Global Standard for TECOing Process Orders

Hi All,
Is there any standard rule for how long it should take for a process order to be TECO'ed?
Currently our PO's get TECO'ed anywhere between 2-8 days after confirmation. But we do have them all TECO'ed prior to month end. I would prefer to set a general rule (based on global and benchmarking standards) on how many days it should take us to TECO them.
Appreciate your help and inputs.
Thanks,
Deeksha

Dear Deeksha,
Once the process order has been confirmed with final confirmation or say the complete confirmation,goods movements(Gi&Gr)
activities are completed,then the TECO status can be set on the same day of final confirmation and GR or else on the next day.
If my understanding is correct then SAP suggests to set the TECO status once the shop floor activities are completed and no
where I could see the no of days for performing this activity.
If required this can be individually set at process order level in COR2 or else as month ending activity by setting TECO for a list
of process orders using T.Code COHVPI.
Check and revert back.
Regards
Mangalraj.S

Similar Messages

  • Standard costing in Process order for external operation

    Hi SAP - PP gurus,
    Need your expert suggestion on the current scenario. We are having a sequence of operations in a process order. One specific operation is used to trigger subcontracting activity for completion of some services.
    while calculating the total planned & actual costs & variance costs for the process order as a whole , we are not getting the desired results.
    The  planned cost is not getting calculated or variance is not populated correctly. what might be the problem or is there any alternate solution to approaching this scenario.

    I do not have an 'expert' response for you - but I can share my experience and maybe both of us will learn the 'truth' before too long.
    In the external processing - indicator in the control key for a phase/operation in a recipe - when it is set, the system requires that either a Purchasing Information Record or an Outline Agreement # and Outline Agreement line item # be entered. If I enter a PIR, the data from the PIR is loaded into the external op fully. This results in a proper cost roll-up and proper processing.
    If I use an Outline Agreement + Item # - the system expects me to copy all this detailed information into the remaining General Data fields (that were populated automatically when I used the PIR). I don't have to enter anything except the OA + Item numbers. But if I do not enter a price - then I, like you, get less than acceptable pricing because this operation is NOT priced (I do get a warning - this leads me to believe that SAP will not be populating these fields - the warning is to remind ME to do it --- I want the system to do it since I am specifying the OA + item numbers).
    I have searched help and now have posted an OSS note for the answer to this: The PIR does what I want (it has to be created prior to application of course), but because External processing is merely a service and can't be specified by Material # and it only works per Material Group # - then I only have the chance to enter one price per Material Group - and that is insufficient in my situation (I have about 50 materials per each group and each item can have a different price). So I have to use OAs - and not having them able to trigger auto copying into the external op phase - this causes a lot of extra work and risk of data inaccuracy (mis-keying the price, etc.). There does not seem to be a fix - so I think the manual application in the ext op will be your recourse.
    Let me know if you have learned more.

  • TECO Process Order

    Hi,
    I am not able to TECO the process Order if the Contol recipees were generated (CRCR). this CRCR status automatically genreates when the Process Orders are released. threre were no confirmations, GIs, or any postings done. How can i TECO the Process Orders with this status.
    Thanks,
    Nagesh.

    Dear,
    It is because default SAP status settings does not allow TECO when CRCR is active. I think it is not advisable to change the std one though BS22 - I00045 for TECO here permitted for CRCR.
    Standard practice is that you need to make system status CRFI ,
    Transaction CO57, to trigger manually a process message with message Category PI_CRST for the process order and Control reciepe combination.Then use Transaction CO54 to send the Message to the process order.
    Regards,
    R.Brahmankar

  • Target Vs Acual Cost Comparison for multiple process orders

    Dear SAPians,
    I want to take a report for target vs actual cost for all process orders and product cost collectors created in a particular period. I have checked the standard report KKBC_ORD that serve my purpose but for a single order. I want the same report for multiple process orders and product cost collectors.
    Is there any standard report or should I create a report painter report. I have tried to create a report painter report based on library 7KO, but target cost was not showing for selected order.
    Kindly suggest.
    Shirazi

    Target Costs are available in library 601 for internal orders (and can be used for process/production orders).
    Regards,
    Adrian

  • Report for open process orders

    Dear SAP experts,
    As the period of the process order from open to close is not short, will take 1 or 2 months in our business case, so we want to find a report which can get the information just like the output of KSPP(for planned orders) .
    I tried to analysis the logic of program KSPP, and it seems the function modules based on the planned orders only.
    Is there any way to get the similar report for open process orders?
    Many Thanks,
    Lisa Yao

    Is there any clues?

  • BOM Explosion for Multiple Process Orders

    Hi,
    I hope someone can assist me with the following: Is there a report I can run or transaction I can do to have BOM explosion for multiple Process Orders? I would like to input process orders for a week and see the BOM details per PO.
    Thanks

    Dear Sukendar,
    1.For this requirement you have to go for a Z report and you can give the Functional Spec's to prepare
    this report to your ABAP consultant.Prepare the input format,logic of the program and the output format.
    In the logic part you can make use of this Functional Modules's CSAP_MAT_BOM_READ or 
    CSEP_MAT_BOM_READ  or CS_BOM_EXPLOSION   or CS_BOM_EXPL_MAT_V2 .
    2.Using CEWB helps you to identify all the material that's having the BOM,but here the report does not
    shows you the level by level by BOM for a FERT.
    Check and revert back.
    Regards
    Mangalraj.S

  • Process instructions for particular process order.

    Hi SAP gurus,
    How can I find table level data of process instructions (Like READ 1 , READ2 , INSTR ) maintain  for particular process order.
    If should not with respect to recipe but it should be respect to process order.
    Can any Plz buddy explain me the chain of  tables starting  from order number?
    Best Regards,
    Parag Save

    Hi...
    i could not find the table for the relationship u r looking for... but i would suggest the following...
    Go to SE16.. press F4 in the table list...go to the application help... their you will find tables for each module... even for PP you will find table specific to process industry... this you can search ur own what can be relevant for ur requirement... finally u can use SAP query to join some table to the get the information u want....
    Try this...hopw it should work for u...
    Neeraj

  • Inspection type 04 should not generate Insp.lot for specific Process orders

    Hi Guyes,
    I Want to skip the Inspection lots generation for specific process orders of a particular material during Goods Reciept and stock should be directly posting in to Un-restricted stock.
    In the material master assigned with Inspection type 04.
    Please advise me the possible options to map this scenario.
    regads,
    Rao

    In  QDR1
    stage 10-click on insp stage
    stage 10
    no. of insp : 5
    new insp stage : 20
    rej : 1
    new insp stage : 10
    stage 20 - tick on skip
    stage 20
    no. of skip : say "5"
    new insp stage : 10
    rej : 1
    new insp stage : 10
    Now use this DMR in Header of inspection plan of material of process order.
    what this will do is after 5 inspections it will skip the next 5 inspection lots.
    Make sure :
    You can maintain setting for "maximum skip duration in plant level.
    In QM view click on Skip & auto UD
    Create variant in QA16 & run through QA17
    Here in QA17 maintain the duration after which you want to take UD
    Also make sure that in selected set maintain stock posting proposal for unrestricted.

  • Tcode to view fico related postings for one process order

    Hi Experts,
    Is there any trasaction code which can be used to view all related posting into FICO for one process order
    Thanks in advance.
    Narayanan
    Moderator: Please, search SDN

    Hi,
    Check In KoB1 T.code, Give Order Number and Date Range.
    Thanks
    Goutam

  • Single time receiving material from stores for diff process order.

    Dear all,
    I am creating 5 different process order for 5 different FG material.
    But for all 5 fg material one bill of material is common to all.
    While receiving material from stores that particular bom i need to get single time only from stores for all five process order.
    Kindly please let me know how to process.
    Regards
    Rajasekaran

    Hi Raja,
    As replied to your earlier threads, unique reseration is created against each process order. Accordingly issue also takes place againt unique reservation/process order. Use MB1A/MIGO for individual issue or pick list COIK where issue an be done by stores for all process orders in on go.
    In SAP Mill Products once DIMP is activated there is combination order functionallity available where if operations/ BOM of 5 orders are same then combination order (New order) can be created by combining the qty of 5 individual orders. Here Goods issue is done against the new combined order which is single order for total 5 orders qty. This functionality i used in Discrete Maufacturing.
    Have a look.
    Combined Production Order Processing (DIMP)
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/7c/ea814440ce11d385c70000e8200b4c/content.htm
    Thanks & Regards,
    Ramagiri

  • The Prerequisites for releasing process order

    Hi all,
    What are the Prerequisites for releasing process order?
    Can we issue the material against process order, if it is on CRTD status?

    Hi,
    Prerequiste for REL of Process Order -
    Process order should have CRTD status.
    Other with IMG setting, you can have order status directly REL once it is created also. See Prod Sch Profile setting.
    You cannot do goods posting (GI and GR) unless order is REL status. Not possible with CRTD status.
    Srini

  • Tcode for FICO related postings for one process order

    Hi Experts,
    Is there any Tcocde which can be used to view all related posting into FICO for one process order
    Thanks in advance
    Narayanan
    cross-post

    Hi Venkat,
    Don't know any tcode, but from se16n BSEG table u can extract document data by filling AUFNR field with process order number.
    Hope this helps
    Best regards
    Vimal

  • Goods Receipt for Material which has no Standard Price in Process Order

    Hello everyone, is there a way by which we can prevent GR for process order which contains material that does not have standard price? And if ever we received material using process order how can we correct the process order right after we correct the standard price.

    Hi,
    i just don't know why you raised new thread as already ur previous thread is not closed
    Now just let us know whether system is throwing any error
    or what exactly happing in cofirmation screen
    Go to OPK4, here
    under goods movement there is option all components  just tick it
    then in second tab Gen individual entry tick Goods movement & termination for incorrect goods movement
    Coming to GR
    what is storage location ur giving
    just check in MMSC, whether this storage location is activated for the header material ( GR )
    Added
    Plz Go through all possible options
    [Auto GR is not happening.;
    Regards
    kumar
    Edited by: kumar kumar on Nov 10, 2009 2:25 PM

  • Global Standard for Measures

    Now that I know much more about data and data bases, I want to make very clear the requested standard, being the foundation of what I call the 'Base1' system.
    The request is for a global standard of all measurements in all professions to be recorded for sharing as a single entity, called a 'Point' having attributes ID, URL, alt, lat, lon, time, measure, spatial radius, time radius, measure radius.
    The URL being the contact for the originator of the measures, who is naturally charged with maintaining and making available MetaData on the techniques, and for searches, etc, on a per-list basis, each list having all such attributes in common and being the measure of one and only one magnitude (not any kind of difference, sum, or ratio). The list ID being attributed to each Point object from that list.
    The time and time radius being in seconds since 1970 and seconds, respectively.
    The altitude and spatial radius being in latitude seconds (to avoid feet/meters conventions confusion).
    The measure radius being measured according to the same unit as the unit of measure (which unit of measure is recorded with the URL MetaData for the list).
    The 'radius' refering to the +/- accuracy range for the point.
    Any data which is sensitive being shared on a scale of 1.

    Dear Deeksha,
    Once the process order has been confirmed with final confirmation or say the complete confirmation,goods movements(Gi&Gr)
    activities are completed,then the TECO status can be set on the same day of final confirmation and GR or else on the next day.
    If my understanding is correct then SAP suggests to set the TECO status once the shop floor activities are completed and no
    where I could see the no of days for performing this activity.
    If required this can be individually set at process order level in COR2 or else as month ending activity by setting TECO for a list
    of process orders using T.Code COHVPI.
    Check and revert back.
    Regards
    Mangalraj.S

  • User Exit or BADI for Blocking process orders from R/3 to APO?

    Dear Experts,
    I am looking for a user exit or badi to block the process orders from R/3 to APO. As per standard it is not transferring orders which are clsd(closed status). Means that it is not updating live cache but its reading from R3.
    We are facing some problems in cif queues which are not correctly maintained in R3 side. We dont want to touch those orders bcoz its very old data which is not required for planning.
    There will be huge data which needs to be deleted while transferring through cif.
    Please give any user exit (outbound intial transfer) from R/3.
    Or any sugg. I apprecite your inputs...
    Thanks
    Cris

    Hi Cris,
    You can use user exit APOCF004 - Inbound Processing: Production Order/Planned Order in APO to prevent orders coming to APO by deleting orders which are not intended to goto APO from internal tables IT_ORD and IT_OUT.
    Hope this helps.
    Best Regards,
    Ramesh M