How to change process chain in SAP APO, in RSCP tcode.

HI SAP APO Experts
I am from SAP ABAP background, I need to change a 'AND' operator in process chain in RSCP tranaaction in SAP APO.
I dont have any idea how to change process chain.
Could you please help me how to change process chain in SAP APO in RSCP tcode.
Appreciate your help or comments.
Sandeep..

Hi Sandeep,
The t-code RSCP does not exist in SAP APO.  The correct t-code is RSPC. 
Step 1:- In RSPC t-code, select the process chain which you need to change. 
Step 2:- Double click on it. 
Step 3:- It will display the various programmes attached to the process chain.  Go to change mode by clicking on the change indicator (Control + F9)
Step 4:- Select the programme area where you need to do the correction or change.  Double click on it.
Step 5:- It will take you to the programme and its selection contents.  Make the relevant changes.  You can directly carry out the change in se38 also if there is variant kind of changes for that particular programme.
Step 6:- Once the changes are done, save the changes and press F3 button which will take you to the home page of the process chain
Step 7:- Save again so that the change in the programme alongwith the process chain will get saved.
Regards
R. Senthil Mareeswaran.

Similar Messages

  • How to change process chain description

    when i am creating  the process chain the word  "New:" (Eg :  New: SPL Load Daily Night) is added to custom description,How delete the "New: "
    Can any body help in this regard.
    Thanks,
    Bala.

    Hi,
    If it is just about those that say New, then try what Dinesh has suggested...See this thread for details:
    Re: Assign Process Chain name to Application Component
    Hope this helps...

  • HOW TO STOP A SCHEDULING A PROCESS CHAIN IN SAP BPC

    Hello Expert,
    Can Any 1 tell me  how to stop a scheduling of a process chain in sap bpc ??

    Hi Neeraj,
    Your question is not clear.
    If you are asking - How to delete a schedule which runs a process chain/DM package from EPM, then please go to Data Manager -> click View Status arrow -> select view schedule status -> select the schedule, right click and choose delete schedule.
    Neha

  • How to Delete Process Chain?

    How to Delete Process Chain?

    When in the change mode of a process chain, choose the menu entry 'Process Chain --> Delete' (Only available on change mode).
      Cheers
       SAP NetWeaver 2004s Ramp-Up BI Back Office Team

  • How to schedule Process chains in Bi Admin Cockpit

    Hello friens,
    I am working on installing Bi cockpit.
    After installing the info providers, i have to schedule the process chains for Bi admin Cockpit.
    I know the transaction is RSPC.
    But I dont know how to schedule process chains for Bi admin cockpit.
    How to schedule Init and Delta
    If you can send me step by step documents.
    Or any good sap note number.
    Or any good links i will really apreciate it.
    I want to schedule process chains
    Content Master Data
    Data Load Statistics # Delta
    Data Load Statistics # Init
    Query Runtime Statistics # Delta
    Query Runtime Statistics # Init
    System Master Data
    Please advise

    Hi,
    Please check out this document:
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/8da0cd90-0201-0010-2d9a-abab69f10045
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/36693695-0501-0010-698a-a015c6aac9e1
    Hope it helps.
    Thanks
    Mona

  • How to create Process chain in BI 7.0

    hi,
        I dont know how to create process chain in BI 7. If any one have document step by step process to create process chain. help me. thank u.

    check these links..
    http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/00a1f389-ec7c-2c10-04bc-9d81b3084171
    http://wiki.sdn.sap.com/wiki/display/BI/Processchainscreationandmonitoring
    http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/900be605-7b59-2b10-c6a8-c4f7b2d98bae
    http://wiki.sdn.sap.com/wiki/display/BI/FiveWaystoEnhanceBIFunctionalityUsingABAP--PartV--ABAPinProcess+Chain

  • How to create Process chain for Aggregate for Master data

    Hello friends,
    I created Aggregates on Navigational Attributes.
    Now they are working fine, but i need to know that how shall i create the Roll up for Aggregates on Navigational Attributes.
    The point is the master data changes frequently a lot of time for e.g. for 0customer etc.....
    So if any one can send me the step by step documents so as to know how to roll up the Aggregates for Navigation attributes or for aggregates created on Master data....
    How to create process chains for the same ?????????
    Because if master data changes, then rolling up the aggregates straight forward will not help.
    So we need to write a process chain so that it deactivates the aggregate and reactivate again and fill up again..........
    If i mis interpreted something please rectify it.......
    Please advise

    Hello,
    the changerun that you have to schedule in order to activate the master data will adjust the aggregates automatically.  There is no need to deactivate them after master data loads.
    Best regards,
    Ralf

  • How to create process chain ?

    hi all,
    will you please simlify how to create process chain if anybody has a screen shot or slide show about pc creation it will definatly help me a lot.
    rewrd point for sure,

    This may help:
    [http://help.sap.com/saphelp_nw04s/helpdata/en/67/13843b74f7be0fe10000000a114084/content.htm]
    [https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/8da0cd90-0201-0010-2d9a-abab69f10045]
    Regards,
    Jordi

  • How to create process chains,and how to use process like and or xor

    Hi,
    How to create process chains,and how to use process like and or xor.
    can any one please give me a example in each.
    Thanks,
    cheta.

    Hi Cheta,
    Here is step by step procedure to create process chains
    Process chain is nothing but executing a process ..(or) loading the data any process we can do in background.. that means.. automatically we can execute our process based on Time or any event..
    Creating Process Chains
    Prerequisites
    If you want to include a load process in the process chain, you need to have already created an InfoPackage.
    You cannot load flat file data from a client workstation in the background. For this reason, you have stored your data on an application server.
    Creating Process Chains
    You have the option of creating a process chain in the process chain maintenance screen directly or by using a maintenance dialog for a process:
    Creating a Process Chain Directly in the Process Chain Maintenance Screen
    You are in the BW Administrator Workbench.
    1. Click on the Process Chain Maintenance icon in the AWB toolbar.
    The Process Chain Selection dialog window appears.
    2. Choose Create.
    3. Enter the technical name and a description of the chain, and confirm your entry.
    The Add Start Process dialog window appears.
    4. Create a variant for a start process.
    1. a. On the Maintain Start Process screen, choose whether you want to schedule the chain directly or whether you want to start it using a metachain.
    2. b. If you choose to schedule the chain directly, enter the start date value for the chain under Change Selections and save your entries.
    The Maintain Start Process screen appears again.
    3. c. Save your entries, return to the previous screen and confirm your entries in the Add Start Process dialog window.
    You are taken to the Plan View of the process chain maintenance screen.
    In the left-hand area of the screen, a navigation area is displayed. In the right-hand area of the screen, the process chain is displayed.
    5. Use the drag-and-drop function to add the relevant processes into your process chain.
    You use the Process Types function to select the processes. This sorts the process types according to different categories. You can also call up InfoPackages and processes for the data target from the separate InfoSources and Data Targets navigation trees.
    Hope this helps
    Regards
    Karthik

  • How to find process chain using background job in sm37

    How to find process chain using background job in sm37

    Better is to select the job.
    Select (Define) Step (s) or F6.
    Select the line and Menu Goto>Variant.
    The variant contains the name of the CHAIN and its VARIANT.
    Success
    We faced an old job and via job monitoring we were informed about a cancelled job every 'interval'.
    We noticed that the related chain was deleted but still the job was scheduled each interval again and was cancelled because an event was missing
    We could not find the scheduled job via SM37.
    Via view V_OP, view over tbtco abd tbtcp, we find the related entry.
    We delete these entries via function BP_JOB_DELETE....
    Edited by: Jack Otten on Jul 9, 2010 2:50 PM

  • How to change the color of SAP screen?

    Hi Frens,
    I know it has nothing to do with SD Community, but still I am asking. Can anyone tell me "How to change the color of SAP screen?" It is needed especially when you are working on System Landscape including PRD, Qua & Dev. There are chances that you end up making a test case in PRD instead of Dev or Qua. To avoid that, different color of SAP screen may be very useful and safe.
    Regards
    Vikas Chhabra
    SD/CIN Consultant

    We had a clone of SAP for testing
    Only GUIXT solution was available for users to distinguish between real Prod & Clone as SID was same
    Created 2 scripts n C:\guixt\scripts
    saplsmtr_navigation.e0100.txt
    Esession.txt
    BOTH having identical code
    if V[_ashost=10.3.3.18]
      TitlePrefix "CLONE18"
      TitleSuffix "(CLONE8)"
    endif
    if V[_ashost=10.3.3.25]
      TitlePrefix "PROD25"
      TitleSuffix "(PROD25)"
    endif
    After much research - this was only solution.
    GUIXT will be around; like SAPSCRIPT & SMARTFORMS
    despite the enticement of Adobe Forms!
    After some time you may set GUIXT profile start window HIDDEN
    This you do by clicking profile button of GUIXT menu
    If you want to see GUIXT Window again
    CMD.exe Dos prompt
    cd C:\Program Files\SAP\FrontEnd\SAPgui
    guixt visible
    Regards
    Jayanta Narayan Choudhuri
    Kolkata
    URL: http://ojnc.byethost11.com

  • How to stop process chain, if it is taking too much time than expected.

    Some times if a process chain takes to much time to finish than expected, how I can stop the process chain and execute it again.
    Thanks in Advance.
    Harman

    how I can stop the process chain ??
    If the job is running for a long time ,
    1)GOTO RSMO and SM37 and check the long running job over there.
    2)There you can see the status of the job.
    3)If the job is still running you can kill that job
    4)delete the failed request from data target.
    for more details go to this below link
    how to stop process chain if it yellow for long time
    how I can execute it again ?
    GOto Function module  RSPC_API_CHAIN_START
    and give u r process chain name there.and execute.

  • How to kill process/Actavity in SAP ?

    How to kill process/Actavity in SAP ?

    The core file contains the memory state of the work process at the point it was terminated. You could use it for debugging the work process if you had access to the kernel source code, which you don't unless you are SAP. For most people, then, the core file is of no interest and just takes up space in the operating system's file system. Using "cancel without core" is the thing to do.
    That said, sometimes I find "cancel without core" doesn't actually work but "cancel with core" does. I always try without core first, but occasionally have to resort to with core. If you do cancel with core, make sure to go and delete the core file afterwards to avoid the file system filling up. Work process core files can be large. You'll find it in a directory/folder here - /usr/sap/SID/DVEBMGS00/work (substitute DVEBMGS00 as appropriate).
    Steve.

  • How the excise  process  happen in SAP.

    Hi All !
    Please tell me ,how to find out diffrence amount for given problem:-
    Opening Balances of Excise duty payable accounts as on 31.3.2009  are coming in to picture  in T- Code FAGLB03 is showing  a  credit balance Which actually should show zero balances. In same way cenvat  Credit balances both in RG23 A part II and RG 23 C part II   are also not matching.
    for FAGLB03 ,some entry is passed with sa document type with FB50.
    And explain me  how the excise  process  happen in SAP.
    Thanks and Regards
    Archana Sharma

    Hi!
    Please give the details of process and tell me how I will update in given table J_2IACCBAL.
    Thanks & Regards
    Archana Sharma

  • How the excise  process  happen in SAP. FAGLB03 is showing  a  credit ba.

    Hi All !
    Please tell me ,how to find out diffrence amount for given problem:-
    Opening Balances of Excise duty payable accounts as on 31.3.2009  are coming in to picture  in T- Code FAGLB03 is showing  a  credit balance Which actually should show zero balances. In same way cenvat  Credit balances both in RG23 A part II and RG 23 C part II   are also not matching.
    for FAGLB03 ,some entry is passed with sa document type with FB50.
    And explain me  how the excise  process  happen in SAP.
    Thanks and Regards
    Archana Sharma

    Hi,
    Reverse FB50 Document & post through J1IH.
    Ramesh

Maybe you are looking for