Forecast values in RRP3

Hi,
Where forecast values in PPDS RRP3 transaction r stored? How do i fetch the forecast values?
Is there any function module or table?
Thanks
Shan

Live Cache data cannot be viewed in any static tables. that is the reason we use Function Modules to interrogate the live cache for this data.
If you have a backup of planning area process in place, it should be possible to look at the data in infocube backed up.

Similar Messages

  • Error while udating the forecast value in M.master through RMDATIND Program

    If anyone knows please respond urgently.
    Thanks in advance.
    Cheers
    Vallabhaneni
    Hi All
    Good Day
      In my custom Program I am using the three structures bgr00,bmm00,bmmh1 & bmmh3 and through rmdatind(Direct input method) program, i am trying to update the forecast value in material master data
    and i am getting error message as Specify a tracking limit and i have taken the tracking limit as 4 in my program.
    Actually there are 2 fields exists for tracking limit in structure bmmh1
    1.SIGGR and
    2.SIGG2
    I had given the  input as 4 for these 2 fields but I am getting the same error message Specify a tracking limit
    Can anyone please help me in this case.
    Thanks in advance.
    Cheers
    Vallabhaneni

    debug your program.
    Compare the field content of the value in the field you submitted with the content in field that is checked  when message M3 456 is issued.

  • Error while updating the forecast value in M.Master through RMDATIND

    Hi All
    Good Day
      In my custom Program I am using the three structures bgr00,bmm00,bmmh1 & bmmh3 and through rmdatind(Direct input method) program, i am trying to update the forecast value in material master data
    and i am getting error message as Specify a tracking limit and i have taken the tracking limit as 4 in my program.
    Actually there are 2 fields exists for tracking limit in structure bmmh1
    1.SIGGR and
    2.SIGG2
    I had given the  input as 4 for these 2 fields but I am getting the same error message Specify a tracking limit
    Can anyone please help me in this case.
    Thanks in advance.
    Cheers
    Vallabhaneni

    debug your program.
    Compare the field content of the value in the field you submitted with the content in field that is checked  when message M3 456 is issued.

  • How to find out user info for a forecasted value

    Hi Experts,
    Suppose, a user plans on a planning application and consequently creates some forecast values. How do i find out which user did the planning? Is there any way to know this? Please let me know of this if anybody knows.
    Regards
    Swaroop

    Hi, I'm using BPS so can't say forIP. But if you really want to see who posted which data, the planning application has to be set up that way in order to capture the user, time, date details, as indicated by the previous post. This will ptentially of course create very many more records in some cases, where data is amended.
    But your post also requested info about who ran which planning functionality, and when. You can get this sort of information in BPS from the transactions BPS_STAT0 and BPS_STAT1. You may want to narrow the amount of analysis using the username/ date /time filters.
    Stephen

  • In SOP- transfer forecasted values from material master to info structure?

    Hi All,
    I wanted to test out a few scenarios. Do you know the answers  / can you help simulate and check the below?
    1.     If I run the forecast using different models for different materials using the total forecast run (MP38), the forecast values will get updated in the material master. Can I get these values transferred directly into the SOP (standard or flexible), without re-running the forecast in SOP? What I am looking at is a possible scenario where individual materials have different forecast model, so do not want to run forecast from SOP using one model for all.
    2.       Can you have the capability of selecting diff model (say based on material master data) in SOP for diff materials? When I ran SOP, the model I specify there for forecasting is applied for all materials
    3.       If I upload historical values/forecasted values in the material master, can I directly transfer them to SOP without any change to the value?
    Appreaciate your inputs.

    Hi All,
    I wanted to test out a few scenarios. Do you know the answers  / can you help simulate and check the below?
    1.     If I run the forecast using different models for different materials using the total forecast run (MP38), the forecast values will get updated in the material master. Can I get these values transferred directly into the SOP (standard or flexible), without re-running the forecast in SOP? What I am looking at is a possible scenario where individual materials have different forecast model, so do not want to run forecast from SOP using one model for all.
    2.       Can you have the capability of selecting diff model (say based on material master data) in SOP for diff materials? When I ran SOP, the model I specify there for forecasting is applied for all materials
    3.       If I upload historical values/forecasted values in the material master, can I directly transfer them to SOP without any change to the value?
    Appreciate your inputs.

  • Problem while updating the forecast value in m.master by direct input menth

    Hi All
      Good Day
      I am updating the forecast value in material master by direct input method.
    my program is working fine when I am running it online.
    but when i am runnig in back ground I am getting one error which is mentioned below
                                                                                    Job ZM_OPTIMIZA_UPLOAD: Data does not match the job definition; job terminated    BD    078     E    
    Please anyone can help ne in above case.
    Thanks in advance.
    Cheers
    Vallabhaneni

    Hi Hakim
    How are you
    Thanks for your valuable suggestion.
    I am executing my program in background with bmv0 transaction with variant, in development I can run this job in background with out any logical errors but in QA I am getting errors.
    Can you please help me in the above case.
    In Bmv0 transaction first I defined the job and in  program rmdatind (execute) screen first I mentioned the Max. no of logical errors as 500 and Transactions per commit unit as 500 and I run the program in background in bmv0 transaction and I am getting the message background job terminated immediately
    Because of this again I changed the Max. no of logical errors 500 to 99999 and transaction per commit unit 500 to 999999 and then i scheduled my program in background.
    Alomost it ran for 27 hours and then it has given the message background job terminated.
    Job log entries are as follows.
    22.12.2008  11:19:46  A system error has occurred while locking                                 
    22.12.2008  11:19:46  Transaction 0000040840; material number SUJ82J8400; error gravity E       
    22.12.2008  11:19:46  Transaction 0000040840: Taxes for sales org.  cannot be transferred       
    22.12.2008  11:19:46  A system error has occurred while locking                                 
    22.12.2008  11:19:46  Transaction 0000040841; material number SUJ84G3001; error gravity E       
    22.12.2008  11:19:46  Transaction 0000040841: Taxes for sales org.  cannot be transferred       
    22.12.2008  11:19:46  A system error has occurred while locking                                 
    22.12.2008  11:19:46  Transaction 0000040842; material number SUJ84G3002; error gravity E       
    22.12.2008  11:19:46  Transaction 0000040842: Taxes for sales org.  cannot be transferred       
    22.12.2008  11:19:46  A system error has occurred while locking                                 
    22.12.2008  11:19:46  Transaction 0000040843; material number SUJ86G0100; error gravity E       
    22.12.2008  11:19:46  Transaction 0000040843: Taxes for sales org.  cannot be transferred       
    22.12.2008  11:19:46  A system error has occurred while locking                                 
    22.12.2008  11:19:46  Transaction 0000040844; material number SUJ86G0300; error gravity E       
    22.12.2008  11:19:46  Transaction 0000040844: Taxes for sales org.  cannot be transferred       
    22.12.2008  11:19:46  A system error has occurred while locking                                 
    22.12.2008  11:19:46  Transaction 0000040845; material number SUJ86G0900; error gravity E       
    22.12.2008  11:19:46  Transaction 0000040845: Taxes for sales org.  cannot be transferred       
    22.12.2008  11:19:46  A system error has occurred while locking                                 
    22.12.2008  11:19:46  Transaction 0000040846; material number SUJ86G9600; error gravity E       
    22.12.2008  11:19:46  Transaction 0000040846: Taxes for sales org.  cannot be transferred       
    22.12.2008  11:19:46  A system error has occurred while locking                                 
    22.12.2008  11:19:46  Transaction 0000040847; material number SUJ86G9601; error gravity E       
    22.12.2008  11:19:46  Transaction 0000040847: Taxes for sales org.  cannot be transferred       
    22.12.2008  11:19:46  A system error has occurred while locking                                 
    22.12.2008  11:19:46  Transaction 0000040848; material number SUJ86J0000; error gravity E       
    22.12.2008  11:19:46  Transaction 0000040848: Taxes for sales org.  cannot be transferred       
    22.12.2008  11:19:46  A system error has occurred while locking                                 
    22.12.2008  11:20:54  Transaction 0000040848 completed Mat. no.  No. of log. errors 0000040848  
    22.12.2008  11:21:30  ABAP/4 processor: TSV_TNEW_PAGE_ALLOC_FAILED                              
    22.12.2008  11:21:30  Job cancelled      
    I know it has taken long time to process the job  because of I changed the transactions per commit unit (500 to 999999) it kills the system
    But I am supposed to provide some number < 999999 in transactions per commit unit
    actually I haven't tried like I said above < 999999 because i don't have any hopes.
    Please look at this problem and help me in this case.
    Thanks in advance.
    Vallabhaneni

  • ABAP report to display material wise forecasted value in sap APO

    Hi All,
    I want to create a ABAP report in which i want to display the forecasted values of the material from the planning book.
    Could anyone please help me with the information with any database table or the function module or any other source to get the forecasted value against the key figure ZCONSTR form the planning book data.
    It's very urgent.....Awaiting your reply.
    Edited by: Komal Bhutada on Jul 22, 2011 5:50 PM

    Hi,
    You can more details from transaction BAPI->Supply Chain Management ->Advanced Planning and Optimization ->PlanningBookAPS ->GetDetail2 .Here you can find input parameter and in detail documentation.
    Regards,
    Sunitha

  • Which table can we see consumption and forecast values in forecast based planning

    Dear SAP Gurus,
    I am working on implementing forecast based planning for Spare parts for my client. They have one Main Plant which do purchase of Spare Parts and through Stock transfers moved to 60+ Plants from where Spares are being sold.
    Now I am carrying out SAP trial runs for a set of 160+ materials with various models and want to compare with their existing methodology of requirement calculation.
    I want to compile Consumption and Forecast data month wise for these trial materials (160+ materials in 60 Plants) . One way I thought is to go individual Material Master and looks for values in Forecast view. However it is tedious and time consuming.
    The table name shows RMCP2 and RM03M for forecast and Cons values, but I could not find the table.
    Hence I want to know which table if I can view I can get the consumption and forecast data calculated for quick copying and compilation. 
    Thanks and Regards,
    R.Velmurugan.

    Dear Mariano,
    Thanks for your valuable inputs.
    Like I could able to get the consumption values for materials using table MVER and fields GSV01,GSV02 etc.,
    What field I need refer in table PROP for getting forecast values.
    As such I could not see any column where in data are similar to Forecast view.
    Thanks and Regards,
    R.Velmurugan.

  • Forecast Values

    Dear Friends
    For forecast based planning what is the difference of entering the forecast values in MM02 and in MD61, also i want to know whether  the system will automatically get the forecast values, insteaded of entering manually.
    If i want to change the forecast values whare can i update it.
    IS it possible can we export the annual sales forecast excel sheet to material master forecast values.
    thanks & regards
    Shivani

    Hi Shivani,
    It is not possible to explore Multiple BOM's during MRP. Instead you create different alternative boms with different production versions. When you run MRP system creates a planned order, where you can change the production version and view the status of capacity and material ATP. Just check and come back...
    Ramagiri

  • Calculate Forecast Value in SSRS

    HI All:
    I have a question on how to calculate the Forecast in SSRS.
    Values are being calculated in excel as below- 
    =FORECAST(A154,$K$141:$K$147,$A$141:$A$147)
    How can a forecast value be generated in SSRS report ?
    Apprecaite all your help.
    Thanks!
    Shalini

    Hi steve,
    If I understand correctly, you want to calculate the response time between visitor and operator. And if there are more than one visitors between two operators, we should calculate the first visitor. After testing the issue in my local environment, please
    refer to the following steps:
    In the design mode, click the menu” Report”>>”Report Properties”>>”Code” tab. Then place the code below in the section:
    Dim shared AA As String 
    Dim shared CC As Date
    Dim shared DD As Date
    Public Shared Function getPrevious(Person as String,Item As Date) As Integer
      If (Person="operator") Then
         DD=Item
      End If  
      If (Person=AA) OR (Person="operator")  Then
      Else
        AA=Person
        CC=Item
      End If     
      If (Person="operator") Then
           AA="nothing"
           return DateDiff("s",CC,DD)
      End If
     End Function
    Right-click the times (response time) column to insert a column right of it.
    Modify the expression of the new cell as follows:
    =code.getPrevious(Fields!Person.Value,Fields!times.Value)
    The following screenshot is for your reference:
    If you have any other questions, please feel free to ask.
    Thanks,
    Katherine Xiong
    Katherine Xiong
    TechNet Community Support

  • Creation of Purchase Requisitions from Forecasting Values

    Dear Friends
    I coud do forcasting and generated the forecasting values and the values are also visible in the MD04 Stocks/Requirements List. Please guide me to create the Purchase Requisitions from the forecasting values.
    Thanks and Regards
    Suresh

    Depending on the MRP type in the material master you'll need to run either MRP or MPS.  I'd start with single item single level which will just plan the one material.  The Tcode is MD03 for MRP items and MD42 for MPS items.  It sounds like you're new to this so you should look around at the settings in the MRP1 - 4 views of the material master to understand the different settings that control the output of MRP (e.g. MRP Type, Lot Size Data, etc).  Lastly, check the MRP Control parameters that are entered when you run the MRP transaction.  Specific to your question, running it with Create Purchase Req 1 or 2 will create Purchase Reqs directly.
    Hope this helps.

  • Project system tables for getting baseline and forecast values

    Hi all,
    I am new to Project systems and currently i am having the PS report.
    I need to pick the following values based on project definition (proj-pspid):
    --> historical baseline values like:
    1) versions
    2) created by
    3) created on
    --> historical forecast values like:
    1) versions
    2) created by
    3) created on
    Can you please let me know the tables and fileds for fetching the above values.
    Regards,
    raviraj.

    Hi,
    IMAK Appropriation requests - general data
    IMAV Appropriation request variant
    IMPR Investment Program Positions
    IMPU Texts for cap. inv. program positions
    IMTP Investment programs
    IMZO Assignment Table- CO Object - Capital Investment Prog.Pos.
    PMCO Cost structure of maintenance order
    PRHI Work Breakdown Structure, Edges (Hierarchy Pointer)
    PROJ Project definition
    PRPS WBS (Work Breakdown Structure) Element Master Data
    Check with tables

  • MM - Consumption Forecast Value

    Hi everyone,
    I have added in 'MM02->Additional Data->Consumption' some values in the Corrected Value column. What I need to know is the table in which these values are stored.
    Moreover, I would also like to know in which table are the forecasted consumption values stored.
    Thanks in advance and best regards.
    Ben.

    Please check the table MVER for consumption values in material master. PROW for forecasted values.

  • Setting Negative Forecast Values to Zero

    In 7.0 we used a option - Setting Negative Forecast Values to Zero.
    But after upgrade to 7.3 this option is missing and I can find any information about this.
    Can we open the option in 7.3?
    Anatoly

    Hi,
    thanks for your reply.
    mls qos
    interface GigabitEthernet3/34
    description *** DATA VLAN 35 - VOICE VLAN 34 ***
    switchport
    switchport trunk native vlan 36
    switchport trunk allowed vlan 34,36
    switchport mode trunk
    mls qos trust dscp
    no cdp enable
    spanning-tree portfast trunk
    If i don't include the global 'mls qos' command then the voice packets keep the dscp 46 value.  If I add the mls qos command this causes the switch to set the dscp values to zero.
    Thanks again 
    ps.  there are some other mls commands on the switch... i don't know if these could interfere but they were already on there so i'm reluctant to remove them..

  • What is "WITHDRAWAL:" and "ALLOCATED" in Forecast tab in RRP3

    Hello Gurus,
    The quantity and date in withdrawal and allocated in forecast tab of RRP3 does not match with MB51 of ECC,
    also pls clarify exactly how it is determined.
    Regards.

    Hi there!  Withdrawal and allocated quantities distinguish between two concepts - forecast consumption and forecast reduction.  The withdrawal quantity represents the amount of forecast which has been "reduced" and the allocated quantity represents the amount of forecast which has been "consumed".  Consumption becomes reduction when a sales order / delivery is PGI'd.  Or, when an SO is canceled, the consumption is simply reversed and no reduction occurs. 
    Forecast reduction prevents "over-planning" for a given time period, meaning that the system "remembers" how much was shipped out to the customer so that the forecast shows in the system as "fulfilled".
    For example, consider a day which has a forecast of 10.  There are open sales orders of 5, and another 3 were ordered and shipped today.  Assume also that there is no forward/backward consumption.  SO's consume forecast for the same day only.  In this case, the allocated quantity would be 5 - for the currently open orders.  The withdrawal quantity would be 3.  And the remaining unconsumed forecast for the day would be 2.
    Not sure why there may be inconsistencies with ECC, however.  If you give more specifics on the nature of the discrepancy, I will try to respond with some additional input.

Maybe you are looking for