Hi All,
Here I am facing error in process chain for delta pack.
Error:
     Last delta upload not yet completed. Cancel     I     
Please send me the solution asap.
Thanks

Hi,
This message means there may be a load triggered by the same infopackage that may be still running or may be still having yellow status. Go to the monitor screen from this IP itself and it will show the paricular request (it will be the latest one). See if that load is active and running. If its active try to find out if load is happening, if its happening you may let it progress. If its not active you need to force the status to red and delete from the target. Once this is done you can retrigger the load. If its a datamart load you may need to reset the data mart status before the triggering the load.
Refer
Last delta update is not yet completed
Last delta update not yet completed-PC Chain Error
Last Delta Not Yet Completed
This is the same issue as yours.
Thanks,
JituK

Similar Messages

  • Error in Process chain for CO-PC

    Dear ALL
                I am facing one problem.I have a process chain for CO-PC cost object controlling.In that after start process i have another process chain Manufacturing order.After this other processes are there.Upto 4th march i have the delta running fine.After that the manufacturing order PC is failing when i open the process chain i find its failing in DTP section.
    Now what i did is i run the DTP for manufacturing order actually it consist of ATTRIBUTES AND TEXTS.After finishing i find in manage that the records are transferred but 0 records added and when i find the log its saying
    @5C@     0PRODORDER : Data record 1 ('000001000000 ') : Duplicate data record     RSDMD     191     
    Thanks in Advance

    Hi,
    Check below these links for more business knowledge about CO-PC.
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/COPCIS/COPCIS.pdf
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/fb07ab90-0201-0010-c489-d527d39cc0c6.
    Regards,
    Praveena.

  • Process chains for deltas

    hello I have one scenario...Can anyone explain how we can implement it?
    I want to load data from R3 into Master Data Attribute in BW/BI..and it should include future delta loading also.....
    and I want to use Process Chains for this....how can we do it.?(I have knowledge of loading data from R3 To MD Attribute using Process Chain but without deltas)
    Thank you
    Regards
    NR

    Hi......
    Sorry for late reply.......
    If we take the second implementation of PC in your abbove post.....as we included fullload in PC....before delta init.....can it be possible that fullload happens all the time as its in process chain?
    yes..........since it is a part of the process chain every time when you will execute the chain.........full upload will also done..............you can do one thing you can copy the chain.......and remove that process......I mean open the chain in Planning view.....in the top where we write tcode......there write Copy...
    then the chain will be copied.........remove the start process and the full upload and init upload.........then create a new start process.........look you have to create a new start process.......because you cannot use the same start variant twice..........
    whats the use of attrib change run in PCs in general?
    Attribute change run is used to activate the master data.......ie to convert the master data from M version to A version..........because upon activation of master data SID will generate...........which is needed to link the master data to transaction data ie dimension table.........in extended star shcema............Also Once active, the data is available in your reports........
    Attribute change run also adjust aggregates........
    Another thing......This process is just required for Attributes and Hierarchies, not for Text data.
    Hope this helps..
    Regards,
    Debjani........
    Edited by: Debjani  Mukherjee on Nov 4, 2008 2:11 PM

  • Error in process chain for PCA full load

    Hello everyone,
    I'm trying to use a process chain in order to delete a previous full load of plan data in a cube prior to the new load (to avoid double records). The successor job in the process chain is loading a delta of actual data into the same cube (same info source).
    When executing the process chain (and the included info package (full load)), the setting "Automatic loading of similar/identical requests from info cube" in the info package is not working (I have ticked "full or init, data-/infosource are the same")...
    I have checked that the function itself works as I have executed the info package manually with success. So the problem is the chain somehow.
    In the chain I just execute the info package as usual... so to my understanding, it should work the same way as if I executed it manually. Or am I wrong? Is some additional setting required in the chain in order to make it work?
    Any ideas?
    Thanks,
    Fredrik

    Hi Fredrik,
    not all settings in infopackages work in chains in the same way they do while running the package manually. Mostly you can check that with pressing F1 on the setting. In your case, you need to add a process type for deleting the data to the chain. In your chain maintenance, look at process types and then in load processes .... There you will find the type you need.
    kind regards
    Siggi

  • Error in Process Chain for DTP- Job not finished

    Hi Experts,
    We have an issue with one of our process chains. When we execute the chain manually, there is no problem. BUt if we schedule the chain, issues arise. the last part of the chain is DTP. But the job doesnt finished even if the DTP step si already green. Locks occur for the DTP and the infoobject. When we look at the job log in SM37, it is still active. But this should not take a long time, since if we execute it manually it is ok.
    Pleas help experts

    Guys, I am also facing the same issue.
    When DTP is completed successfully, it has the job log blow :
    Job started
    Step 001 started (program RSPROCESS, variant &0000000391261, user ID BWREMOTE)
    Performing check and potential update for status control table
    Status 'Executable' (user BWREMOTE)
    Status 'Active' (user BWREMOTE)
    Program RSBATCH_EXECUTE_PROZESS successfully scheduled as job BIDTPR_335754_1 with ID 06532200
    Job finished
    When it fails or remain yelllow for long time and then turn into red.
    Job started
    Step 001 started (program RSPROCESS, variant &0000000391306, user ID BWREMOTE)
    Performing check and potential update for status control table
    Status 'Executable' (user BWREMOTE)
    Status 'Active' (user BWREMOTE)
    EXTRACTION OF DATAPACKAGE 000001
    EXTRACTION OF DATAPACKAGE 000002
    Job finished
    The question is, why the program  RSBATCH_EXECUTE_PROZESS is not scheduled.  Is it because there is no free resource? Or poor response from SAP ECC?
    Finally what does "EXTRACTION OF DATAPACKAGE 000001" mean? Its not scheduled?
    Regards
    MultiABAP
    Edited by: MultiABAP on Oct 6, 2010 10:32 AM

  • Process chain for full load.

    Hi,
    I have developed a Process chain for delta loads. Now my question is, can we use process chain to load full load data source for master data, if yeas then what are the steps.
    If we can use process chain for full load to master data then can we use delta and full load infopackages in the process chain.
    Please update.

    Hi Sata,
      You can Include both Full and Delta in the Process Chain. But make sure that you execute the Init InfoPackage manually before executing the delta InfoPackage in the Process Chain.
    For Full Load Process chain, add the infopackage
    >DTP for Full Load---->delete PSA data variant(after 2days) -
    >attribute change run
    Normally load the hierarchy first then the attribute and text.
    Assign points if it helped you.
    Regards,
    Senoy

  • BW: Not getting Dump For Program error in Process Chain

    I have one issue regarding Master data loading issue in BW(3.5).
    My business flow like we have received data from server A and Server A extract data from Server B and
    Server B which is extract data from source(R/3).
    Flow like this R/3-->Server B-->Server A(ETL) -
    > My Server.
    We have a mater data process chain and that chain we have have the source system Server A but in the process chain one process is there which is fethces data like global transport e.g UOM,factory calender etc through Custom program directly from Server B.
    Oneday what happened On that process the process chain Yellow since more than 16 hrs.Once nextday process chain trigger the process chain runs sucessfuly.
    But lastdays process chain paticular process stills remains yellow?
    We are not getting any dumps and even if from Server A there is no logs then anyone could please tell me what is reason and how to solve it.
    Note: it will be helpful for me  if any one know how to check dump for program errors in Process chain as narated issue.

    Guys, I am also facing the same issue.
    When DTP is completed successfully, it has the job log blow :
    Job started
    Step 001 started (program RSPROCESS, variant &0000000391261, user ID BWREMOTE)
    Performing check and potential update for status control table
    Status 'Executable' (user BWREMOTE)
    Status 'Active' (user BWREMOTE)
    Program RSBATCH_EXECUTE_PROZESS successfully scheduled as job BIDTPR_335754_1 with ID 06532200
    Job finished
    When it fails or remain yelllow for long time and then turn into red.
    Job started
    Step 001 started (program RSPROCESS, variant &0000000391306, user ID BWREMOTE)
    Performing check and potential update for status control table
    Status 'Executable' (user BWREMOTE)
    Status 'Active' (user BWREMOTE)
    EXTRACTION OF DATAPACKAGE 000001
    EXTRACTION OF DATAPACKAGE 000002
    Job finished
    The question is, why the program  RSBATCH_EXECUTE_PROZESS is not scheduled.  Is it because there is no free resource? Or poor response from SAP ECC?
    Finally what does "EXTRACTION OF DATAPACKAGE 000001" mean? Its not scheduled?
    Regards
    MultiABAP
    Edited by: MultiABAP on Oct 6, 2010 10:32 AM

  • Delta and Full process chain for same master data target.

    Hi  Friends,
    Can I do full update and delta update through process chain for same master data target and from same source ?
    Regards
    shekar reddy

    Hi Sriram,
    why you want to load full and delta for same master data object?
    you can achieve this but make sure that you select repair full option for full load IP.
    you have this option in scheduler in menu bar
    Regards,
    Venkatesh

  • Error in process chain (psa data)

    We have got an error in our PROCESS chain for master data.
    Info object Name : 0customer
    In that it was showing  there was error in our request. When I wanted to correct data in the request there it was showing no error records. All the records are good  and  also it is showing as error in request. I have deleted the request from infoobject and also from the PSA. And the last updated good request is also showing error as No data packets available for the request .
    0Customer is delta update ; Process chain is daily based.
    My doubt is whether the records in the deleted requests will be reloaded again from sap R/3 into PSA, as requests during Process chain or not.
    While monitoring the request details in Monitor u2013 Administrator Work bench, it shows the following:
    1.     Requests (messages) Everything Ok
    2.     Extraction (messages) Missing messages
    3.     Transfer (IDocs and TRFC) Missing messages
    4.     Processing (data Packet) No data
    5.     Process chains : Everything Ok.
    Even after deleting the requests my process chain is not getting updated.
    Kindly help me in solving the above problem
    Regards
    Padma

    Hi,
    Once deleted the request, try to manually trigger the load and see whether it completes. if it completes and pulls reocrd then you can push the chain process ahead with the program RSPC_PROCESS_FINISH
    Regds,
    Shashank

  • DTP error in Process chain

    Hi,
             Im creating Process chain for 0notification master object, here we have 8 infopackages with different selections but im not able to use 1 DTP for all the Infopackages. so plz solve my issue
    Thanks and Regards
       Satish Kumar K.S

    Hi Satish,
    Not clear about your requirement.
    As per your post, there are 8 infopackages with different selections.
    These infopackage will load data to PSA and from PSA to data target ( say DSO ) will be loaded by DTP.
    If the DTP is full load, it will load all data from PSA. If it is a delta DTP, last changed data will be loaded to target ( based on delta pointer ) . You can use single DTP to load data to target, from PSA. Number of Infopackages is not an issue.
    In the process chain, use all 8 Infopackage steps in series and then use DTP. It will work fine.
    Please let us know the error message you are getting.
    Thanks,
    Vinod.
    Edited by: Vinod Sivadas on Feb 23, 2012 8:21 AM

  • Data load Error using Process chain

    Hi,
    In NW2004s when I schedule delta loads for 2LIS_11_VAITM using process chains, when there is zero delta, the manage screens of the infocubes show green light with zero records correctly whereas the process chain log display shows red. The details of the process monitor show zero records. Is this right? I assume that even if there is zero delta, the log must show green and all the subsequent processes like activation of ODS, deleting of PSA, construction of indexes must be carried out. Please confirm. Is this a bug?
    Thanks.
    Param

    Hi Victor,
    Can you please advice how you solved issue as we are having similar issue where it works fine when loaded manually but throws communication error when process chain runs, following is error message..
    Communication error: call FM RSSDK_DATA_REMOTE_GET
    Thanks in advance for your help!!
    Sandeep

  • Error in Process chain while deleting index and create index

    While executing the process chain  for delete index  the process chain failed with the below error message as "The system has not finished loading request 445315 into data target ZECC_C01". While creating index also it failed with error message as "Lock NOT set for: Generate index, RSSM_PROCESS_INDEX terminated, because InfoCube/DSO object ZECC_C01 could not be locked".
    Please help me in solving this issue.
    Thanks & Regards,
    Bharathi

    Hi,
    Manage the data target - ZECC_C01 and check the request number 445315. Also check the subsequent data targets if further loading was erroneous. Check whether the request is green / Properly loaded or not.
    You can also use RSBKREQUEST table to check the request and its corresponding data target.
    This request is either red or yellow caused this failure.
    Hope this helps.
    Regards,

  • Error in Process chain( Urgent Please )

    error in Process chains:
    My Process Chain errors out in the step to activate the ODS after loading data inot it.
    The loading is correct and green. The Activation step errors out .
    Can u please explaing me the error messgae what it means & how to overcome the error & correct it ?
    I get message like this :
    Req. REQU_0WBTMPS7KTKP9BWTZ173XWX3Y, data package 000001 with status 2 in rsodsactreq missing in return
    Message no. RSMPC129
    Diagnosis
    Request REQU_0WBTMPS7KTKP9BWTZ173XWX3Y, data package 000001 with status &3 in table 'RSODSACTREQ' is passed to the return structure as correct.
    System response
    The return structure is corrected and the data package is marked as incorrect.
    Message was edited by:
            Chris Gokul

    Chris,
    Looks like a request has not got deleted properly from the table :
    Options that you could look at :
    1. Delete all the data from the ODS and load again ( if that is an option )
    2. There are some entries you need to delete from the RSODSACTREQ table- but for this the suggestion would be to raise an OSS note for SAP to look into the same - we had a similar issue and raised an OSS note for the same and then got some notes from sap.
    Also please mention your BI version and patch level.
    Arun

  • Problem in creating process chains for CO

    Hi Friends,
                     I have a CO cube "0OPA_C11" getting data from Three datasources,
    those are 0CO_OM_OPA_6(supports delta), 0CO_OM_OPA_1(full only), 0CO_OM_OPA_2(full only), i have already created process chain to this cube using these three datasources, the chain is like this,
    1. delete indexes
    2.0CO_OM_OPA_6(supports delta
    3.0CO_OM_OPA_1(full only),
    4.0CO_OM_OPA_1(request overlapping)
    5.0CO_OM_OPA_2(full only),
    6.0CO_OM_OPA_2(request overlapping)
    7.create indexes
            Is it right? here the chain is running, after completion of that, in manage of cube, it is showing only the request for 0CO_OM_OPA_2(full only), the request which were there earlier like Init request and new delta request for .0CO_OM_OPA_6, full request for 0CO_OM_OPA_1 are getting deleted, it is showing the request only for 0CO_OM_OPA_2,
      the way how i created the process chain is right or wrong? can anybody give me the solution?
    Thanx in Advance
    BalajiReddy

    Hi Nick,
              Thanx for your reply, everthing is ok what you've asked me to check, i think there is certain scenario to create the process chains for the data targets, which are getting data from multiple datasources, which support delta's as well as full.
              I want that scenario, can you tell me? or can anybody tell me?
    The right points are assigned to the right answers.
    Thanx in advance
    balajireddy

  • Error in Process Chains

    Hi APO Gurus
    I am getting following error in Process Chain :
    1 Tab Page ICkw6Rdc7s7x000002e0280 still contains 3 temporary aggregates when deleting
    2 Deletion of tab page ICkw6Rdc7s7x000002e0280 with 16566 registrations failed.
    3  Error in function module : < OM_TS_DELETE_REGISTER> Return Code : 3
    Can anyone guide  through this and my process chains for the macros are running very slow.Ihave splitted the jobs for macros but still it is running very slow.How to fasten my process chains.
    Amit

    Hi All,
    Thank you for your inputs on that....I changed the InfoPackage settings to App. Server and also background scheduling.
    Now I get another error in the Load Data process of the process chain. the errors are as follows:
    1.Error when opening the data file /usr/sap/interfaces/bw/sv5/GO/Plan/Current Pass/T (origin A)     @35@
    Diagnosis: File  /usr/sap/interfaces/bw/sv5/GO/Plan/Current Pass/T (origin A) could not be opened.
    2. @5C@     Errors in source system     @35@
    3. @5C@     Error 1 when loading external data     @35@
    The file name is actually TEST12.txt, but I am not sure whether the process chain is actually picking up the entire path or not.
    ALso I checked the batch monitor and found that the job is actually running under the user Z_R3USER and this user has the read and write privelges to application server
    Can anyone explain wht the problem could be?
    THank you

Maybe you are looking for

  • Contract net value for Header Statistics is not correct

    There is issue with value contract. The net value for Header Statistics is not showing correctly for some contracts. Especially, when we delete the PO line items or reverse all entries (GR and IR) for PO line item. Contract has one line with account

  • IPod classic recognized in 'my computer' but not in iTunes

    This has been going on for about a year and I've been able to fix it (but now I can't remember how) but now nothing will work. I connect it and this message pops up and asks 'Do you want to scan and fix iPod?' and I click 'continue without scanning'

  • How do I share iTunes library between different versions of iTunes

    I have an old motorola powerPC based iMac which is running Mac OS 9. The latest iTunes version for the old Mac is 9.2.  I also have various computers including an Intel Mac and other Windows PCs that run the latest iTunes version 10.6.3. When I tried

  • S/A Bridge Exception Handling

    Hi Experts, I'm using an integration process to call different synchronous interfaces from one syncronous interface. Now i've got the problem that the interfaces could raise an exception and I like to send this exception back to sender. I have design

  • Error in ADF-BC Database view instead of insert trigger

    I received the following errors when trying to insert. Any help or hint will be greatly appreciated. JBO-26041: Failed to post data to database during "Insert": SQL Statement "BEGIN INSERT INTO DEV_EQMT_HISTORY_BY_CODE(ID,D_E_ID,STATUS_KEY) VALUES (?