Hi all:
    while I am trying to do cost distribution , a message comes that
Cycle DOFF is not valid on 11/01/2008
Message no. GA509
Diagnosis
Cycle DOFF is valid as of the starting date 04/14/2009
System response
This cycle cannot be processed.
Could you please tell me how solve the issue ?
Thank you very much

Hi,
The error is because you have created Cycle DOFF with the starting date 04/14/2009 & you are trying to run the distribution cycle for November 2008.
For which period do you want to run the cycle?
1) If it is for April 2009, then enter the correct period & year when executing the cycle.
2) If it is for November 2008, then you will have to increase the validity of the cycle. I dont think you can change the start date of a cycle. You could however create a new cycle with validity period Nov 2008 to Dec 9999 by copying the cycle DOFF & only changing the start & end date. Then execute this new cycle.
Regards,
Sangeeta

Similar Messages

  • Error while doing AUC Settlement in KO88

    Hi
    I am getting the below error while doing KO88. I have maintained the Allocation structure for FXA and given the cost element group in the Source field & Given FXA in Receiver category and selected By cost element option aginast Receiver category FXA in Settlement Cost Element field. I am getting the below error while settling in KO88.
    Define a settlement cost element for receiver type FXA
    Message no. KD506
    Diagnosis
    In allocation structure A1 (controlling area BP01), you did not define which cost element should be used when settling costs/revenues of the sender. Nor did you define receiver type FXA.
    Procedure
    Assign a different allocation structure to the settlement sender (-> Master data -> Settlement rule -> Goto -> Settlement parameters), or maintain allocation structure A1.
    Please help me
    Thanks
    Kishore

    Please check your allocation structure , it looks that settlement cost element that you have assigned in the allocation strcuture is not having correct cost element category.
    regards
    Ranjan

  • Error while doing settlement from WBS to P&L Account

    Hello
    I am trying to do a settlement from WBS to P&L Account(Expense account). In this case, "Dummy" Prof Ctr is getting derived from 0KE5 (we have maintained a dummy prof ctr). We have set the validations to disallow any postings/settlements to dummy prof ctr. Hence I am getting an error while doing settlement.
    Now I am maintaning a Prof ctr in my WBS master data. I am unable to understand why system is deriving dummy prof ctr and not the one maintained on WBS master data. The settlements are working fine when I do them against Balance sheet accounts and proper prof ctr is getting derived, which is being maintained on WBS master data. I am getting trouble only while doing settlement to my P&lL i.e. expense accounts.
    can anyone throw some light on this?
    Thks
    Sarang

    Dear Sarang,
    You have maintained profit center in WBS master which is not updated at the time settlement to FI that what makes you worried. If you are making FI posting and give WBS as an additional account assignment then Profit center in WBS master will be updated. Here in settlement WBS is sender not the receiver so that profit center will not be updated. In settlement receiver (any) is debited and sender (WBS) is credited so this credit entry will be updated in profit center.
    To your second query that when you carry out settlement to balance sheet account right profit center is updated then please make sure, that balance sheet account is maintained in 3KEH with profit center or OKB9.
    Your P&L account (expense) receives dummy profit center because it is not able to find cost center which can fetch profit center from the master. So, if you can afford, maintain that cost elements (expense account) with profit center in OKB9.
    might help you..........................................................

  • Error while doing Goods receipt for process order. Error code: "BS027"

    I am getting error while doing GR for a day whereas previous day(s) GR is already done and also 2 days post that day are also done successfully.
    Error :  ""Goods receipt for prodn. order" is not allowed (ORD XX-CEMTSAL) " (XX = First two characters of plant code)
    Error code: BS027.
    Thanks to all in advance.

    Hello,
    This issue would occur when you want to post a confirmation for a production order. The error message is generated if you wanted to post a backflush for a component and if this component was assigned to a sales order stock. The sales order itself was assigned to a work breakdown structure element which should be debited with the actual costs. However, the business transaction 'Confirm' is not permitted for a work breakdown structure.
    Please look into SAP Note 62367 and 64370
    Hope the information is helpful
    regards

  • I am getting error while doing MFBF for semifinisg good

    Hi,
    i am getting error while doing MFBF for semifinisg good
    Existing standard cost estimate cannot be used
    Message no. RM175
    Diagnosis
    This error appears under the following circumstances:
    The existing standard cost estimate cannot be used for backflushing activities as the repetitive manufacturing profile was not maintained correctly when the standard cost estimate was carried out.
    The standard cost estimate must come from product costing. Other cost estimates (such as base object controlling) are not possible.
    Procedure
    The repetitive manufacturing profile assigned to the material at the time of the planned cost estimate must be a profile for repetitive manufacturing with product cost collector.
    Use product costing to create the standard cost estimate.

    I had already check REM profile repetitive mfg profile final backflush w. activities.
    this particular material is semifinish material attached in BOM of finish material.
    backflush of finish good is possible but now new requirement is to do production booking for the semifinish material.
    i had assign production version , done routing and maintain REM profile,
    created material cost with quantity structure ck11n then run the costing in ck40n.
    still getting the error what else is to done to able to book this thru MFBF.

  • Error while doing ABGL Asset Credit Memo

    Hi Friends,
    I am getting the below error while doing Asset Credit Memo in ABGL. Please help me in fix this issue.
    Balance for transaction type group 10 negative for the area 01
    Note:In Asset Explorer Fiscal year start Asset value is 98,425.45 and Change is 4768.19. So total Asset value as of now is 1,03,193.64.
    Now we are trying to do ABGL with 12,790.23 value (Transaction type is 105). System is giving the above highlighted error.
    If we give the amount 4768.19 in ABGL transaction, system is not giving any error. If we give more that that system is giving error.
    Why system is giving error even the asset has balance of 1,03,193.64? Please help me on this..
    Thanks
    Sunil

    Hi,
    If the asset has been capitalized during earlier years, use ABGF to post credit memo.  ABGL is meant for assets capitalized during the year.
    Best Regards,
    Madhu

  • Error while doing "Visulaize Plan"

    Hi,
    Before i did Visualize plan many times without any problem.Now I am getting error while doing so.
    I was able to run "Explain Plan" successfully.
    I am on HANA revision 60.
    I saved above error log and the log information is given below:
    I can identify invalid XML tag <TablesInvolved><![CDATA[raj/AN_VIZ]]></TablesInvolved> but how to fix this issue?
    I gone through various blogs related to Visulaization Plan but not found related to this issue.
    <Plan xmlns="http://www.sap.com/ndb/planviz" ID="ID_0" Type="Estimated">
    <SQL><![CDATA[SELECT KOKRS, BELNR, PERIO, SUM(MEGBTR)
    FROM "_SYS_BIC"."raj/AN_VIZ"
    GROUP BY KOKRS, BELNR, PERIO]]></SQL>
    <CompileTime>
      <Start Unit="us">1401281467643661</Start>
      <End Unit="us">1401281467658329</End>
    </CompileTime>
    <RootRelation ID="ID_0" TypeName="PROJECT" Status="Finished">
      <Name>Project</Name>
      <ExecutionType>Row Search</ExecutionType>
      <Summary><![CDATA[raj/AN_VIZ.KOKRS, raj/AN_VIZ.BELNR, raj/AN_VIZ.PERIO, SUM(raj/AN_VIZ.MEGBTR)]]></Summary>
      <Location>hanasp7:30003</Location>
      <EstimatedCost>
       <Exclusive Unit="us">2.12902e+06</Exclusive>
       <Inclusive Unit="us">2.64021e+06</Inclusive>
      </EstimatedCost>
      <EstimatedOutputCardinality>648284</EstimatedOutputCardinality>
      <Details><![CDATA[{"Projected Cols":"raj/AN_VIZ.KOKRS, raj/AN_VIZ.BELNR, raj/AN_VIZ.PERIO, SUM(raj/AN_VIZ.MEGBTR)","Project column0":"NString(4, 0)  __trex_field_NVarchar3__() ....... [3]:040:<5/7 (16B)>:
      /1/ void*  \"__rids__\" ....... [0]:NOP:<0/1 (8B)>:
      /2/ int32_t(10, 0) const := 0 ....... [1]:LOAD:<3/4 (4B)>:
      /3/ int32_t(10, 0) const := 0 ....... [2]:LOAD:<4/5 (4B)>:","Project column1":"NString(10, 0)  __trex_field_NVarchar3__() ....... [8]:040:<5/7 (16B)>:
      /1/ void*  \"__rids__\" ....... [5]:NOP:<0/1 (8B)>:
      /2/ int32_t(10, 0) const := 0 ....... [6]:LOAD:<3/4 (4B)>:
      /3/ int32_t(10, 0) const := 1 ....... [7]:LOAD:<4/5 (4B)>:","Project column2":"NString(3, 0)  __trex_field_NVarchar3__() ....... [13]:040:<5/7 (16B)>:
      /1/ void*  \"__rids__\" ....... [10]:NOP:<0/1 (8B)>:
      /2/ int32_t(10, 0) const := 0 ....... [11]:LOAD:<3/4 (4B)>:
      /3/ int32_t(10, 0) const := 2 ....... [12]:LOAD:<4/5 (4B)>:","Project column3":"Decimal(18, 3)  __typecast__() ....... [23]:076:<10/12 (16B)>:
      /1/ Fixed16(18, 3)  __trex_field_Fixed16__() ....... [19]:043:<6/8 (16B)>: 
         /1/ void*  \"__rids__\" ....... [15]:NOP:<0/1 (8B)>:
         /2/ int32_t(10, 0) const := 0 ....... [16]:LOAD:<3/4 (4B)>:
         /3/ int32_t(10, 0) const := 3 ....... [17]:LOAD:<4/5 (4B)>:
         /4/ int32_t(10, 0) const := 3 ....... [18]:LOAD:<5/6 (4B)>: 
      /2/ int32_t(10, 0) const := 18 ....... [21]:LOAD:<8/9 (4B)>:
      /3/ int32_t(10, 0) const := 3 ....... [22]:LOAD:<9/10 (4B)>:"}]]></Details>
      <Child ID="ID_8" >
      </Child>
    </RootRelation>
    <Relation ID="ID_8" TypeName="TREX_SEARCH" Status="Finished">
      <Name>Column Search</Name>
      <ExecutionType>Column Search</ExecutionType>
      <Summary><![CDATA[Aggregation on a single table]]></Summary>
      <Location>hanasp7:30003</Location>
      <EstimatedCost>
       <Exclusive Unit="us">511194</Exclusive>
       <Inclusive Unit="us">511194</Inclusive>
      </EstimatedCost>
      <EstimatedOutputCardinality>648284</EstimatedOutputCardinality>
      <TablesInvolved><![CDATA[raj/AN_VIZ]]></TablesInvolved>
      <LogicalPlan ID="ID_11" Type="Estimated">
       <RootRelation ID="ID_11" TypeName="PROJECT" Status="Finished">
        <Name>Project</Name>
        <EstimatedCost>
         <Exclusive Unit="us">0</Exclusive>
         <Inclusive Unit="us">0</Inclusive>
        </EstimatedCost>
        <EstimatedOutputCardinality>648284</EstimatedOutputCardinality>
        <Child ID="ID_12" >
        </Child>
       </RootRelation>
       <Relation ID="ID_12" TypeName="GROUP_BY" Status="Finished">
        <Name>Aggregation</Name>
        <Summary><![CDATA[raj/AN_VIZ.KOKRS, raj/AN_VIZ.BELNR, raj/AN_VIZ.PERIO\nSUM(raj/AN_VIZ.MEGBTR)]]></Summary>
        <EstimatedCost>
         <Exclusive Unit="us">0</Exclusive>
         <Inclusive Unit="us">0</Inclusive>
        </EstimatedCost>
        <EstimatedOutputCardinality>648284</EstimatedOutputCardinality>
        <Details><![CDATA[{"Grouping Cols":"raj/AN_VIZ.KOKRS, raj/AN_VIZ.BELNR, raj/AN_VIZ.PERIO","Aggregation Cols":"SUM(raj/AN_VIZ.MEGBTR)"}]]></Details>
        <Child ID="ID_13" >
        </Child>
       </Relation>
       <Relation ID="ID_13" TypeName="TABLE" Status="Finished">
        <Name>Column View</Name>
        <Schema><![CDATA[_SYS_BIC]]></Schema>
        <ObjectName><![CDATA[raj/AN_VIZ]]></ObjectName>
        <Location>hanasp7:30003</Location>
        <EstimatedCost>
         <Exclusive Unit="us">0</Exclusive>
         <Inclusive Unit="us">0</Inclusive>
        </EstimatedCost>
        <EstimatedOutputCardinality>682404</EstimatedOutputCardinality>
       </Relation>
      </LogicalPlan>
    </Relation>
    </Plan>
    Regards
    Raj

    Hi,
    To solve this you must update your studio. In lower studio versions (PlanViz) does not allow "unknown" XML tags sent by higher version servers. A fix for this issue was made so that PlanViz parser can simply skip unknown tags.
    Please go to version 74, if possible.
    Regards,
    Michael

  • Error while doing EHP4 upgrade in downtime phase

    HI .
    Iam facing the below error while doing the EHP4 upgrade , in downtime phase.
    Checks after phase MAIN_SWITCH/STARTSAP_TRANS were negative!
    Last error code set: RFC call to subst_get_uvers failed with key RFC_ERROR_COMMUNICATION (open): SAP_CMINIT3 : rc=20 >
    Connect to SAP gateway failed Connect_PM GWHOST=Hydhtc4526D, GWSERV=sapgw04, SYSNR=04  LOCATION CPIC (TCP/IP) on local host with Unicode ERROR partner '10.136.162.30:3304' not reached TIME Mon Jun 06 18:17:46 2011 RELEASE 720 COMPONENT NI (network interface) VERSION 40 RC -10 MODULE nixxi.cpp LINE 3286 DETAIL NiPConnect2: 10.136.162.30:3304 SYSTEM CALL connect ERRNO 10061 ERRNO TEXT WSAECONNREFUSED: Connection refused COUNTER System start failed
    Please help me in resolving this error.
    Sanketh.

    Hi,
    Upgrade tool is trying to start the system but system is not coming up. Try to start system manually and see if system comes up or not. If not then check logs in work directory for why system is not coming up.
    Thanks
    Sunny

  • Error while doing  GR for scheduling aggrement

    Dear Experts,
    We are facing error while doing GR for scheduling aggrement.
    we have done the following steps.
    1) Scheduling aggreement in ME31L
    2) Released in ME35L
    3) Mainatined Sch.Agmt Schdule in ME38 for todays and date 200 qty and other line is 800 qty.
    When we are trying to do GR in MIGO system is giving the following message.
    Document 5500000152 does not contain any selectable items
    can I know what I have missed in the above steps.
    Please guide me to resolve this.
    Regards,
    Prasad

    Hi,
    Please check Please check if Gr is already done against this document.  Also please check whether you have attached SA in the source list with line items.
    T-code:ME01
    Enter Mat.code & Plant.
    In the next screen pl.do the following:
    Valid from - commencement date of the SA
    Valid to - End date of the SA
    Vendor - Vendor on whom the SA is released
    POrg - Your purchase organisation
    PPL - Leave it blank(This is only for interplant)
    OUn - Ordering unit
    Agreement - SA number
    Item - 1
    I hope this will resolve your issue. Thanking you

  • Error  While doing ABT1N transaction

    Hi,
    I am facing the below error while doing ABT1N in Asset Accounting.Please help me in fixing this Issue.
    Error Message -No depreciation area for receiving the revenue
    Message no.AAPO149
    Diagnosis
    You tried to post a retirement on asset 1000 100007-0.You entered transaction type 300,in which the retirement with revenue indicator is not set
    You tried to transfer asset 1000 100007-0.According to transfer variant 0001,none of the areas on the asset uses a transaction type for retirement with revenue
    In  both of these cases, you are not allowed to enter revenue or make specifications for the determination of revenue.
    Proceedure
    Check the transfer variant  and check your entry
    please do the needful
    Thanks
    Supriya

    Hello,
    You will have a check box for the same.
    Double click on transaction type, you will see the check box for revenue.
    Otherwise, tomorrow I will get back to you once I am in front of the system.
    Regards,
    Ravi
    Edited by: Ravi Sankar Venna on May 5, 2009 7:53 PM

  • Error while doing F-90 Asset Acquisation

    Hi,
    I am getting the below error while doing F-90 Asset Acquisation scenario. Please help me to fix this issue.
    Tax code V1 country IN does not exist in procedure TAXINN
    Message no. FF713
    Diagnosis
    You entered a tax code which is not defined for the country of the company code to be posted to in the tax calculation procedure.
    System Response
    Procedure
    Check and, if necessary, correct the entry.
    Procedure for System Administration
    If it is not an input error, check and possibly change the system settings.
    To do this, choose Maintain entries (F5).
    Check whether the company code is assigned to the correct country and whether the correct tax calculation procedure has been entered for the company code country.
    Create a new tax code if necessary.
    Caution:
    Since it is possible that the tables in question are being updated at a different time on another computer, it can take a certain amount of time for the tax code to be on all local machines in client server architectures after saving the new code.
    Thanks
    KB

    Hi,
    you need to maintain Tax Code A0 & V0 in t.code OBCL t.code.
    and also ensure to check whether you have created tax code V1 or not in FTXP t.code. If not, create V1 tax code and assign GL on that in the right Transaction event keys in OB40.
    Try.... if not working let me know....
    Regards,
    MOhan.

  • Error while doing AIAB Settlement

    Hi I am facing the below error while doing AIAB during AUC settlement. Please do the needful.
    Data for determination of capitalization not managed in area 01
    Message no. AW507
    Diagnosis
    You have chosen a depreciation area, which does not carry the depreciation data from table COEPBR.
    Procedure
    Choose a different depreciation area.
    Thanks
    KC

    Hi,
    This message could be helpful:
    Error AW507
    Please check the field T082AVIEWB-AUTHORITY. If it is not on 2 this is the reason.
    In this case, you can change the value in T093-VIEW1 using the coding as per SAP note 29706 which you have already discovered. There will be no risk involved in changing this value.
    regards Bernhard

  • Error while doing BAM configuration in JDeveloper

    Hi,
    I tried to create a connection to my local BAM Server in JDev 10.1.3.2.0 and also in 10.1.3.3, but I always failed! Error messages:
    "Server is not set up correctly SOA1"
    I'm running on Windows 2003 and installed BAM according to the Installation Guide (version was Bam with Enterprise Link for windows 10.1.3.3.0).
    I did not get any error while doing the other setups and can access the different BAM tools via the Oracle BAM Start page, but I can't create a connection in JDev. I used the following parameters:
    Host Name: SOA1(system name)
    Port Number: 80
    User Name: Administrator
    Password: <windows domain pwd>
    Domain Name: DOMAINNAME
    Any help would be highly appreciated.
    Regards,
    Shaily

    hi Shaily
    It looks like suggesting a different forum is not needed, because you already tried that ...
    Error while doing BAM connection in jdeveloper
    Error while doing BAM connection in jdeveloper
    Error while doing BAM connection in jdeveloper
    I hope you get some answers.
    success
    Jan Vervecken

  • Error while doing BAM connection in jdeveloper

    Hi,
    I tried to create a connection to my local BAM Server in JDev 10.1.3.2.0 and also in 10.1.3.3, but I always failed! Error messages:
    "Server is not set up correctly SOA1"
    I'm running on Windows 2003 and installed BAM according to the Installation Guide (version was Bam with Enterprise Link for windows 10.1.3.3.0).
    I did not get any error while doing the other setups and can access the different BAM tools via the Oracle BAM Start page, but I can't create a connection in JDev. I used the following parameters:
    Host Name: SOA1(system name)
    Port Number: 80
    User Name: Administrator
    Password: <windows domain pwd>
    Domain Name: DOMAINNAME
    Any help would be highly appreciated.
    Regards,
    Shaily

    *** Duplicate Posting ***Edited by: damorgan on Oct 6, 2008 11:05 PM

  • Error while doing File to File Scenario

    All,
    I am trying a simple file to file scenario - where xi picks up the file from a location and maps the message and dumps it in another location.
    I am Getting the below error while doing the same .........
    Time Stamp Status Description
    2009-03-30 14:30:24 Success Channel Test_send_cc: Send binary file  "d:\input\input.xml". Size 203 with QoS EO
    2009-03-30 14:30:24 Success Application attempting to send an XI message asynchronously using connection AFW.
    2009-03-30 14:30:24 Success Trying to put the message into the send queue.
    2009-03-30 14:30:24 Success Message successfully put into the queue.
    2009-03-30 14:30:24 Success The application sent the message asynchronously using connection AFW. Returning to application.
    2009-03-30 14:30:24 Error Attempt to delete file "d:\input\input.xml" after processing failed. Retry
    2009-03-30 14:30:24 Success The message was successfully retrieved from the send queue.
    2009-03-30 14:30:24 Success The message status set to DLNG.
    *+2009-03-30 14:30:24 Error Transmitting the message to endpoint http://filip:8000/sap/xi/engine?type=entry using connection AFW failed, due to: com.sap.aii.af.ra.ms.api.RecoverableException: Received HTTP response code 401 : Unauthorized.*
    2009-03-30 14:30:24 Success The asynchronous message was successfully scheduled to be delivered at Mon Mar 30 14:35:24 GMT+05:30 2009.
    And i cant see the meesages using the SXMB_MONI trasaction
    please help me resolve ths issue
    Regards,
    Mahesh.
    Edited by: mahesh uma on May 3, 2008 2:12 PM

    Hi Uma,
    Go through this links::
    Hope these links are useful to you..
    Urgent: Message not transmitted from AFW to Integration server
    Error with huge file
    File to JDBC error
    Thanks,
    Satya Kumar..

Maybe you are looking for

  • How to differentiate a Goods receipt ?

    hello gurus how to differentiate the Goods receipts which are done only against an Inbound Deliveries  from that of direct POs. Is there any table to check the same ? Thanks in advance

  • ITunes library on external hard drive that nots always connected.....

    Can anyone help please? I have a laptop running Win XP and i have the latest version of itunes. I want to keep all my music on an external hard drive because i can't fit it on the laptop. This in itself isnt a problem - i have all the files on the ex

  • Safari crashes on pages made with iWeb

    Hi there, does someone have an idea on the route cause, please? As well, Safari crashes on homepages made with iWeb or pages using flash - even latest adobe update were sucessful installed. FYI - restart Safari or reinstall does not reflect any chang

  • Looking to change book size but maintain my page layouts

    Is there a smart way of changing the book size in aperture but be able to maintain the page layouts. I dont want to redo the entire book. Any tricks or suggestions would be of immense help. I have custom layouts for images.

  • Transfer history notifications from one system to another using ale/inotif

    Hi experts,i wan't to transfer 15000 completed,historical notifications from one sap system top another. I use ale configuration to do this. I have set rfc connections,message type,distribution model and i've generated partner profiles. My question i