How to create a manufactured component in a production order network

Hi,
I've been facing problems to create a subnetwork in a production order. I want to add a manufactured component at a production order network.
Does anyone know any BAPI or FM to solve this problem?
Thks,

I tried to use the below FM sequence, but I just create no-manufactured compenents. However this tried was failed too, becaus a couple of fields was missing when I go to CO02 transaction.
CO_XT_COMPONENT_ADD
CO_XT_ORDER_PREPARE_COMMIT

Similar Messages

  • How to Create a Table Component Dynamically based on the Need

    Hello all,
    I have a problem i need to create dynamically tables based on the no of records in the database. How can i create the table object using java code.
    Please help.

    Winston's blog will probably be helpful:
    How to create a table component dynamically:
    http://blogs.sun.com/roller/page/winston?entry=creating_dynamic_table
    Adding components to a dynamically created table
    http://blogs.sun.com/roller/page/winston?entry=dynamic_button_table
    Lark
    Creator Team

  • How to create a new component using SPICE?

    People, I don't know how to create a new component using SPICE.
    I know that it's possible to create a new component and use a SPICE code, but I don't know how to do this very well, and I need the TI ISO124 (Isolation Amplifier), and I have no idea on how to do that. Can somebody help me? I need to develop a layout.
    Thank you!!

    Hi,
    Here is a tutorial that explains in details how to create your own component in Multisim using a SPICE model.
    Hope you find it helpful,
    Mahmoud W
    National Instruments

  • How to create  Auto suggestion component by using of ADF tag

    Hi ,
    In my project, I am using the ADF frame work and I need to use the auto suggestion component.
    Can any body suggest me how to create Auto suggestion component by using of ADF tag.
    Waiting for your valuable suggestions...

    Try this forum:
    JDeveloper and ADF
    You might get a lot more response.
    Jan Kettenis

  • How to create Re-usable component ???

    Is there any tutorials, on how to create Re-usable component ???
    Thanks

    Hi,
    Reusable component is the one which could be used in another component. This can be done through the concept of component usage. Refer this article[Component Usage|https://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/2e71ce83-0b01-0010-11a4-98c28a33195f].
    I hope it helps.
    Regards
    Arjun

  • How to create a table component dynamically in netbeans 6.0 (JSF 1.2)?

    How to create a table component dynamically in netbeans 6.0 (JSF 1.2)?
    This example http://developers.sun.com/jscreator/reference/techart/2/createTableDynamically.html works only with JSF 1.1.

    Please help my write correct code.
    How to replace this strings for run example?
    rowGroup.setValueBinding("sourceData", getApplication().createValueBinding("#{Page1.tripDataProvider}"));
    staticText1.setValueBinding("text", getApplication().createValueBinding("#{currentRow.value['TRIP.TRIPID']}"));

  • How to create a Templates for Categories and Products In BCC

    Hi All,
    Could you please tell me How to create a Templates for Categories and Products In BCC and how Can I get those Templates details(Categories and Products)in jsp
    If possible can any one send the document or where we find in atg docs
    Regards,

    At product/category/sku level there is a property called template.
    Find the property in ACC/BCC and provide all the values including the URL property.
    In you jsp, you can use this property from product/sku like the way you retrieve any other property from sku/product.
    <dsp:valueof param="product.template.URL" />
    Using that property with <dsp:include> includes that page.
    Peace
    Shaik

  • How to create a record for table PLAF with order type 'NB'.

    How to create a record for table PLAF with order type 'NB'(standard purchase order).
    who can tell me the T-code or some usefull information?
    Thanks.

    Hi
    This will be updated automatically when generate planned orders thru MRP. (MD02)
    regards
    Srinivas

  • How to create Extra Freight Unit for LCL Forwarding Order in Web Version of SAP?

    Hi,
    Can anyone please tell me how to create Extra Freight Unit in LCL Forwarding Order. Normally, each LCL Forwarding Order has one Freight Unit. But, if there are two types of Dangerous Goods and need to be transported via separate containers. Obviously, it should have separate Freight Unit to be created in the system. But, even adding package in Items Tab, unable to create Freight Unit for LCL order. Is there any other way to create Extra Freght Unit?

    Hi Aaron,
    When the FWO saving, it would build the freight unit auotmatically.
    The filed "Document Type" in FUBR is used to specify the FU type.
    So the FWO build the FU base on the FUBR which maintain in the FWO type.
    Useful link for FUBR :
    http://help.sap.com/saphelp_tm80/helpdata/en/5a/6749c4614f46e2a12160c775ff19de/frameset.htm
    Best Regards
    Clark Huang

  • Scrap Quantity component  in the production order

    Dear gurus,
    in the material master of a component i insert the scrap % ( view mrp4) = 10 %.
    The field is read by planning Mrp and explosion of bom , but when i inseert this component in the production order manually the system don't read this % and the field "scrap quantity in the component detail of the production order is blank.
    Are there a setting for uograde this field ( in the production order ) when i insert MANUALLY the component in the production order?
    Example:
    1) material master of the component  > scrap % (view MRP4 ) = 10 %
    2) production order created
    3) insert this component quantity 100 pc and the system after read the material master  insert 110 pc , and upgrade the field automatically 10 % (as material master)?
    Thansk a lot
    Daniele Pistilli
    PP TEAM

    Hi Danielepistilli,
    Well there is a lot of difference is there: see you are creating production order for header material which is FG. If you maintained component scrap in material level it will be dependent on BOM quantity which you maintained for the header material.
    For example say component x quantity is 50 in BOM. How it will calculate when you run the MRP.
    component scrap % is 5% then:
                                     ===>            (5/100) * 50 + 50
    Formula is: Percentage of scrap quantity x original quantity + original quantity
      So                           ===>           52.5 quantity should be come for component
    So, the order quantity for the header material will not take this quantity or scrap but if you see individually in MD04 screen for X material you can find this quantity ok.
    I hope it clears your doubt and helps you any queries please revert me back.
    Regards,
    Madhu.G

  • Component addition in Production order.

    Iam doing Sales order Mrp. After that planned order is converted into production order.
    Bom components appear in pegged requirements.
    In production order change mode I delete some components and refresh MD04. Components disappear from pegged requirement. It is ok
    Now In production order change mode I add some components and refresh MD04. Components does not appear in pegged requirement.
    I do MRP again but Components does not appear in pegged requirement.
    How to get components in Pegged requirement list??

    Hi,
    Why requirement for new component does not get added when MD50 is carriied out??
    While running MRP using T-code MD50, The system will explode BOM and it will do the net reqmt calculations. Since the newly added component is not part of the BOM, that is the reason it is not considered.
    After doing Plant level MRP requirement for that component gets generated but it does not appear in pegged requirement of header material??
    When you add the component in the production order, it will create the reservation. In the next MRP run only this reservation will be considered and it will plan.
    Regards,
    V. Suresh

  • Component quantity in production order

    Hi,
    For my finished product component quantity in BOM is 1.386 for the base quantity 100.When am creating the production order for 100 in my component overview of  production order screen it is showing component quanitity as 2 instead of 1.386.
    Since am not using any rounding value,rounding profile and scrap nad upto 3 decimals allowed in CUNI for particular UOM.
    Thanks
    P.Srinivasan
    Edited by: srinivasan ponnurangam on Dec 23, 2011 12:33 AM
    Edited by: srinivasan ponnurangam on Dec 23, 2011 12:35 AM

    As I understand even if production order screen it is showing component quanitity as 2 instead of 1.386 ,Internally it is stored as 1.386 only.
    So as per knowledge it should not affect anything.
    Refer Note 931971 - Decimal places in stocks and stock postings
    Also refer
    Problem with item/component quantity in BOM

  • How to collective read PP master data in Production order?

    Hi: Guys
    Please tell me how to collective read PP master data in production orders. in COHV, I can find out some collective functions but read PP master data.
    Thanks
    Henry

    Read PP master data is only to update routing and BOM in production order if it is already created to effect the changesmade in routing and BOM.    I think in that collective option is not possible.  
    Regards
    KrishnamurthyDSS

  • To issue the component to the Production Order

    Hello All,
    I have assigned the component to the Operation of Production Order from Different plant(say 1100) of Same company code(1000).
    I want to issue that material from that plant to this plant (say 1000) of Production Order.
      So my question is the correct method of directly issuing the component to this Production Order of different plant.
    Shailendra

    Hi  HAdkar
    The correct procedure is .
    You have to assign special procurement key 80 in material master for which you want to procure from plant 1100. The material master of procuring material should exist for the plant 1100. While running MPR the procurement proposal will be automatically created in the 1100 plant. From 1100 plant you do stock transfer to your storage location. Then finally do GI for the header prod order in you plant.
    This is the procure in SAP. Eventhough both the plants exist in the same compound.
    Regards
    J . Saravan

  • How do I insert a document in a production order?

    Hi
    Does anyone know how I can insert a document in a production order on the "Document Links"?
    I have a assembly drawing that I would like to be printed on release.

    Hi,
    As rightly said you can have the documents or document links in material master or in BOM. But if you prefer to have the documents attached to Document links in production order, you can assign those documents to the operation of production order and remember to maintain the document link activated for production order (PORDER) for the document type.
    Thanks.

Maybe you are looking for