How can consider Planned delivery time for subcontracting dependent of qty

Dear guru ,
How can mrp schedule delivery date of a subcontracting purchase requisition in order to consider planned delivery time and quantity to purchase.
Thanks

dear guru ,
I want to create a self-defined info structure similar to S013.
I want to add field purchasing group from EKKO-EKGRP. The other fields are similar to S013 with the same rules.
What do you suggest i can do consider note 397864 :
You are not permitted :a) to use info structure S013 as a template for self-defined info structures (This is prevented as of Release 4.5 due to a termination message).b) to create any update rules for S013 with a self-defined update group.c) to include the enhanced update rules that are used for S013 during the definition of key figure updating into the definition of the update of a self-defined info structure (compute...).
Thanks

Similar Messages

  • Regarding planned delivery time for Subcontracting process

    1.Factory calender is maintained  and assigned to the plant,SUNDAY is
    not working day for Client,so the system is not planning any internal
    activities for SUNDAY,up to here it is fine.
    2.One semi finished material is produced by vendor.i.e.Sub contracting
    process, it takes 2 days to complete.For vendor SUNDAY is not a
    working day.
    3.Planned delivery time is maintained as 2 days ,so that if PO is
    release on MONDAY ,the delivery date on WEDNESDAY.
    4.If  requirement is on MONDAY ,In MRP Run System is generating the
    release date on SATURDAY and delivery date on MONDAY,here system is
    taking the calender days not the factory calender days,Client is
    asking for correct delivery date.
    5.Is there any way to tell the system that SUNDAY is not working day
    for vendor,so that system will generate the release date on FRIDAY
    and delivery date on MONDAY.
    Please give your valuable inputs.

    Hi
    the following link might help you in setting the planned delivery time in your defined calendar, rather than the general calendar days.
    SAP ERP Manufacturing - Production Planning (SAP PP)

  • Consider planned delivery time field in MRP Areas

    Hi,
    I would like to know if the "Consider Planned Delivery Time" field in the MRP areas is taken into the scheduling of materials during MRP run? From the help documentation, it seems to be yes. Otherwise the system will take the Planned Delivery Time from the Plant level. May I ask how we can tick this field for all materials? We are currently in the process of activating the MRP areas in our system. Before, we didn't use the MRP areas but we think the need for it has arrived. Is there a mass maintenance tool to do this? Or do I have to use LSMW? Thanks!
    Regards,
    Chester

    Hello Chester
    If you flag the field "consider planned delivery time" the planned delivery time defined on the MRP area will be considered by MRP. You should tick it for all the materials if the value from the MRP area should be considered.
    Also, the report RMMDDIBE can be used for mass processing of MRP areas.
    BR
    Caetano

  • System is not considering Planned Delivery time

    Dear Gurus,
    As iam planning for the month of January and running the MRP,schedulelines are getting generated but system is not condering Planned Delivery time maintained in the material master ie. 7days.Following is the example:
    I have a FERT-X with a component A-1PC in its BOM and its planned delvery time from vendor is 7 Days.If iam running the MRP on 13/12/2010 for FERT-X  100 PCS for January1,2011 then the schedule lines are getting generated for for component A is on 01/01/2011.But PDT is maintianed in material master is 7 days and same has been maintianed in vendor inforecord.But system is not considering it.
    Kindly help to resolve the issue.
    With Regards.

    I have one ROH which has two different vendors.
    Two scheduling Agreemnt with target qty 100000 kg each.
    Two different Vendor info record with Min. order qty maintained.V1-1000Kg,V2-6000Kg.
    One source list with two vendors and with respective scheduling agreement.
    Quota arrangement is there in which SOB is maintiained 50:50.
    I hv the requirement of 3084 kg of ROH.
    I run the MRP and two diiferent schedule lines are getting generated with 50:50 qty as mentioned in Quota arrangement.
    Not considering the minimum order qty maintiained in vendor info record.
    The above process is correct
    Only One doubt In Quota Arrangement?
    IS two schedule line is created after MRP run?
    Generally System will  select a vendor Whose Quota value is less
    quota rating   = quota base quantity + quota-allocated quantity/ quota
    Edited by: Sundaresan . E. V on Dec 14, 2010 3:26 PM

  • How can i calculate execution time for methods?

    I'm making a project that i want to calculate execution time for a
    method in "miliseconds" or "microseconds".You see,I have a sort algorithm and i want to calculate execution time of this algorithm.How can i do?
    Thanks...

    Just remembered.
    The answer you get isn't trustworthy below a hundred millis, so you may need to sort a hundred or a thousand times to get a reasonable elapsed time. You also need to run the test five or ten times and take an average. In Windows you should fire up the Task Manager and be sure that your other CPU usage is as near to zero as you can get.

  • How can I get the time for a simulate signal express vi waveform?

    I tried converting to an array and then indexing, but every index I try only gives me the y value. See attached VI for clarification on what I mean.
    Attachments:
    simulate signal.vi ‏49 KB

    You will have to keep track of that yourself.  You are sampling at 360kHz.  This means that each sample is ~2.8us.  You can easily get the time by taking that dt (2.8us) multiplied by the sample index and adding the time at which the first sample was taken.
    There are only two ways to tell somebody thanks: Kudos and Marked Solutions
    Unofficial Forum Rules and Guidelines

  • Running FF12.0, how can I set maximum time for History Storage? What's the maximum time?

    Previous versions would allow me to set storage time up to 1 year, I think. Now I can't find the path to set this time. I would like to set it to as much as possible.

    Firefox 4+ versions do not have a time limit for the history.<br />
    Firefox determines automatically how many pages can be kept without affecting the performance.<br />
    You can see the current value via the read-only pref places.history.expiration.transient_max_pages on the about:config page.<br />
    You can reset no longer used browser.history_expire_days* prefs from older Firefox versions, if you still have them, to remove them on the next start.
    See Marco Bonardo's blog about this:
    * http://blog.bonardo.net/2010/01/20/places-got-async-expiration
    *Precise Clear History: https://addons.mozilla.org/firefox/addon/precise-clear-history/
    *Expire history by days: https://addons.mozilla.org/firefox/addon/expire-history-by-days/

  • MRP - Planned Delivery Time as 'Number of workdays' - How ?

    Hi All,
    We want to use 'Planned Delivery Time'(PDT) as 'Number of workdays' rather than 'Number of calendar days' while running MRP (Single item, multi level) from MD02 AND eventually that would be reflected in 'Availability date' in MD04. Can we achieve this by config or we need to search a proper user exit / BADI / enhancement spot for this ? Any suggestion on this is most welcome.
    Note - Factory Calendar ID has been maintained properly with Mon - Fri as working days.
    Thanks,
    Ashok

    Hi Csaba,
    Thanks for your input. The link you have provided does give information on how to assign the factory calender at plant level. However it doesn't answer to my question of how to use 'Planned Delivery Time' as 'Number of workdays'  rather than 'Number of Calender days' .
    My concern is 'Is it possible achieving this ? If YES, How ? By using config OR by any enhancement spots / User exits ?'
    Any suggestion is welcome.
    Thanks,
    Ashok

  • Purchasing: Planned delivery time

    I have a material that are being purchased from 2 vendors.  one vendor delivers the material in 2 days.  the other takes 20 days.  In the material master, I have to maintain the planned delivery time.  As per the help info, I will need to maintain the average time here.  So, that would be 11 days.
    So, when I run MRP, 11 days will be taken as the planned delivery time.  My planning is not going to be accurate if I choose any of the vendors.
    Can anyone guide me how I can take care of this scenario?

    Raj,
    You maintain your planned delivery times for each vendor in your info records.
    You need to ensure you have flagged the <i>scheduling info record/agreem.</i> flag (Determine Planned Delivery Time) in transaction OPPQ.
    You also need to ensure that you have maintained source list entries for your vendors that are relevant for MRP.
    Now the MRP run will consider the planned delivery time in the info record and not the material master.
    Hope this helps.
    H Narayan

  • Contract - Plant Conditions - Different delivery times for plant

    Hi people,
    I have a question about contracts , in transaction ME32K.
    I enter a Contract number
    Edit -> Plant Conditions menu.
    Select a plant and I can enter a different Net Price for each item for this plant. How can I enter "Planned Delivery Time" for each item for this plant?
    In this case, the vendor has different delivery times for each plant and I cannot enter this information.
    Do you know if it is possible?
    Thanks a lot!

    Hi,
        The basic requirement is for the trading of material which is imported  and for the material which are purchase locally there should be different invoice for such materials,  but while creating the sales order we have only one sales order including all types of materials so in such case we want to create different delivery challans  so that different invoice can be made easily  or only twi invoice for one delivery challan.
    regards,
    zafar

  • Planned Delivery Time from Material Master instead of PIRs

    Hi SAP Gurus,
    Do you know if there is a way to have MRP look at the Planned Delivery Time from the Material Master (MRP 2 tab) instead of the PIR?
    We would like to create global PIRs with a PDT of 1 and have the Material Master PDT set to a different number (example 5).  So when MRP runs it will read 5 instead of 1.
    Any additional information is appreciated.
    Thank you
    -nic

    Hi Nicholas,
    In Standard SAP will consider Planned delivery time maintained in Inforecord and than time maintained in Material master. Inforecord has higher priority than material master. When a requisition is manually created, the Planned Delivery date will always be taken from the material master.
    For MRP you can make setting OMDT for your plant or MRP group to determine planned delivery time.
    Deactive the flag 'Scheduling according to purchasing info record or agreement' in Customizing (Plant or MRP group). and test the same.
    Regards,
    R.Brahmankar

  • Can I write Design-time for JSP custom tag(not JSF components)

    I have some old JSP custom tags(not JSF components), and I want to use them in the IDE through the toolbox.
    Now I have already written the BeanInfos for these tags, and they can be drag from the toolbox; but it will throw a Exception when render the tags, and the properties in the Property Editor are not which I describe in the BeanInfos.
    How can I write Design-time for these tags? or whether it is possible to write the Design-time for these tags?
    the Exception is shown as follow:
    java.lang.ClassCastException
         at com.sun.rave.insync.faces.FacesPageUnit.renderNode(FacesPageUnit.java:1347)
    [catch] at com.sun.rave.insync.faces.FacesPageUnit.renderBean(FacesPageUnit.java:1086)
         at com.sun.rave.insync.faces.FacesPageUnit.getFacesRenderTree(FacesPageUnit.java:993)
         at com.sun.rave.css2.FacesSupport.getFacesHtml(FacesSupport.java:152)
         at com.sun.rave.css2.CssContainerBox.addNode(CssContainerBox.java:373)
         at com.sun.rave.css2.CssContainerBox.createChildren(CssContainerBox.java:354)
         at com.sun.rave.css2.DocumentBox.createChildren(DocumentBox.java:90)
         at com.sun.rave.css2.DocumentBox.relayout(DocumentBox.java:160)
         at com.sun.rave.css2.PageBox.layout(PageBox.java:392)
         at com.sun.rave.css2.PageBox.relayout(PageBox.java:454)
         at com.sun.rave.css2.DocumentBox.redoLayout(DocumentBox.java:313)
         at com.sun.rave.css2.PageBox.redoLayout(PageBox.java:460)
         at com.sun.rave.css2.DocumentBox.changed(DocumentBox.java:634)
         at com.sun.rave.designer.DesignerPaneUI$UpdateHandler.changedUpdate(DesignerPaneUI.java:1012)
         at com.sun.rave.text.Document.fireChangedUpdate(Document.java:851)
         at com.sun.rave.text.Document$5.run(Document.java:631)
         at java.awt.event.InvocationEvent.dispatch(InvocationEvent.java:178)
         at java.awt.EventQueue.dispatchEvent(EventQueue.java:454)
         at java.awt.EventDispatchThread.pumpOneEventForHierarchy(EventDispatchThread.java:201)
         at java.awt.EventDispatchThread.pumpEventsForHierarchy(EventDispatchThread.java:151)
         at java.awt.EventDispatchThread.pumpEvents(EventDispatchThread.java:145)
         at java.awt.EventDispatchThread.pumpEvents(EventDispatchThread.java:137)
         at java.awt.EventDispatchThread.run(EventDispatchThread.java:100)

    I have some old JSP custom tags(not JSF components), and I want to use them in the IDE through the toolbox.
    Now I have already written the BeanInfos for these tags, and they can be drag from the toolbox; but it will throw a Exception when render the tags, and the properties in the Property Editor are not which I describe in the BeanInfos.
    How can I write Design-time for these tags? or whether it is possible to write the Design-time for these tags?
    the Exception is shown as follow:
    java.lang.ClassCastException
         at com.sun.rave.insync.faces.FacesPageUnit.renderNode(FacesPageUnit.java:1347)
    [catch] at com.sun.rave.insync.faces.FacesPageUnit.renderBean(FacesPageUnit.java:1086)
         at com.sun.rave.insync.faces.FacesPageUnit.getFacesRenderTree(FacesPageUnit.java:993)
         at com.sun.rave.css2.FacesSupport.getFacesHtml(FacesSupport.java:152)
         at com.sun.rave.css2.CssContainerBox.addNode(CssContainerBox.java:373)
         at com.sun.rave.css2.CssContainerBox.createChildren(CssContainerBox.java:354)
         at com.sun.rave.css2.DocumentBox.createChildren(DocumentBox.java:90)
         at com.sun.rave.css2.DocumentBox.relayout(DocumentBox.java:160)
         at com.sun.rave.css2.PageBox.layout(PageBox.java:392)
         at com.sun.rave.css2.PageBox.relayout(PageBox.java:454)
         at com.sun.rave.css2.DocumentBox.redoLayout(DocumentBox.java:313)
         at com.sun.rave.css2.PageBox.redoLayout(PageBox.java:460)
         at com.sun.rave.css2.DocumentBox.changed(DocumentBox.java:634)
         at com.sun.rave.designer.DesignerPaneUI$UpdateHandler.changedUpdate(DesignerPaneUI.java:1012)
         at com.sun.rave.text.Document.fireChangedUpdate(Document.java:851)
         at com.sun.rave.text.Document$5.run(Document.java:631)
         at java.awt.event.InvocationEvent.dispatch(InvocationEvent.java:178)
         at java.awt.EventQueue.dispatchEvent(EventQueue.java:454)
         at java.awt.EventDispatchThread.pumpOneEventForHierarchy(EventDispatchThread.java:201)
         at java.awt.EventDispatchThread.pumpEventsForHierarchy(EventDispatchThread.java:151)
         at java.awt.EventDispatchThread.pumpEvents(EventDispatchThread.java:145)
         at java.awt.EventDispatchThread.pumpEvents(EventDispatchThread.java:137)
         at java.awt.EventDispatchThread.run(EventDispatchThread.java:100)

  • Planned Delivery time not considered after MRP run for scheduling

    Dear All,
    After running MRP, the planned delivery time maintained in Purchase info record is not taken into consideration for calculating start date of the schedule line of externally procured material generated by the system.
    Planned delivery time is 3 days & Requirement of parent material falls on 15/02/2010. With this, system should calculate the start date for schedule line as on 12/02/2010 considering 3 days Planned Delivery time.
    Any idea as to what might have gone wrong?
    thx for your help in advance.
    Rgds,
    Ranjeet

    Hi,
    Determination of PLD from the Purchase info record is maintained in transaction code:OMDT. Planned Delivery time is also maintained in Scheduling agreement. However, it is not calculating delivery date as well as release date.
    Rgds,
    Ranjeet

  • Is planned delivery time is considered in scheduling agreement ????

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"". System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) G .R processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 10.07.2008
    Please Guide . How i can take care of that time which is requiered at vendor ends.
    Regards
    Rahul Bhardwaj

    Go to OPPQ for that plant
    Click on "External Procurement " tab and check if you have maintained any planned delivery time?
    Tick indicator " Scheduling info record/agreement " (This will take Planned del time specified in scheduling info rec or agreement)

  • How planned delivery time effects delivery creation?

    Dear All,
    Some time before, while placing order thro' CRM, we came across a typical error (hard error).
    "date (11/12/2011) lies afterthe end of validity calendar". 
    we could not place order in CRM but in SAP we could create save the order despite of same error but soft. However system didn't allow to create delivery for same order & same error message populated"
    Later it was found that it is because for material  " Planned Deliv. Time  maintained for say "X "days in material master MRP2 view" & was corrected.
    How planned delivery time effects delivery creation?
    For material even though planned delivery time was maintained as say for 500 days, sales order requested delivery date & delivery date in order schedule line got determined as order date (Considering avaliability of funds & material).
    i.e order date/req. delivery date/delivery date in schedule line are same as date on which order is placed.
    Regards
    Suhas W

    Hi,
    Extended your factory calender in SCA3.
    Regards,

Maybe you are looking for

  • Service Desk User access

    Hi Experts, I want my service desk users login on Solman and they can update Msg status and ther remarks. so what are auth. object needs on there profile, please suggest. Can we block users access in such a way , they are not able to do add change on

  • Do this device have Wifi connectivity ? Insignia - Blu-ray Disc Player: NS-WBRDVD

    http://www.bestbuy.com/site/Insignia&%23174%3B+-+Blu-ray+Disc+Player+with+Wi-Fi+and+1080p+Output/938... "Built-in Wi-Fi support  For future streaming and product updates." What does this mean "future streaming" -- does this mean it's does currently w

  • Reassigned scratch disk--now, PS won't open!!!

    I have a Power Mac G4 (AGP) with two hard drives running Tiger. I installed CS4 and everything was fine until I started fiddling around in Photoshop and changed the scratch disk from disk 1 (10G start disk) to disk 2 (80G). All my applications are in

  • 2 Full Albums showing corruption error when I try to download?

    I purchased two full albums of hollywood undead yesterday, and every time I try to download the albums from the iTunes store I get the following error: "The file seems to be corrupted. To redownload the file, choose "Check for Available Downloads" fr

  • N80 v4 Firmware on Voda - any news ..?

    Since being fobbed off by Voda a couple of weeks ago, I've heard nothing - and needless to say there's no update available on NSU. Just wondering if anybody else had been in touch with Vodafone and had any news .. like they're at least working on it: