Hello friends,
I need help to map below scenario in SAP:
We have third party business process, where vendor V1 is supplying material to customer. When customer receives material; V1 invoices us and we make payments to V1.At this point PO is closed for vendor V1.
Now if customer faces any problem with material, then we call local vendor V2 to repair or service the material. What ever charges come from local vendor is suppose to reimburse by vendor V1.
Now how can we link V2 vendor invoice amount to V1 invoice. What will be the document flow? How to map back charge process . 
Note:
We have considered adding negative line items to the existing PO but understand this is not possible once payment has been issued and the PO is closed.
We have considered creating a u201Creverse sales orderu201D but do not want to create a separate order or handle the vendor under a separate sold-to account (as a customer)
We have considered a manual FI invoice but do not want to handle the vendor under a separate sold-to account (as a customer)
Seeking valuable inputs from experts.
Regards
Ravi

Hi Raghavendra
Yes V2 exist in SAP, right now we create new purchase order to V2 for services for material at customer location, after his service we do payment to V2 and same amount is charged to V1.
While charging V1 , we need to treat V1 as a customer( sold to party ) , which we donu2019t want , and direct clearing from FI is also not fusible as we again need to treat V1 as customer ( sold to party ) .
Our requirement is to map using some credit memo or debit memo or any other documents.
regards
Ravi

Similar Messages

  • How to map expdp parallele process to output file

    How to map expdp parallel process to its output file while running...
    say i use expdp dumpfile=test_%U.dmp parallel=5 ..
    Each parallele process writing to its related output file.. i want to know the mapping in run time...

    I'm not sure if this information is reported in the status command but it's worth a shot. You can get to the status command 2 ways:
    if you are running a datapump job from a terminal window, then while it is running, type ctl-c and you will get the datapump prompt. Either IMPORT> or EXPORT>
    IMPORT> status
    If you type status, it will tell you a bunch of information about the job and then each process. It may have dumpfile information in there.
    If you run it interactively, then you need to attach to the job. To do this, you need to know the job name. If you don't know, you can look at sys.dba_datapump_jobs if prived, or sys.user_datapump_jobs if not prived. You will see a job name and a schema name. Once you have that, you can:
    expdp user/password attach=schema.job_name
    This will bring you to the EXPORT>/iMPORT> prompt. Type status there.
    Like I said, I'm not sure if file name information is specified, but it might be. If it is not there, then I don't know of any other way to get it.
    Dean

  • How to map consignment stockist process

    Dear Gurus
    My client is doing business trading business he is acted as  consignment stockist for IOCL company. IOCL has given a enterprise portal to do this business. My client sending purchase indent through this enterprise portal. IOCL send the goods to my client go down, the maintenance fee and everything is paying by IOCL . My client selling goods to the customer and delivering products from our godown. The customer is paying to my client with some different terms of payment. My client paying amount to the IOCL within 48 hours through bank or direct payment. But purchase sales order, delivery, and billing is done by IOCL. IOCL sends the invoice to our client through enterprise portal. Then my client send the goods to the customer from our godown based on the Invoice generated in enterprise portal. How to map this business in my client sap system.
    Regards
    Thiruapthi
    Edited by: gopathi3 on Jan 27, 2012 6:42 PM

    Hi Raghavendra
    Yes V2 exist in SAP, right now we create new purchase order to V2 for services for material at customer location, after his service we do payment to V2 and same amount is charged to V1.
    While charging V1 , we need to treat V1 as a customer( sold to party ) , which we donu2019t want , and direct clearing from FI is also not fusible as we again need to treat V1 as customer ( sold to party ) .
    Our requirement is to map using some credit memo or debit memo or any other documents.
    regards
    Ravi

  • How to map sales return process from customer to mfg plant without Depot??

    Dear All
    we have a Mfg plant (mfg1) & having  seven Depot.
    regular process of STO DEPOT process
    ME21N-Purchase order STO
    VL10B - Replenishment delivery
    VL02N - PGI
    VF01- Proforma invoice
    J1IIN - Excise invoice
    MIGO - Goods Receipt
    J1IG - Excise Capture
    VA01 - sale order
    VL01N - Out bond Delivery
    J1IJ - Excise invoice
    VF01 - commercial invoice.
    J1IDEPOTSTOCK - RG23D Report.
    In Case of rejection the Sales Return is directly delivered from customer to 
    manufacturing Plant,In this process depot is not directly  billed. The transaction is
    done between customer to manufacturing plant.our question is how to MAP above scenario in sap
    (currently all this activity is done in excel sheet ) please suggest any proper method....
    Regards
    Sachin

    Hi Laksmipati,
    Thanks for your reply, however one of my clients requirment is that the returns delivery will be made directly to the mfg plant and not to the depot plant. In this case the excise calculation is going HAYWAYAA......I understand that it will make sense if the returns is 1st made to the depot and then to the mgf plant. The system wont allow me to do a returns with refernece to the invoice since it has been made from the depot to the plant. Also this will create a problem while doing A PGR. I will be grateful if you could comment on the same.
    Thanks
    Sachin

  • How to do Back Order Processing?

    Hi Murthy here,
    Can some1 please give me an overiew of BackOrder Processing settings process. The funda clear bt please brief about how 's it done?

    Please make a search in the forum before posting such repeated questions.  This question has been answered many times and to cite an example, check the following threads
    [BackOrder processing in SD   |Re: BackOrder processing in SD]
    [Reagarding Back order Processing   |Re: Reagarding Back order Processing]
    [Backorder processing in Scheduling agreement   |Backorder processing in Scheduling agreement]
    thanks
    G. Lakshmipathi

  • How to map Self consumption process in SD

    Hi All,
    I have a scenario where i need to map self consumption process through SD.
    The requirement is as follows:
    The FG manufactured (cement) has to be internally issued to plant for building, maintenance work, etc.
    So when the goods are issued then inventory credited and consumption debited
    Please let me know whether there is a standard process in SAP to map this.

    Hi
    This scenario is not sales/SD related, but rather is an Purchasing/MM related.
    One scenario is you issue (goods issue) the FG through Tcode MB1A and novement type 201 (if you want to issue to Cost center), mvt type 221 (if you want to issue to Project)...
    If you alreday have maintained the Building as a project, then you should issue against this project.
    In this case, the stock account will be credited and the consumption account is debited.
    Regards
    Sidi

  • How to map Lubricant reclamation process

    We use Refurbishment Order for Repair of Spare Parts.
    But we have a scenerio where Used lubricant is reclaimed. During this process the volume reduces drastically.
    How this can be mapped in SAP? Whether this goes out of maintenance and enters production jurisdiction?
    Experts in this field may kindly suggest.
    Regards
    Jogeswara Rao

    Process is same as described in the question. This question has already been marked answered .
    Please follw the link Please suggest a maintenance tool for a scenerio
    Regards
    Jogeswara Rao

  • How to kill back ground processes?

    I had installed Amonitor app and it shows there are these 3 processes, poc-bbot, bash, cp running. It was never there. can anyone tell me how to kill it?

    Hi, thanks.
    Actually these 3 processes has never shows up. And yes, i was kill all the apps once i dont use them. my recently open bar is always empty.
    The reason why i has concern is my bat life is shorter when these 3 processes are running. It used to has this, so i restore to factory mode. then after awhile, these came back.

  • How to get back deleted Process chain?

    Could some one aid me in getting back the deleted process chain, in production?
    Thanks in advance....

    Hi..................
    It is not possible to get it back...........Since generally we don't create Pc in Production Server.......
    If it exist in you Development or Quality Server.............again transport it from there....
    Regards,
    Debjani..........

  • How to map the business process in account receivable

    Hi All,
    i am working on a different scenario can any body suggest me on this,
    Business process  my client is into service industry they will send Tenders to customer along with EMD amount,
    once they got the project they will coverts that amount into  securiy deposit,
    for example:
    EMD amount 1000000
    got the project that amount goes to security deposit 1000000,
    after work done they will rese invoice to that customer based on payment terms they will get money from customer,
    if they rise 50000  invoice he will be sending  48000 rupess only remaing 2000 will be keep it as security deposit
    and again they will rise 50000 he will be seding 48000 rupess only remaing 2000 will be keep it as secrity deposit once the project closed after six to eight month he will be sending that 4000 rupees.
    here my client want that 4000 should not be shown as open item.
    can any body suggest me how to do that in SAP
    kind regards
    kiran

    Hi Kiran
    As per the business scenario and the process in SAP, you are having only three options in clearing procudure as you may be aware.
    1) standard - bill to total payment
    2) partial - partial amount against invoice(Inovice and receipt will be in open item status)
    3) residual ( new open item will be generated)
    If they don't want to show the remaining 4,000 as open item in the customer account, how they want to treat in the books.
    create a seperate G/L security deposits receivables and transfer the amounts to the account. Whenver you receive the amount knock off the amount
    with regards
    Siva

  • Subcontracting how to receive back Un-Processed Material

    Dear Sir,
    We had created a PO for subcontracting and then transferred the input Material to vendor Stock in the PO reference and Subcontract Challan was made and Material was sent to Subcontractor .
    Now due to some problem with the Vendor , He has returned back the complete Material as it is ( Un-Processed) .
    Kindly guide us as what steps need to be followed to receive back the input Material and then Cancel / Completion of the Subcontract Challan .
    With Thanks and Rgds
    Sonia

    Hi,
    For eg: material sent to subcontract in 100pc and the subcontract supplied is 70pc then the vendor gets problem and returned the 30pc but the challan created is 100pc
    first receive the 70pc through migo and reconcile with that challan in J1IFQ.
    Now the challan has the balance qty is 30pc and in subcontract side also 30 pc.
    Now subcontract sends the material back so do 542 for 30pc against that vendor and reconcile with challan 30pc.
    In subcontract side the qty 30pc will be reduced and it will increase in your side 30pc
    now do J1if13 completion of challan.
    Asok.N

  • How to map this Business process

    Wanted to dispatch Goods thru Stock transfer from plant A to plant C which are in two different states. Further Plant C doesn't have unloding point hence the goods are unloaded at Plant B an intemediate location.
    For this presently one STO is created from plant A to Plant B and another STO from plant A to C. Goods are transferred thru delivery and movement types 641 to location B & C.
    Hence on system delivery is appering twice in stock transfer reports against plants B & C.
    How this procedure can be mapped in single transaction.
    anya

    any reply .

  • Back charges senario , how to map????

    Hello friends,
    I need help to map below scenario in SAP:
    We have third party business process, where vendor V1 is supplying material to customer. When customer receives material; V1 invoices us and we make payments to V1.At this point PO is closed for vendor V1.
    Now if customer faces any problem with material, then we call local vendor V2 to repair or service the material. What ever charges come from local vendor is suppose to reimburse by vendor V1.
    Now how can we link V2 vendor invoice amount to V1 invoice. What will be the document flow? How to map back charge process .
    Note:
    We have considered adding negative line items to the existing PO but understand this is not possible once payment has been issued and the PO is closed.
    We have considered creating a u201Creverse sales orderu201D but do not want to create a separate order or handle the vendor under a separate sold-to account (as a customer)
    We have considered a manual FI invoice but do not want to handle the vendor under a separate sold-to account (as a customer)
    Seeking valuable inputs from experts.
    Regards
    Ravi

    Hi,
    Option 1
    If you are using QM Module, you can create a notification (Customer Compliant, Vendor Compliant, Internal Problem so on) with reference to Material Document / Sales Order / Production Order so on.
    Option 2
    If V2 Vendor exclusively for V1 Vendor, then you can use Head Office and Branch Office concepts in Vendor Master.
    You can specify head office account number only for branch accounts. Materials that posts using the branch account number are automatically posted to the Head Office Account. The system records the branch account number in the line items.
    PS: Neither transactions nor balances are kept in the branch account.
    Option 3
    At the time of Logistics Invoice Verification, post to different Vendor (subject to your finance / accounts clerance)
    Bye,
    Muralidhara

  • Back charges scenario in SAP

    Hello friends,
    I need help to map below scenario in SAP:
    We have third party business process, where vendor V1 is supplying material to customer. When customer receives material; V1 invoices us and we make payments to V1.At this point PO is closed for vendor V1.
    Now if customer faces any problem with material, then we call local vendor V2 to repair or service the material. What ever charges come from local vendor is suppose to reimburse by vendor V1.
    Now how can we link V2 vendor invoice amount to V1 invoice. What will be the document flow? How to map back charge process .
    Note:
    We have considered adding negative line items to the existing PO but understand this is not possible once payment has been issued and the PO is closed.
    We have considered creating a u201Creverse sales orderu201D but do not want to create a separate order or handle the vendor under a separate sold-to account (as a customer)
    We have considered a manual FI invoice but do not want to handle the vendor under a separate sold-to account (as a customer)
    Seeking valuable inputs from experts.
    Regards
    Ravi

    Hi Ravi,
    Your scenario is similar to "warranty'.
    You should not charge-reduce- V1's bill against V2's bill.Rather it should be against the V1's open item;
    try " noted item" for V1's payment against V2's bill.This should solve your problem.
    Regards
    Ramesh

  • How to map business process and enterprise service?

    Recently, I read some documents about ESA. I'm confusing about the relationship between business process and enterprise service. In other word, how to map the business process to enterprise service after the business process is analyzed? Is there any methodology/rule to define business process and wrap them into service in ESA?

    Hi Sherry,
    I like to add some of my thoughts about that discussion. From my point of view ESA is much more than just another BPM or Enterprise BPM. ESA is adresses six key areas and I think all of them are really needed:
    - <b>People Productivity</b> as the word itself describes...it's about portals and productivity.
    - <b>Embedded Analytics</b> has to integrate transactional and analytical content.
    - <b>Service Composition</b> is used for model-driven service composition and services orchestration.
    - <b>Service Enablement</b> is about a Enterprise Services Repository filled with business meaningful Enterprise Services and service patterns for enabled objects. Excactly this is where SAP has years of experiences.
    - <b>Business Process Platform</b> is about service enablement of all application platform objects and engines. This is the place where "BPM" for core business processes resits.
    - <b>Life-Cycle Management</b> has to cover the deployment, configuration, operation and change management for ESA based processes.
    Therefore the term "BPM" is located in serveral layers of an ESA approach. On the level of <u>Business Process Platform</u> BPM is providing the choreography for core business preocesses.
    At <u>Service Enablement</u> BPM needs to compose out of granular services (I would say "atomic" services)
    buiness meaningful services (here we have "molecular" services).
    The third level where BPM could be used is <u>Service Composition</u> because exactly this is the place
    where serveral Enterprise Services could be combined to a process representation.
    To come back to the discussion:
    1. The question should be how to indentify business meaningful services which could represent single process steps. ATP check, Credit card check, ... could be examples. In theory this service could be out-tasked, defined more flexible etc. This means that processes needs to be evaluated for Enterprise Service candidates. Afterwards you can check against SAP's Enterprise Services Repository for already existing Enterprise Services. The evalution for enterprise services candidates will be supported by the metodology mentioned by Kaj and David.
    2. I think domains in this context should be motivated by business and/or functional areas. Depending on the granularity. For example Order Fulfilment Services, Master Data Services, Search Services... These kind of serices can be combined again to services such as "Search of Master Data" (Search Service + Read Master Data Service) etc. or can be used to generate UI to be used in a ESA application.
    Your thoughts?
    Very best regards
    Wulff

Maybe you are looking for

  • Lumia 800 synchrinize with outlook office 365

    Hi, I try to synchronize my lumia 800 with my account in Office 365. It seems that is synchronizing my contacts but in outlook contacts of office 365 I can't see them. Could someone help me?

  • Clearcase and Solaris 10/zones

    Hi All Any one installed Rational Clearcase on a node with zones. If so 1. If each zone requires clearcase access, should clearcase be installed per zone 2. Or can it be installed in the global zone once and the zones can get access to it. Your help

  • JMS Adapter binary conversion error

    I am getting an MQ message. The message has / embedded when it is picked by JMS Adapter. Because the message content has /, JMS is stripping the message. Is there anyway to get the whole message into XI from JMS without the message getting stripped.

  • Languages and keyboards

    I recently installed an English version of CS6 indesign. I live in a German speaking country, however, and my keyboard is German.  How can I set myself up to work in English but still be able to use the German keyboard shortcuts??

  • CPU utilization on Solaris

    When running a series of performance tests on Solaris machine running Weblogic 8.1sp2 and comparing the results to a Windows200 machine running Weblogic 8.1sp2 I noticed the Solaris box was only using 10% of the each of its 4 CPUs. The Window2k machi