Hi,
I have a production order for that I need to purchase 2 materials. but my problem is when the material come there is no reservation for my production order. someone can take it for another production order. How can I do that the system create a  reservation after the GR
Thank

Dear,
When you create and release production order, the reservation is created for that order. Now you should first activate the Avelability check in production order.
It is PP configuration
Then you need to activate dynamic aveailability check in goods issue in MM configuration.
Hence if the stock is reserved for your production order, then no one can issue and system will give error message.
please come back if required.

Similar Messages

  • How to create  the BOM for co product

    Dear friends,
    How to create the BOM for Co product  and How the production will create and  how the costing will capture for that.
    Regards,
    Sabhapathy R

    Dear Umesh,
    How Bom created for co product
    By product
    Header
    xxx
    101
    mvt
    mvt
    qty
    item
    yyy
    261
    1
    zzz
    531
    0.5-
    By product
    Same way how we create co product for BOM. pl explain with simple example.
    Thanks &regards,
    Sabhapathy R

  • Open the reservation for the Production order

    Hi,
    I have post the GI for Production order MB1A with movement type 261 from 100 peaces components. I would like to cancel a partial quantity of components from this posting (about 30 peaces). After cancel it the reservation for the production order has to be open for 30 peaces of components.
    I've canceled it through MB1A and mtype 262 but the reservations weren't open and in the PO (component overview there is always the sign"the Final Issue for This Reservation").
    Which T.code and mtype could I use.
    Thanks
    Dede

    Hi,
    Have you cancelled the movement (of 30 pieces) by selecting the "with reference" option from the menu?
    If not, then reverse the current cancellation document. Then again cancel the 261 movemtn by selecting the with refernce button from the menu. It will sove the problem.
    Check & revert.
    Regards,
    Rohit.

  • How to create a PR for each Maintenance Order

    Dear All,
    Please guide me how to create a PR for each Maintenance Order.
    I test on Ides, I have some Maintenance Orders, all of them require the same stock material. When I run MRP, system always create one PR for all requirements. I don't know how to change.
    Regards,
    QuangDD

    Hi,
    As you planning for Stock Items, by running MRP, system will create single PR only. If it is non stock items, then it would be possible to create different PR based on Orders.
    Regards,
    Maheswaran.

  • How to create an Invoice for the sales order using the T-Code VF01

    Hello Experts,
    How to create an Invoice for a sales order using the T-Code VF01?
    Thanks in advace,
    Suma

    hi,
    Make the following settings-
    1. Create sales document and billing type
    2. assign billing type in sales document type config VOV8
    3. Activate itemcategory as sales order related billing
    4. Maintain copy control header and item level between sales order and billing
    5. Maintain pricing procedure for sales order and billing
    6. Define Output procedure in case to print invoice
    Regards
    Goutham

  • How  to create one delivery for two sales orders?

    Hi Experts,
    I need to create one delivery for two sales orders. But it fails.
    The route, shipping point, ship to party are same for both orders but INCOTERMS are different.
    Delivery date, Good issue date, loading date,material availability date, transportation planning date for 1st order is 12/07/11 and for second order is 14/07/11.
    I have created delivery on 14/07/2011 but the delivery is created for 1st order only, the second order is missing in the delivery.
    It not happened because of incorterms.? different dates
    Kindly help regarding this.
    Thanks
    Raghu

    Hi
    To understand splitting behavior, see SAP Note 546668 - FAQ: Delivery split when creating deliveries. And yes, incoterms happens.
    I think that with the help of question 6 you can try to force the merging of SO. Then, see SAP Note 166397 - Delivery split according to customer field ZUKRL, and handling the field ZUKRL in a VOFM in the copy rule I think that you can try to do it.
    Finally See  Note 4505 - Duprec when adding delivery (VL04, VL01, VL10*) to avoid problems while you are merging.
    Regards
    Eduardo

  • How to create one delivery for multiple sales order

    Hi!! Friends,
    Can some one explain the steps to be followed in creating one delivery for multiple sales order in SAP SD.
    Regards
    AKASH
    Message was edited by:
            AKASH TAMBI

    Hi.,
                  You can combine different orders in to one delivery ,But for the customer Order combination should be checked in  the sales area data of the shipping tab,we can combine orders but the ship to party,Route,Inco terms,Shipping date,shipping point should be same,you can do in T.code VL04 & VL10
    REWARD if helpfull
    Thanks & Regards
    Narayana

  • How to create a silo for a product on a website with natural shadow?

    I have 15 images that are shot on a white background and need to create a silo that has a transparent background but includes a natural shadow.
    I'd also like to create an action for it.

    I don't know what you mean by "silo", but just in general...
    Use transparency in your Photoshop design, use e.g., a Drop Shadow  layer style, and save your image as a PNG-24 file, which supports 24 bit color and partial transparency.  All the modern web browsers will render PNG files with transparency.
    Look over this page as a quick and simple example:
    http://Noel.ProDigitalSoftware.com/temp/TransparencyTest/TransparencyTest.html
    -Noel

  • How to create true Procurement Document and production order instead of PO

    Hello - I have learned how to make purchase orders from out the sales order, but it only generates PO's but some items are produced in our factories. So I don't need a PO for surtent items but Production orders. How can I do this?
    Thanks in advance.

    Hello Gordon, tha is working perfect now I finaly get the forecasted items in my MRP window If I click on show recommendations I see he recommends he wants to order some pcs, and Indd what I split in to Buy or Make is separated in an Production order. But how do I change the recommendations into orders?

  • Multiple batches for a production order and mapping with components

    Hello Gurus,
    Our business requires to create multiple batches for one production order + they want to trace which component in the production order has been issued to the main equipment.
    For example, I am creating production order for 'A' equipment for 4 qty. Business wants to create 4 different batches for these equipment
    Lets say now 4 batches are created A001, A002, A003 and A004.
    Now lets assume 2 nos of 'B' component are required for 1no of 'A' component. So the requirement of B component is 8.
    Lets say 8 batches are generated B001, B002 ......B008
    Now lets say batch B001 and B002 are issued for A001 and packed together. How do we map this?
    I understand we can do some enhancement for creating the multiple batches but I still dont know how to map them with each other.
    Please help

    Hi Ethan
    There is a functionality called WIP batches, that allows you keep the batch traceability within an order.
    With WIO batches you can track which batch of component was used to produce each batch of finished product.
    See this link for more details:
    Work-in-Process (WIP) Batch - SAP Library
    BR
    Caetano

  • Accounting Document for a Production Order

    Hi,
    How to get Accounting Document for a Production Order?
    Please help.
    Thanks,
    Shiva

    Hi Shiva,
    Go to table bseg....
    retrieve belnr -
    > accounting document number
    for a particular aufnr-----> production order
    where bukrs = your company code.
    Regards
    Debarshi

  • Target cost for a Production order

    Hi
       How to get Target Cost for a production order?
    Thanks
    Naga

    Well Naga, Right now I’m on HR implementation , but I programmed same kind of requirement two years before , but I got planned cost and actual cost .
    I also notice “cost analysis" the cost is not exact , it wont read the value from KP26 of that particular month .
    Here I am talking about 4.5b system.
    You can find the sales order ref on production order, and your production order is made up of your different kind of material like scarp, raw, semi-finished etc
    Here are the steps I followed .
    1- I read the material which you can see in material component on production order in Co03.
    After that I take the qty and also multiply by the cost at which machine is posted .
    I have that programs, as I need to find out . I’ll post you later .
    But you have to read the tables afko,afpo,afru,caufv,cost ..etc
    Do you see information structure I refer you , If i am not wrong this CO3 ( cost analysis ) report use report painter ( Tr.Gr51,Gr52 ) . you can also see by going in to said transaction which information structure its populating . This’ll also help you.
    Hope this’ll give you idea!!
    <b>P.S award the points.!!! DOn`t forget :)!!!!</b>
    Good luck
    Thanks
    Saquib Khan
    "Knowledge comes but wisdom lingers!!"
    "Some are wise and some are otherwise"

  • How to create a Templates for Categories and Products In BCC

    Hi All,
    Could you please tell me How to create a Templates for Categories and Products In BCC and how Can I get those Templates details(Categories and Products)in jsp
    If possible can any one send the document or where we find in atg docs
    Regards,

    At product/category/sku level there is a property called template.
    Find the property in ACC/BCC and provide all the values including the URL property.
    In you jsp, you can use this property from product/sku like the way you retrieve any other property from sku/product.
    <dsp:valueof param="product.template.URL" />
    Using that property with <dsp:include> includes that page.
    Peace
    Shaik

  • How to create "Dependent reservation"?

    Hi,
    Could you tell me how to create "Dependent reservation", please? Thanks in advance.
    PS: the MRP element of  the record shows "OrdRes" in MD04 screen.
    Best regards
    Lily

    Hi,
    When you create Production order for Parent  material (CO01) , dependent reservation will be created for Components automatically. If u select the Dep reservation it will show the  Parent material production Order Number( Pegged requirement) (Md04).
    or U  can create reservation manually  at MB21
    Pradeep

  • How to create a macro for a planning type in MC8b transaction

    Hi,
    I am presently working for a product allocation demand, which have a information structiure with characteristic and key field.
    the characteristic are production allocation quantity, incoming order quantity, and open order quantity.
    i have created a planning type in which the data updation takes from the excel file to the planning type in mc95.
    but i need to create a macro for this planning type .
    can any body give the details information how to create a Macro for a planning type.
    Thanks and regards
    GopalKrishna

    Dear Gopal
    May be the link would be helpful to you.
    [Planning Types and Macros|http://help.sap.com/saphelp_46c/helpdata/en/a5/631cc443a211d189410000e829fbbd/frameset.htm]
    Drill down the left tab once you opened the link, for more information.
    Thanks
    G. Lakshmipathi

Maybe you are looking for

  • Open Prodaction orders

    Hi sap gurus, I am chaining Material type.its showing Some Open Prodaction orders.But its not open Prodaction orders its completed orders.plz tell me why its showing open orders.how can i overview these problem

  • How can I use Text-Elements in Dynpro Buttons ?

    Hello Experts, I have create a dynpro screen with the screen-painter. In this screen have a button, in which label i want to use defined textelements. This has the advantage that i can expand it to other languages. The screen is an standard screen. I

  • Installing 8.1.6 on RH6.2 via remote X client - Problems

    I've installed 8.1.5 quite a few times in the past without any problems. However, when trying to install 8.1.6 on a freshly installed RH6.2 system, I get a ton of what look like possible JRE errors and warnings. My RH6.2 system is just a server, so t

  • Wacom Intuos 2 lives to see another OSx (10.9.2) upgrade!

    Re: installing Wacom Intuos 2 on OSX 10.9.2. Wacom Intuos 2 lives to see another OS upgrade! I upgaded to a iMac 27"  Intel Core i7 from a wonderful iMac circa 2005 running OSX 10.6, but woefully underpowered After unsuccessfully attempting to instal

  • Toshiba TS-L632H don't working correctly

    CD/DVD-Rom Toshiba TS-L632H don't read burned cd/dvd's and don't recognize virgin cd/dvd's, only read original cd/dvd's. What's the problem?