How to change operation dates in Production Order /Capacity Leveling

Dear Experts ,
We are using ECC 5.0 .In production order , scheduling happing as Backward  based on the Sales Order Delivery Date .I am doing the following :
1.Demand as Sales Order with Delievery date : 20.03.2010
2.Running MRP with Lead Time Scheduling -2  in md02 and converting the Planned Order to Production Order .
4.Production Order have following dates :
         Basic Finsish Date : 21.03.2010
         Basic Start : the day Pl.Or--Pr.Ord
         Schedule Start : 15.03.2010
         Schedule Finsish : 17.03.2010
        Schedule Release : 13.03.2010
5.In schedueling margin key :  Float Before Production : 3    , FAP : 3 , Release Period : 2
6.In material master : Work Scheduling View : Setup : 3 days , Processing : 4 ,Interoperation : 2 for one Base Qty 1
7.In operation : Op1  : Start Date  : 15.03.2010    Finish Date: 15.03.2010
                         Op2 : Start Date : 16.03.2010      Finish Date : 17.03.2010
                         Op2 : Start Date : 17.03.2010      FD : 17.03.2010
Question :
1.How to change the Operation dates  in Production Order Operation over view screen ? Today,  operation over view screen , Start date and Finsih Date  of individual operation are not changable with in Production Basic Start /BF date  or beyond .It is only changing based on the Standard Value : Labor
2.How to change/re-schedule operation dates d in CM21 (Graphical view -Work Center Capacity load as per   Production Order and Operation combination ) based on capacity availale in advance dates? I am using  Time Profile : SAPSFCZ002 -SFC Graph midterm-3 motnhs and Planning  ,
How to solve this above issue in scheduling operation and capacity distribution .
Regards
JH

Closing the thread

Similar Messages

  • How to change material discription at sales order item level ?

    Dear Gurus,
            We have some requirement need to change material description at sales order item level , but in system it is in disable mode how to change that  into change mode in sales order item level?
    Thanks in advance
    Regards
    Venkat

    Not possible in SAP Standard.
    Instead why not create a Customer Material Info Record in T-Code - VD51?
    Alternatively it the requirement to change the Description is only for few Sales Order then create a Text ID & Enter the Description in Text Feild. Then in Smartform program wrie a code which will check for Material Description in the Text first & if not found then take from normal material Description in Sales Order.
    But Customer Material info Record seems to be the best solution.
    Hope this helps,
    Thanks,
    Jignesh Mehta

  • How to change Profit center in production order

    Hi guys,
    I have to change Profit center value in production order. Order has been created and released also. How to change, if i directly change system throwing error...Please suggest me in this case.
    RGDS
    Dos

    Then Go to OBA5 enter the KO  Application area
    Add the 367 message and  your user iD enter warning in online and Batch,
    After that You can able to Change the   profit center in Order with warning message in Order

  • How to change translation date in sales order

    Hi would it still be possible to change the translation date in the sales order if delivery document is already created and good issue is already is already posted. Please advise where on the sales order i can change the translation date.
    Thank you

    Dear,
         Please give me path of translation date in sales order. I find but not getting in sales order.
    Sandip

  • How to set deletion flag in Production order item level

    Hi Friends,
    I have a requirement like...
    Suppose production order conatians 100 items. now i want to set deletion flag for 20 items only.
    In Co02 t.code deletion check box is disable mode.
    There are nearly 100 production orders .i have to write the program....
    Is there any BAPI or other way to meet this requirement.
    Can you please help me..

    Also, You might want to have a look at the BAPIs like BAPI_PRODORD_SET_DELETION_FLAG which are used to set the deletion indicator but it appears to me the deletion flag can only be set at the header level using these BAPIs.
    Please have a look at SAP business object BUS2005 methods from transaction SW01 for more Production Order related BAPIs.
    One more thing ... since you mentioned that in CO02 the deletion indicator is greyed out, then it might mean you are missing the authorizations to set the deletion flag. Please consult with your Authorization (BASIS) administrator. As a hint, the authorization object here is C_AFKO_AWK.
    Cheers,
    Aditya

  • Error while creating production order (capacity leveling)

    Hello Friends,
    For capacity Planning - Leveling, i am using overall profile  "SAPMPSG006 - MPS/MRP: Capacity availability check", in Production scheduling profile, which i have attached in the material master.
    In Availability check parameter, checking control for the combination of Plant,order type and business transaction 1, in capacity availability section also, i have maintained the overall profile "SAPMPSG006 - MPS/MRP: Capacity availability check'.
    Now i have created the production order for a particular period (start date 17.03.10 , finish date 20.03.10). In CM01, agaist the work center, i can see the load. Hence available capacity and required capacity is same for three days.
    Now again i have created one more production order for the same period (start date 17.03.10 , finish date 20.03.10), system is showing the window with the message work center with overload.On the same screen, when  i click on finite scheduling tab, than system showing the new latest start date and time the same as earlier date i.e 17.03.10.
    Here my question is , when i click on finite scheduling tab, than system should propose the date 21.03.10, as on and after this date capacity on this workcenter is available. But system is not proposing the dates, where capacity is available.
    When i checked the dispatching log, there i found two errors.
    continued..................

    Dear,
    That's great production order system is proposing the future date automatically.
    Few check,
    1) Factory calendar for holidays?
    2)Any other production order on that days?
    3)Your capacity profile and its setting?
    Basic dates
    Check whether scheduling should be performed with a time being specified. For this, check the scheduling data of the scheduling type in Customizing. OPU3
    Do the basic dates change?
    Check whether the alternative "Adjust basic dates" has been selected for the scheduling parameters.
    Check whether the basic dates are set correctly on account of the operation dates. So check operation dates also?
    Regards,
    R.Brahmankar

  • How to Find Operations on a Production Order.

    Hi Friends,
    I have got a requirement, in which I have to Delete all of the operations on the order that have already been confirmed.
    Actually we will be getting Excel file they will be gving us fileds Like :
                         Material Number
         Quantity
                         Batch Number
         Serial number
         Expiration Dates
         Last confirmed operation
    i have wriited the code for creating Bacth number serial number and production oreder.
    but, I have to delete all the operations that have been done on the order.Excel sheet contains the last confirmed operations.
    Kindly let me know In which table I will be able to find the operations?
    Regards,
    Xavier.P
    Edited by: Xavier on Sep 24, 2009 8:32 PM

    Xavier,
    Sorry for the late reply. Yes, you are correct.  AFVC-VORNR will give you operation no. & AFVC-LTXA1 will give the operation short text. I am guessing since you already have the confirmed operations on your excel sheet. You should be able to download AFVC table operations to excel, do Vlookup to get your unconfrimed operations. Alternatively you can use Access database  to get your unconfirmed operation records.
    But if you need confirmed operations then as mentioned by our other friend AFRU table would be useful .
    If you have more questions let us know. Hope this helps you.
    Thanks,
    Ram

  • How to Change delivery  date in Sales Order????

    Hi Guru
    If i creating Sales order (OR) for eg date 29/11/2007, for delivery date it will 6/11/2007, If i change Mannualy for delivery date, it will getting some error, i need delivery date should be one or two days delay only.
    regards
    [email protected]

    Hi Mohammed,
    In the sales document type configuration screen you have the field for Delivery Date Proposal. Use the appropriate value that is required. Also confirm the order date in your question is later than the delivery date maybe that is the reason why the system is giving you an error.
    Regards
    Nadarajah Pratheb

  • Changing operation date in co02

    Hello everyone,
    We have quite lengthy production operations and we need to change individual operation date, of planned or production orders (especially production order, in fact, before they are relased in fact).
    The problem is that when I access Co02, and go to the operation list view, I cannot change the date. I can enter an operation or delete one but I can't change the start date of each operation.
    It is absolutely needed in our case, as we have a lot of waiting time in the shop floor and need to review the schedule to match free slot. There is not a lot of orders , so the most convenient way is to do it from the Operation list, in Co02.
    Please could you tell me how it is possible.
    Many thanks,
    Pierre Mikael

    Dear ,
    I am not sure whether you have Capacity Requirement Planning is in place  for PP cycle .Basically , operation dates and production order schedule dates can be changes based on the available capacity of Work Centre wehre the respective operations are happing in shop floor.There two kind of production scheduling happend in any production order .One is operation level scheduling and another order level scheduling .Order level scheuling should havppned based on the total details scheduling of operation based on the work centre load ( available , over load , requirement hrs at work centre ) .
    Any operation in a scheuled production order , can have changes in date wheile deispathing the operation for work centre once the CRP in place .Here , we have Scheduling margine ( FBP, FAP, Opening periods ) contributes to Basic Start Dates in Production order .It is possible though Capacity Leveling -CM21/CM22/CM31/CM23  after cheking the Capacity Load in CM05/CM07 for a particular work centre level.
    The simplest way to adop CRP and explore the same .please find belwo the detaiuls of  the same :
    Setting Required :*
    1. Settings for Available Capacity
    2. Setting for Capacity requirements
    3. Settings for Capacity evaluation and leveling
    4.Materials Master define the Production scheduler and production scheduling profile
    5.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view. 6.Routing - enter the values for the standard values. Use control key with scheduling.
    7.In transaction OPU5 and OPU3Z - define the scheduling parameters for planned order and productiion orders and activate the checkbox Capacity requirement and Scheduling.
    8.Capacity Setup :
    1.Define time profile in OPD2.
    2.Define the strategy profile in OPDB
    3.Define the Overall profiles in OPD0.
    4.In the order control OPJK  maintained check capacity with SAPSFCG013 profile.
    5.Define Scheduling parameters for Production orders-OPKP-Maintain Capacity Checked /Finite Scheduling Cheked /Scheduing Type -BW/FW .
    Hope this will help u in analysis
    Regards
    JH

  • How to get change date in Production Order ?

    Dear Friends,
    I want to know it, how to get change date in Production Order "Administration-TAB".
    F1-Help, It is displayed with "Change date for Order Master". and Structure table "CAUFVD".
    But, CAUFVD is not Transp. Table.
    Which table should I read ?
    Thanks in advance
    Yamazaki-H

    Dear Friend
    Thank you for an answer.
    It was settled.
    Best regards.

  • How to collective read PP master data in Production order?

    Hi: Guys
    Please tell me how to collective read PP master data in production orders. in COHV, I can find out some collective functions but read PP master data.
    Thanks
    Henry

    Read PP master data is only to update routing and BOM in production order if it is already created to effect the changesmade in routing and BOM.    I think in that collective option is not possible.  
    Regards
    KrishnamurthyDSS

  • FM or BAPI to change Operation data

    Hi,
    Is there any BAPI to change operation data? BAPI_ALM_ORDER_MAINTAIN is not useful in my case. I want to use   IBAPI_ORDER_OPERATION_CHANGE but not able to get proper documentation for same.Can anyone give me a sample code about how to use IBAPI_ORDER_OPERATION_CHANGE?
    My requirement is to tick check box 'Required Splitting' in operation if some conditions are met. I am planning to do this using cuatomer exit. Everything is working fine only i need to know how to use above BAPI. If this doesn't work then as a last option i will go with BDC.
    Regards,
    Kamal

    Hi Kamal,
    Unfortunately I can not see any BAPI which changes operation data of a production order.
    BAPI_PRODORD_CHANGE is available only for changing header details.
    BAPI_ALM_ORDER_MAINTAIN and IBAPI_ORDER_OPERATION_CHANGE are used for changing maintenance or service orders, and not production orders, most probablty this won't work or cause issues.
    I'm afraid BDC is the only option in this case.
    Regards,
    Marcelo Pacheco

  • Programming Operation in a Production Order

    Hello all.
    How can i mark an operation of a production order as programmed with my predifined dates and without being scheduled by SAP?
    Thank you
    Nuno Silva
    Message was edited by:
            Nuno Silva

    Hi,
    In my case i am not using puchasing info records in this cases. i am making the system to create only automatic purchase requestion only.so how can i insert that item category D in this case.
    please suggest .
    rgs
    madan

  • Change Delivery date in Sales Order

    Hi all
    I want to change Request Delivery Date in Sales Order. But when I changed Request Delivery Date system appear" The default date is not copied into existing schedule lines"
    And Delivery Date didn't change.Could you tell me how to change Delivery Date ?
    I setup Request Delivery Date - September 21th but Availability Date is September 19th. Could you tell me how to setup loading time, picking time, packing time ?
    Thank and Best regards,
    Thang

    Hi,
    When you change the Request Delivery Date, it automatically changes the schedule line date of all the materials, but by default does not change the schedule line date of the ordered material.
    So just check the ordered material schedule line date and change it manually in the order.
    Similarly maintain the same date in all the resp fieldsi in the delivery, wherever you see the date.
    Regards,
    Siddharth.

  • How to change Payment Terms in multiple orders at same time?

    How to change Payment Terms in multiple orders at same time?
    I have got 10,000 Order, I need to change the payment terms for all these Orders.
    Can I Know the way out for this.
    Regards,
    Dantham Conpolwedson
    Edited by: Dantham Conpolwedson on Mar 25, 2009 11:18 AM

    Hi
    There are as many options for that
    You can go for
    1)MASS t code
    2) LSMW  (by recording)
    3)BDC (by recording)
    and the most easiest way is by doing the MASS tcode
    goto MASS and enter the object type as BUS2032
    execute now select the sales order haeader data and execute and now enter the sales doc from and to range and execute now all the sales dox will be displayed
    and from the menu click on select fields  and select the terms of payment
    now select the terms of payment row and enter the new values  and click on carry out new changes
    regards

Maybe you are looking for

  • How to turn off numjoin and/or numgroup attributes in basic_lexer

    My user has some digits embedded in subject line, such as "PQR 17234,34394,83343". Oracle interMedia Text is treating them as a big number, instead of three different words. How can I turn off the default numgroup and/or numjoin in the basic_lexer? I

  • Invoice duplication for MIRO

    Hi Friends, We have activated " check for invoice duplication " indiacator at vendor master record. Even though user was able to enter credit memo twice through MIRO for the same vendor. I thought that we couldn't post the same invoice # to avoid dup

  • Receiving all messages including old ones from a JMS Topic

    Hi all, is there a way for a subscriber to receive all messages available in a Topic including the "old" ones? By the "old" messages I mean messages written in the Topic before the subscriber really subscribes or messages created oven before the subc

  • PSE download for Mac?

    I have used the cd for Windows. I would like to install same on Mac but Mac does not have CD player. Is there a download available so I don't have to purchase CD player for this?