How to cleanup the CUA entries

Hi all,
I'm in the process of doing some client cleanup prior to an upgrade project.  I am also just learning about the CUA system so have been reading through the docs.
Our landscape:
UTL - Solution Manager and CUA  (7 ehp1)
DEV - Development (ecc5)
QAS - Quality (ecc5)
PRD - Production (ecc5)
This was set up about 5 years ago during intial implementation, and little has been done to manage the CUA child entries to match up with client useage changes over that time.  At this point, security uses CUA for some clients and local user admin for others.  When I use t-code SCUA I get the message the "CUA definition is inconsistant, for repair see long text."  And I beileve the issue it is complaiing about is there are child systems still defined in CUA that don't exist, or no longer have a connection.
I'm wanting to remove these old child systems, and will delete the actual clients where then exist after removing them from CUA.
What I'm not to clear on yet is what happens after I go through the steps on the central system
a.     T-CODE SCUA
b.     T-CODE WE20
c.     T-CODE BD64
Since I'll be deleting the associated clients on the respective system, do I need to do the steps for deleting a CUA child on the local system as well?  Then delete the client?
At some point I'll be adding the new CUA child entries for the actual/used clients as well.  But I thought I'd go through the delete process first.
Any corrections or clarifications as to what I'm attempting to do will be much appreciated!
Thanks
Laurie McGinley

Thank you Bree,
So as I understand you, I do not need to run through the WE20 and BD64 transactions to remove them from the distribution model IF there may be a chance we could recreate the associated client on the source system. 
So... for example...
I want to get rid of DEV:700 now because we no longer use it.  The CUA child is DEVCLNT700.  I can use the report RSDELCUA and delete the child which removes it from the CUA list.  I can then delete the actual client DEV:700.  In a year, when we decide we want that client back for testing, I can create the client, and add it back to the CUA landscape screen and run SCUG.
If, however, we decide we won't be recreating that client in the future...
I would need to run the report, delete the cua child... and here is where I'm unclear.  Do i need to run WE20 and BD64 in the central system before doing the actual client delete?  And if so, do I need to do the steps at the client system for removing a child from CUA before I actually delete the DEV:700 client.
Hope this isn't too confusing...
Thanks
Laurie

Similar Messages

  • How to delete the total entries in ztable

    Hi ,
    How to delete the total entries in ztable...
    code pls.
    regards,

    Hi Venkat,
    pls see below records,
    Plant  Material                       Alternate material
    3770  00000000000126875          2020202
    3770  000000000005999335        2020202
    3770  117196                           2020202
    3780  00000000000126875           2020202
    3784  00000000000126875         2020202
    3784  000000000002809336       2020202
    3784  000000000005999335        2 020202
    3789  00000000000126875            2020202
    if  i write below syntax ,
    delete from ztable where matkl = '2020202'.
    all records contains  matkl = '2020202' will be deleted ??
    pls. reply.

  • How to tracke the new entries in database table ?

    Hi,
    How to tracke the new entries in database table ? is there any FM or report is there to check it ?
    regards
    vishnu

    Hi Vishnu,
    u can write a report program for this and in that use the event  :
    AT NEW <field-name> ( use primary key)
    your statements
    ENDAT
    for eg.
    loop at itab ( herfe itab must be of type of table for which u want to track new entries)
    at new matnr
    write:/ new record
    endat
    endloop.
    schedule this report in background to run in every 5 or 10 mins as per your requirement and hence changes can be tracked.
    regards
    Vinod

  • How to retrive the deleted entries in the ztable

    please let me know how to retrive the deleted entries in the ztable.

    >
    Naseer uddin wrote:
    > Hi,
    >
    >   While creating a table have u activated the buffering (full).
    >   if not then it is not possible to retrive the lost data, and if u have activated the full buffering of table then it is possible to retrive data, up to some extent, using transaction Code se14.
    Complete Nonsense.*
    buffering doesn't mean that it will buffer the records back in database ,once you deleted.it means it will allow the buffer the table to memory only while read access.

  • How to Reverse the Part1 entries

    Hello,
    We have received the Some goods, at the time of GR we choosed the option "Only Part1 entry"
    So in this case J_1IPART1 table updates the qty field and system will not generate any Doc NO(Internal Number) here.
    So we donot want to take the MODAVT for this material(bcz this is Diffence material). We want to cancell only PART1 entries from table .Bcz we were unable to reverse the goods( qty was already consumed).
    How to cancell the part1 entries, in these table there was no Internal number
    Note:  If material doc was not updated J_1IPART1 table, then we updated from J1I5 t.code, is there any option is there to reverse only Part1 entries.
    Regards
    Mahesh Naik

    Hi,
    1) If you dont want to cancel material document : In this case go to T. Code J1IS and select the option "delete" (a bin symbole made on menu bar). Then enter Internal No and year , then save it. But here you are saying while taking goods receipt Internal no is Not generated so i think this solution will not work for you.
    Through J1IS t.code cancellation was not possible, Bcz in this case we have no internal number
    2) Now you have to Cancel the material Document : Go to MIGo T. Code. and select " Return Delivey" Instead of Cancellation and with reference to Material document save the document. In this way material document will be cancelled and part One entry will be reversed. But make sure that in Configuration of Movement type of CIN is having 122 Mvt type
    We have checked in configuration there 122 mov type was available, if suppose we choose the rerurn delivery then system will reverse the goods(The perticular material doesnot have stock, stock is Zero). Is it reverse Part1 entry. then shall i go for One more time GR? how to do it?

  • I need a fix from HP which outlined how to remove the registry entries which were stopping recognition of the cd/dvd reader but then itunes cannot find the reader.

    I need a fix from HP which outlined how to remove the registry entries which were stopping recognition of the cd/dvd reader but then itunes cannot find the reader.

    Thanks for pointing that out, it was not apparent on the day i used them and wrote the How-To. The links have been replaced with the SID# (Solution ID #) and the title given for the Article.
    Have fun

  • Can anyone explain how to post the manual entries in BCS?

    Hi All,
    Can anyone explain how to post the manual entries in BCS?

    Dear,
    Depands on posting level.
    There is Manual Posting  under Consolidation Functions.
    Please creat document and task.
    Next you add this task for consolidation monitor. There is "Consolidation Monitor " and you choose Hierarchy task and add your task for manul data.
    In document you kind in mind: choose manula posting !!!!!!!!!!!!!!!!!!!!!  in page tab Propertis under Posting!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!.
    If you would like to entry in posting level 01 or 10, please choose Local currency and trasaction currency +- group currency.
    If you would like to entry in posting level 20 or 30, please choose Group currency.
    In SEM_BCS are posting level is very important. 
    Regards,
    anka

  • How to make the manual entry of cost center in MIRO

    Hi
    In MIRO, Cost center field is not populating for the PO without material and with the account assignment project P. I want the cost center to be populated in the MIRO screen.
    In OLMRLIST screen cost center tab is not fixed. Once the cost center populates in the MIRO i can fix it.
    Please let me know the detailed procedure of how to make the manual entry of the cost center in MIRO?
    Raja

    Hi,
    If the PO is Account assigned PO then in MIRO you need to select the Layout as Account assigned -Costcentre, the system will change the Layout of the MIRO.
    So on the line item of MIRO you will find the Account assignment arrow mark (just move rightside of the MIRO line item) press this arrow mark,
    then system will take to other screen where you can enter the Manual entery to the Cost centre along with G/L account in MIRO
    hope this solves your problem. To enter the cost manually you need to select the Layout as Account assignment -- Cost centre.
    rgds
    Chidanand

  • How to remove the 'New Entry' button in the warning message for a dialog bo

    Hi Experts,
    I am calling a Modal Dialog box screen having a pushbutton.
    On the click of the pushbutton, I am performing some checks, and giving a warning message.
    The warning message comes as a popup in this case and has three buttons on it.
    One of these buttons is titled 'New entry'.
    I dont want that button to come on the warning popup.
    Please let me know if there is a way out for this.
    Thanks in advance.
    Useful answers will surely be rewarded.
    Regards,
    Himanshu

    Hi Jyothi,
    Thanks a lot for ur prompt reply.
    But, in my dialog screen, on click of the button I am simply using the statement :
    MESSAGE W000(0K) with 'text'.
    The resulting warning message comes as a popup with the 'New Entry' button on it.
    From the warning popup, how can I remove the button.
    Please let me know.
    Thanks.
    Regards,
    Himanshu

  • How to delete the unwanted entries directly from the UWL of MSS

    Hi experts
    I see an unwanted item stuck in WL of approver but not in his
    inbox how can i delete this entry form UWL,ihave tried refreshing UWL but the problem still persists please explain.
    when trying in the dev system
    *I actually applied leave from a test user
    his manager is able to view this workitem in his inbox
    then went into the background SAP and manually completed the workflow
    now if i go to the managers inbox i dont see it there
    but i still see it in UWL
    Could there be any reason for this,Please advice*
    Thanks in advance for your anticipated cooperation

    Hello,
    It is not easily possible to delete the workitems from UWL in MSS except using Batch program in backend ECC.
    Check again in the ECC, the workflow is got trigered and there is surely workitem in the manager's SAP Inbox. Check the tcode swia, enter the workflow task number and the workflow is got triggerred.
    Use swi5 tcode to see the Completed Workitems and to be completed workitems for that Employe (manager).
    The other reason could be.....somebody might hv executed this wf item, but still lying in UWL lists in  MSS.
    Try to re-register the system using UWL Wokflow Administrator in System Administration.
    Hope this helps.
    Regards,
    Anil Kumar.

  • How to remove the older entries of backup sets in windows server

    Hi guyz, 
    we are using windows server backup feature.. and we are backing up files and folders to remote shared location.
    the problem that we are facing is that, we run this backup every day using a script to new folder (folder name=datemonthyear) , and after each 30 days we start deleting the oldest entry from the shared location
    so its similar to the retention days feature of the dpm.
    but the problem is that even though we delete the actual backed up folder from the shared location, its entry is still there and we can see that when we type Get-WBBackupSet
    can any one tell me how to delete this entry whenever we delete the folder...
    plz help me guyz.

    Hi,
    We can use "wbadmin delete systemstatebackup" command line to delete old versions. If the backup storage location is full, Windows Server Backup automatically deletes the oldest backup version and only the latest backup will be available.
    For more detailed information, please refer to the links below:
    Wbadmin delete systemstatebackup
    http://technet.microsoft.com/en-us/library/cc742081.aspx
    How a can delete old versions
    http://social.technet.microsoft.com/Forums/windowsserver/en-US/62488e7a-4638-430c-950c-e75ac42b0fa3/how-a-can-delete-old-versions?forum=windowsbackup
    how to delete backups from a network share when it is full - Windows 2008R2
    http://social.technet.microsoft.com/Forums/windowsserver/en-US/9562ece3-2c6c-474a-aa44-d293eadbf536/how-to-delete-backups-from-a-network-share-when-it-is-full-windows-2008r2
    Regards,
    We
    are trying to better understand customer views on social support experience, so your participation in this
    interview project would be greatly appreciated if you have time.
    Thanks for helping make community forums a great place.

  • How to populate the Ser Entry ext key into the Doc Head text in ML81N Txn??

    Hello all,
    My requirement is to to populate the Service Entry external key into the Document Header text.
    ( ServiceEntry - ERS Invoice (MRRL) ). through ML81N Transaction.I have checked for exits in ML81N as well as MIRO. those doesn't seem very convincing.
    IF i see the field of Document header text where i need to populate the data it is
    ( BKPF-BKTXT ) how do i populate the data ( SE external field ) which is in ESSR table..?
    if any one has some piece of code please send it across.
    this is urgent pls help...........
    Any pointers for this would be highly appreciated.
    Thanks,
    Sreekanth...

    Please close this thread.Open new thread in forum [SAP Community Network Forums » ABAP Development » ABAP, General |;

  • How to link the variable entry with the planning function execution

    Hi All,
    I am new to IP , we have a requirement where the user enters the value 2008 for a variable year. Then we are supposed to copy the same combinations for the next four years against which the user will be able to input the key figure values. But i have only 2008 data in the cube, so i need to generate new records for the same characteristic combinations as present for 2008 for the next four years. I am planning to use a copy function for this but how can i trigger this planning function once the user enters the value for the year variable. I want the planning function to get executed once the user clicks OK after the variable entry. Request your valuable inputs on the same.

    Hi Tilak,
    for this u have an option of executing the planning sequence when the web template loads ie. after the variable screen.
    open the WAD.
    go to the properties of Web Template web item. Under the section standard action of the webtemplate, we have a n option to include planning functions under action before rendering.
    If u include your planning sequence in this this will get executed every time the layout loads.
    guess this is usefull to u.
    Regards.
    Shafi.

  • How to see the table entries after creating the tansaction XD01

    I creat customer initial screen through Transaction XD01.
    After creating customer initial screen how can i see the yable entries.

    Hi,
    The customer entries are stored in table KNA1.
    Regards,
    Himanshu

  • How to treat the accounting entries for the Process industry?

    Hi SAP Gurus,
    I am working with the Process industry client. Here one raw material goes with chain of process. In one plant half of the process will carried out and the rest of the half process would be carried in another plant. the entire accounting entry would be as follow.
    Plat A
    While Purchasing the RAW material the account entries are
    Raw material Inventory A a/c     Dr
         To GR/IR a/c                Cr
    While issuing material to process order
    Consumption  a/c      Dr
         To Raw material A inventory   A/c      Cr
    While the FG receipt into the stock
    FG B inventory      a/c     Dr
         To COGM   a/c      Cr
    Stock Transfer from Plant A to Plant B
    Goods issue from Plant A
    Goods in Transit   a/c        Dr
    To FG B inventory      a/c     Cr
    Plant B
    Goods Receipt at Plant B
    FG B inventory a/c      Dr
         To Goods in Transit a/c      Cr
    While issuing Goods to process order
    Consumption a/c      Dr
         To FG B inventory a/c     Cr     
    While Final FG receipt
    FG C  inventory a/c Dr
         To COGM a/c          Cr
    In this case mine consumption account gets hitted two times. One at Plant A and another at Plant B. So in my P&L account the consumption will be in two times. In this case how should i treat the accounting entry??
    Advance thanks for the help.
    Regards,
    Deva

    Hi Ravi,
    I have discussed with my user. The business requirement is they want the plant wise Balancesheet and Financial statement. If i do the stock transfer from one plant to another it is very difficult for me to get the balance sheet. What we are planning is while transfering one plant to another the FG invertory credit agaist Intra transfer account (One P&L account) then in the receiving end the intra transfer a/c debit to FG inventory so that i can get the trial balance.
    I will get back to you once i get the solution for this. Let me know if you have some idea on this.
    Thank you.
    Deva.

Maybe you are looking for