it didn't work?
    Hope this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • Project Server 2010 - Active Directory Enterprise Resource Pool Synchronization limitations

    Greetings again.
    I have a quick question about the limitations of Active Directory Enterprise Resource Pool Synchronization.  Specifically, what has your experience
    been with extremely large numbers of users (10k plus).  Is anyone aware of a
    practical limit of users in your AD group you would recommend when using the
    Schedule Synchronization feature on a nightly or weekly basis?
    There is a caveat to this question however.  The client has decided (perhaps for some misinformed reasons) to allow access for every user, to every
    project site, within their PWA environment.  They’ve selected the View Project Site option within the
    Categories for the Team Members PWA Group for which 90% of their intended users reside.  So when we ran a couple test syncs in DEV with a smaller AD group of about 8,000 users, the sync understandably
    lasted upwards of 18 hours.  Obviously unacceptable for a PROD environment on a nightly basis and not necessarily ideal for a weekly sync either.
    Experience in addition to documents like these, “Best
    practices for managing a large number of resources in Project Server 2010” tell me that we are way over the practical limit of a scheduled resource pool synchronization...IF
    the client really desires that all users access all their sites.  But before I submit my recommendations, I wanted to check with the community just in case others may have found a way to synchronize large numbers of users (10k plus) on a nightly or weekly
    basis, within a reasonable time frame AND allowed all users to access all sites within PWA.
    What do you think?
    As always, thanks for your help.
    Chris Addis - MCTS

    Hello Hrishi.
    My delayed response has been due to a large amount of testing we have been performing on this particular topic.  Here is an update, please feel free to provide feedback.
    We went back to testing and spent more time reviewing the documents: 
    Best practices for managing a large number of resources in Project Server 2010 and
    SharePoint Server 2010 capacity management: Software boundaries and limits.  Our team interpreted those documents as saying, 1,000 security
    scopes per site is a recommended limit.  It does not say it’s a hard limit, just a recommended limit.  “When the recommended unique security scope boundaries are exceeded, performance issue can occur.”
    So we decided to perform some tests (31 in total) to try and get a gage of what we are seeing.
    We needed to establish a baseline first.  So we performed a series of 23 Active Directory Resource Pool Synchronizations with various settings in a clean, Out of the Box, environment in order to see some consistent numbers.  Here is it’s summary:
    Our AD group of 8,000 users took about 32 minutes, on average, every time to sync.  The difference between the first sync and last sync differed only by 1-3 minutes.
    Adding 40 project sites increased the average sync time from 32 to 120 minutes.
    Adding 100 users to each of those 40 project sites, did not increase the sync times.
    One setting (identified at this time) reduced the synchronization time.  It was the
    Project Site Permissions check box found within the Project Web App > Server Settings > Project Site Provisioning Settings area.  By deselecting this check box we reduced or synchronization time back to the 32 minute
    average.
    The View Project Site check box within the Project Web App > Server Settings > Manage Groups > Team Members group had no apparent effect on the sync times besides what we had gleaned from the Microsoft documentation.
    Naturally, this left us with a problem.  As I’m sure you know, by deselecting the check box (Project Site Permissions), our project sites are now (figuratively speaking) orphans with no connection to the parent site.  This generates
    a new set of issues.  For example:
    Newly created project sites cannot be accessed by the owner and team members.  They will require someone like the farm admin to come in behind them and add the intended users to the project site along with their required permissions.
    All current and futures sites will no longer have users added via the standard method of building a team and publishing the project, but will have to be added manually.
    You can use the Synchronize option found within Project Web App > Server Settings > Project Sites page, but that kinda defeats the purpose.  It would require constant updating on a per site basis to keep up with
    PM changes.  Not very sensible, but it does work.
    With this baseline information, we moved our tests into our DEV environment which somewhat mimics our PROD environment.  This environment has 352 project sites and we performed 8 tests.  This is where we had some large sync time numbers. 
    Here is the DEV test summary:
    With the Project Site Permissions check box cleared, our AD group of 8,000 users took on average 30 minutes to sync.  This was in line with our baseline times.  With the exception of one test sync that took 99 minutes to complete. 
    That anomaly is acquiescent with what I’ve seen over the years.  Sometimes syncs do some unusual things.
    With the Project Site Permissions check box selected, our AD group of 8,000 users took on average 690 minutes (11.5 hours) to sync.  Unacceptable of course.
    So here’s what we’ve learned when dealing with extremely large numbers of active directory users in your Resource Pool sync:
    We did not see a decrease in subsequent sync times after the initial Active Directory Resource Pool Synchronization as some might expect.
    Our attempt to decrease sync time via the option of removing the View Project Sites was not successful.  (Unless we interpreted Microsoft's document incorrectly.)
    However, our interpretation of the recommended software boundaries and limits of SharePoint Server 2010 as it pertains to security scopes per site at 1,000, appears to be correct.
    Using the option of clearing the Project Site Permissions does produce a reduction in AD sync time, but at a cost segregating your project sites and thus the creation of new processes of maintaining them.
    I’ll remind others that these results are particular to our environments, there may still be exceptions yet to discover.  Others may see numbers contrary to ours.
    The biggest surprise to some members on our team (myself excluded) was that we did not see a reduced sync time after any of our initial syncs.  Some are under the impression that after your initial sync, you should see reduced sync times.  I haven’t
    found that to be the absolute case in all situations, just in some situations.  The reason for this still eludes me.  Any thoughts would be appreciated.
    I’ll let this sit a bit longer, but if no one disagrees with the results, I think we have our answer:
    The number of project sites directly affects your Active Directory Resource Pool Synchronizations if you are using the
    Project Site Permissions option.  If you plan on synchronizing over 1,000 users
    and you have a large number of project sites, proceed with the knowledge that you may have performance issues and long sync times.
    As always, I’d love to hear from you or others just in case I’m missing something.
    Chris Addis - MCTS

  • Bulk changes to Common Resource Parameters

    Hi,
    I need to make changes to many disks and file server resources at once in my cluster.
    The settings I need to change are in the common properties for resources:
    http://msdn.microsoft.com/en-us/library/aa372230(v=vs.85).aspx
    RestartPeriod
    RestartThreshold
    SeperateMonitor
    but when I use this:
    get-clusterresource "cluster disk 104" | get-clusterparameter
    All I get are private properties about the disk. I don't understand how I can bulk change the parameters on the disks or file servers in powershell for common parameters. Does the set-clusterparameter still work for these even though they are not displayed?
    I really do not want to do this manually in the GUI.
    Just to clarify, I wanted something like this:
    get-clustergroup "Group 1" | get-clusterResource | Where {$_.ResourceType -like "Physical Disk"} | set-clusterparameter -name RestartPeriod -value xxxxx
    But I am not sure this will work as if I use "Get" I do not see that particular common parameter listed
    Thanks

    I managed to work this out. It was so easy in the end I was kicking myself.
    Lets say you want to change all DFSR resources that are set to failover if they fail:
    $NeedFixed = get-clusterresource | Where {($_.ResourceType -like "DFS Replicated folder") -and ($_.RestartAction -eq 2)}
    Foreach ($Resource in $NeedFixed) {$Resource.RestartAction = 1}
    or for disks you want to change some settings:
    $GroupDisks = get-clustergroup | Where {$_.Name -like "Groupname"}| get-clusterresource | Where {($_.ResourceType -like "Physical Disk")}
    Foreach ($Disk in $groupDisks) {$Disk.RestartAction = 1; $Disk.RestartPeriod = 1800000; $Disk.RestartThreshold = 10 }
    Thanks

  • Project Server 2010 , Project Center, Resource Center, My Work not loading

    Hi,
    We have Project Server 2010 SP-2 env
    Yesterday one of my Project Manager told me that he is not able to access any of the following page Project Center, Resource Center, My Work in our Quality env. Issue is it shows page is loading infinitely long and on botton it shows some script error mentioned
    below
    Webpage error details
    User Agent: Mozilla/4.0 (compatible; MSIE 8.0; Windows NT 6.1; WOW64; Trident/4.0; SLCC2; .NET CLR 2.0.50727; .NET CLR 3.5.30729; .NET CLR 3.0.30729; .NET4.0C; .NET4.0E)
    Timestamp: Tue, 21 Oct 2014 13:55:19 UTC
    Message: 'null' is null or not an object
    Line: 217
    Char: 4
    Code: 0
    URI: http://XXXXXXXXXXX/_layouts/inc/pwa/library/webmethodmanager.debug.js?rev=BtnvMSOtt14tg%2FnfhDTJpA%3D%3D
    Also I have checked event logs in shows WebHost failed error with Event ID 3 , complete detail mentioned below.
    Event Log Error
    WebHost failed to process a request.
     Sender Information: System.ServiceModel.ServiceHostingEnvironment+HostingManager/45523402
     Exception: System.ServiceModel.ServiceActivationException: The service '/_vti_bin/PSI/ProjectServer.svc' cannot be activated due to an exception during compilation.  The exception message is: Could not load file or assembly 'FirePoint.SharePoint.RssViewerWebPart,
    Version=1.4.7.12, Culture=neutral, PublicKeyToken=e891f27e2edd24d0' or one of its dependencies. The system cannot find the file specified.. ---> System.IO.FileNotFoundException: Could not load file or assembly 'FirePoint.SharePoint.RssViewerWebPart, Version=1.4.7.12,
    Culture=neutral, PublicKeyToken=e891f27e2edd24d0' or one of its dependencies. The system cannot find the file specified.
    File name: 'FirePoint.SharePoint.RssViewerWebPart, Version=1.4.7.12, Culture=neutral, PublicKeyToken=e891f27e2edd24d0'
       at System.Reflection.Assembly._nLoad(AssemblyName fileName, String codeBase, Evidence assemblySecurity, Assembly locationHint, StackCrawlMark& stackMark, Boolean throwOnFileNotFound, Boolean forIntrospection)
       at System.Reflection.Assembly.InternalLoad(AssemblyName assemblyRef, Evidence assemblySecurity, StackCrawlMark& stackMark, Boolean forIntrospection)
       at System.Reflection.Assembly.InternalLoad(String assemblyString, Evidence assemblySecurity, StackCrawlMark& stackMark, Boolean forIntrospection)
       at System.Reflection.Assembly.Load(String assemblyString)
       at System.ServiceModel.Activation.ServiceHostFactory.CreateServiceHost(String constructorString, Uri[] baseAddresses)
       at System.ServiceModel.ServiceHostingEnvironment.HostingManager.CreateService(String normalizedVirtualPath)
       at System.ServiceModel.ServiceHostingEnvironment.HostingManager.ActivateService(String normalizedVirtualPath)
       at System.ServiceModel.ServiceHostingEnvironment.HostingManager.EnsureServiceAvailable(String normalizedVirtualPath)
    WRN: Assembly binding logging is turned OFF.
    To enable assembly bind failure logging, set the registry value [HKLM\Software\Microsoft\Fusion!EnableLog] (DWORD) to 1.
    Note: There is some performance penalty associated with assembly bind failure logging.
    To turn this feature off, remove the registry value [HKLM\Software\Microsoft\Fusion!EnableLog].
       --- End of inner exception stack trace ---
       at System.ServiceModel.ServiceHostingEnvironment.HostingManager.EnsureServiceAvailable(String normalizedVirtualPath)
       at System.ServiceModel.ServiceHostingEnvironment.EnsureServiceAvailableFast(String relativeVirtualPath)
     Process Name: w3wp
     Process ID: 5052
    Also I have checked Brian Smith blog to resolve WebHost error with Event ID 3, but that didn't help.
    So kindly help me to get this issue resolve and do let me know in case need further details.
    Thanks

    Hi,
    From error log it seems you have some custom or thrid party web part activated in your application and that web part is not able to load which might causing those pages to get corrupt.
    As a fix can suggest you below to two thing to check
    1) Remove that "FirePoint.SharePoint.RssViewerWebPart" from your environment and try to access those PWA pages again.
    2) Even after removing above web-part solution does not fix this issue, as it is quality env can you try to disconnect and reconnect the share-point farm . Then try to access those pages again.
    Share us the latest update and your finding on this issue.
    Regards
    Sachin Vashishth MCTS

  • Changing the material options for multiple selections doesn't seem to work

    Hi!
    Is it just me or is it not possible to select multiple layers and change their material options like specularity and shininess all at once? Selecting the layers and clicking on cast shadows certainly does work like this, but for some reason when I do the same and change the specularity, it changes only for that layer, regardless of the selection for the other layers.
    Are you able to change material options for multiple layers in one click?

    Works for me... Not sure what else to say. The only thing to consider would be that you need to expose the same properties on all layers or else AE can't match the property streams, so it may be advisable to hit AA to expose all material options instead of just U or UU to reveal changed/ animated properties.
    Mylenium

  • Material-resource-cost center list

    Dear Friends
    where can i get the list of the Materils related to resourcese +  costcenter .
    which materils are using the costcenter with resource name i  want to know.
    Please let me know.
    Regards,
    srihari.M

    Hi Srihari,
    There is no standard report available to link material, resource and cost center.
    Like Vishal said u have to use the tables and link them through T-Cose SQVI and assign it to a Z tcode.
    Regards
    Suri

  • MAterial Resource Planning (MRP)

    Hi,
    Can you tell me what is Material Resource Planning (MRP)? How & why is it used in SAP MM?
    Regards,
    Krutika

    hi
    it is Material Requirements Planning
    Material Requirements Planning (MRP) enables you to plan material requirements for a manufacturing or procurement process.
    MRP calculates gross requirements for the highest Bill of Materials level based on sales orders and independent demands. It calculates gross requirements at the lowest Bill of Materials levels by carrying down net parent demands through the Bill of Materials structure. The dependent levels might have their own independent demands, such as sales orders and forecasts.
    The results of the MRP run are recommendations that fulfill gross requirements by taking into consideration the existing stock levels and existing purchase and production orders. The MRP run also takes into account defined planning rules for Order Multiple, Order Interval, and Minimum Order Quantity.
    Recommendations are back scheduled by the defined lead time to arrive at the requirement dates for their own components.
    plz check following
    http://www.saptechies.com/category/production-planning/material-requirements-planning/
    http://www50.sap.com/businessmaps/1BD448892DEA413E9D270C761DEB251C.htm
    http://www.sap123.com/showthread.php?t=89
    http://www.sap123.com/showthread.php?t=57
    http://jan.ucc.nau.edu/tlj3/MRP%20and%20Material%20Purchasing%20with%20SAPSCH.doc
    regards
    kunal

  • Change default "new resource avaible" behaviour on Workspaces

    Hi to all,
    Our costumer wants to know if there is some way to change, through Workspace WebServices or SQL sentence, the default "new resource avaible" behaviour on Workspaces (that behavior considered to show the "new resource avaible" GIF).
    Anyone knows how to do it? Or any one knows what are exactly the rules behind the action of passing a "new resource avaible" to "normal resource" showing off the GIF (ex. 3 days after publish the resource? Until the member open this resorce?)? ....
    Lot of thanks in advance and best regards!
    Sergio Arcos

    There is no setting to allow this in Keynote.
    The usual way to do this is either:
    Apple Menu > Recent Items > Documents
    or
    within Keynote;  File > Open Recent

Maybe you are looking for

  • Sending Duplicate emails using Mail and mBox for mac

    I have been sending duplicate emails inadvertantly recently.  It seems it's when I use mBox for mac (registered copy) in Mail to use my Hotmail with IMAP. I hadn't noticed it at first, but now I see everytime I send a mail I get 2 copies in my sent b

  • Dynamic Reference to Registered XSD

    I generate docs from SELECT like this, <span style="color:red;">(I do not store this type of doc in DB/XDB)</span>: <div style="color:blue;"> SELECT '<?xml version="1.0" encoding="utf-8"?>' || chr(10) || xmlelement ("ReinsuranceXfer", xmlattributes  

  • Default date using Personalization

    Hi All, Is it possible to default a date field with todays date using Personalization techniques , if yes please tell me how. I have to default 'Expenditure Item Date' in iProc checkout pages to current date. thanks Sudeep

  • Copy text from Word '03 into RH9

    I need to copy text from Word into RH in a way that does not bring in the Word codes.  I can obviously copy the text into notepad and then into RH, but I am wondering if there is a way to do it that would be similar to the "Paste Special / Unformatte

  • MSI RS480M2-IL audio problem

    Hi, i just set up my new pc with the MSI RS480M2-IL mobo and i am having some serious problems with the sound. i installed the ac97 codec from the msi driver page and here is what happens, the sound works only when i switch it to 4 channel mode or hi