How to release a collective production order in CO05N with MSPT?

The issue was: I want to release a collective order by co05n, e.g. the structure of this collective production order 10000 like this:
10000----20000
30000---40000
                             ---50000
if order 50000 with material shortage, keep the customizing OPJK  release order=3, how to release this collective
order. If it is not possible in standard, can the parallel order 40000 be released??
Thank you, all.
Edited by: Stephen Wang on Apr 15, 2010 3:12 PM

Dear,
In Transaction CO05N, you execute a collective release. For one of the orders, the availability check determines missing part although it has been set in Customizing of the availability check (OPJK) that a release can be executed for missing part per user decision. Therefore, a dialog box is processed on which options a.) 'Release order', b.) 'Missing parts list' and c.) 'Cancel' are displayed.
If you first branch to the missing parts list and then press 'Cancel' on the dialog box there it self
Else you can do this with these options,
1)Use T Code COHVOMRELEASE here select order as you want and release accordingly.
2) Use Transaction SE38 to create the variants for program PPIO_ENTRY and schedule it through SM36 or use standard variant as SAP&RELEASE if want in background.
3) use BAPI BAPI_PRODORD_RELEASE
Please try and come back.
Regards,
R.Brahmankar

Similar Messages

  • Query for releasing and closing Production order ststus in bulk

    Hi
    Releasing planed to released
    1. i want to release all those production orders entered in system which are in planned status.I want to apply one query for that which should change the status of Prod orders to release in systems automatically by applying this query.Please give me that suitable query and how to use it for proper result.
    closing released to planned
    2. Same like above i want to close all those Production orders whose receipt quantity is equal to planned quantity. i.e i want one query which should change the status of production order from release to closed on condition that receipt quantity is equal to the planned quantity.Please give me that suitable query and how to use it for proper result.
    Thanks

    For point 1 and 2:  It should not be tried and using a Query does not comply with SAP Support policy.  Doing so would lead you to lose SAP Support.

  • Collective production order---GR/GI problem

    Dear guru
    My scenerio is collective production order. I have created PUMP header material and 2 component in that component i have maintained 52 special procurment key . and automatically 3 production order are created .
    Now I want to create a stock of header material (PUMP) .
    Actually I tried through MB31 and I do GR of header material and stock is also created to this material .
    but my question is wht about chlid component ? that child component production order is still in MD04 .
    so how it will consume . or  have i made some mistake or tell me rt.  scenerio.of (GR/GI)?

    Dear,
    GR is done for Main order only and document also post for main order. This is standard SAP funcitionality.
    Confirmation is carried out same as normal Production order,
    If u do the confirmation for suborder in the collective structure - the automatic goodsmovements taken place between the production orders in collective structure.
    Since suborder materail is directly produced , when confirm the "suborder", the produced qty will issued automatically to "superior order".
    There is no seperate goods issue is needed for superior order in collective order structure.
    After confirming the suborder, u can confirm the superior order, and make GR for finished product.
    For above process "Collective order with goods movements" check box should be activated for Order type at OPJH
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Rounding value on collective production order

    Hi Guys,
    I want to use rounding value on collective production order, Rounding values do work on production order but not if the material has setup for collective. I do not want to discoonect the material from collective and i do want to use rounding value. Any body has an idea how to achieve that?? Any help be great!

    I have to say that the collective order join the MRP with the way of direct production which is completely different way of net requirement calculation. It just get the quantity from the superior order and can not be influenced by the rounding value/profile.
    The output from the sub level order will be consumed by the superior order directly without manual handling. So that the redundant quantity caused by roudning would cause inconsistency.
    The BADI WORKORDER_UPDATE is being called while creating and chaning the order, so you may check the possibility in it to change the order or component quantity.
    On MRP side, I can see there are BADIs MD_PLDORD_CHANGE & MD_PURREQ_CHANGE to allow the customer change the planned order and PR in MRP, however, you should better not change the quantity as no further BOM explosion occurs for the changed quantity, so there is no perfect solution for your question. Please go to SE18 to read the documentation of the BADIs and their methods to see if you can use them.

  • How to confirm the CO Production Order?

    Hi,all
    The PP Production Order can confirm by TCode CO15.
    Then how to confirm the CO Production Order(Created by KKF1)?

    Hi,
    As you are aware that Co Production Order is being used when there is no quantity structure. Hence, there shall be no routings with details of activities and the quantity of activities, etc and we cannot use confirmation as we are doing in regular Production Corder. Consequently,  we are left with one alternative of passing on the activity cost(qty x price) to the CO Production through Direct Activity Allocaiton(KB21N).
    Trust this helps much!
    Cheers!

  • Collective Production Order for ITEM hierarchy

    Hello All,
    I have a Sales Order , with ITEM 10 XYZ (which is text material (does not have MRP views))
    Below it ihave 2 items
    20 pqr
    30 abc
    Both are assigned as SUB items to higher level  item 10.
    Part 2.
    I now try to create a Production Order (co07),
    When we create a PO for a Given Sales Order it normally
    expands teh BOm item and creates a network of PO for Sub items. (Also allocating the Lead PO number under assignment Tab for child items).
    Unfortunely in this case it does not behave like that , as it is not a BOM item (i.e 10).
    If i want the same behaviour even in this case what all i need to do ..
    F1 Please!!
    Manohar

    HI ALL,
    HOW TO ASSIGN A SUB PRODUCTION ORDER TO AN EXISTING PRODUCTION ORDERß
    Vielen Danke!!
    Manohar

  • How to see cost componentwise production order actual cost-not planned cost

    Hi,
    Can anybody tell me how to see cost componentwise production order actual cost ?
    Thanks,
    Bijay

    Hi,
    CO03->Goto-> costs-> Anlysis
    or use the std. report KKBC_ORD
    std. reoprt MCRI
    KVBI - Actual Costs
    Regards,
    R.Brahmankar

  • Production Order Settlement Process with respect to  a Project

    Hello All,
    I know about normal Production Order Settlement Process in discrete industries.
    Can anyone give me the steps for the Production Order Settlement Process if the Production Order is created with respect to a Project in SAP PP- PS Integration Scenario.
    Thanks in advance for your support.

    Hi Experts,
    Can anyone clarify my above queries.
    Thanks in advance for your support

  • How do I activate NFC in order to pair with a speaker ?

    How do I activate NFC in order to pair with a speaker ?
    The speaker is a Beats Pill (supports NFC).
    Thanks
    Alon

    Yochelman wrote:
    How do I activate NFC in order to pair with a speaker ?
    The speaker is a Beats Pill (supports NFC).
    You don't connect the iPhone to the Pill using NFC.
    You connect 2 Pills using NFC.
    -> http://www.beatsbydre.com/support/how-to/pill/pill-functions.html

  • Collective Production Order ?

    Hi All,
    In a collective order how to distinguish between the header order and sub orders. I need to fetch all the header production order numbers. Please specify the table/field name or FM for achieing the same.
    Thanks and Regards,
    Navneeth K.

    Hi,
    Please try enhancement "PPCO0012"(tcode SMOD) and let me know if further issues are there.
    Reward if helpful.
    Thank you.

  • How we know whether a production order is open or clos

    Hi,
    Anybody can tell me how we can know that whether a production order is open or close?
    Thanks,
    Aparna

    Hi,
    In addition to 1st reply if your order status is TECO ,Clsed,Lcked  then your order is closed .In this status you can open this order for any use.
    TECO -Technically complete .
    Closed -closed for any use.
    Locked -Again same locked for any further process.
    Regards
    SANIL

  • How to Find Out The Production Order Number For The Sales Order Line Items

    Hi All,
    I want to know the number of production orders for each sales order line item. I know the sales order number .Can anyone tell me how the tables can be linked to get all the production order numbers for each sales order line item.

    I think it depends on your configuration. But check fields KDAUF and KDPOS in table AUFK.  or in table AFPO.
    Regards,
    Rich HEilman

  • How to track costing in Production order

    Hello Everyone
    I would like to get some details about how to set the product costs for Finished Goods and also how to track the expenses like packaging, labor, electricity, other charges etc, for individual production order.
    I have created the labor and packaging as a non inventory item and have used it in the BOM, now after the production order is closed, i find these two costs to be in the Actual Additional costs as shown below, till this is great.   
    But the requirement was, when they want to view the expenses or a month, then they require individual split up of costs against each production order. Is this even feasible?
    Please require help from you guys.
    Appreciate your help in this regard.
    Thank You

    Product Costing
    The cost of a FIFO or moving-average product is the sum of its component costs and additional costs (such as labor and overhead). To ensure accurate calculations of product cost, even if the components were issued manually, SAP Business One uses the cost of the items issued to production order and not the cost of the items currently in inventory. This avoids differences between the actual cost of components used in the order and the value of the product.
    Note
    The cost calculation method described here is relevant only for standard and special production orders, but not for disassembly for companies managing perpetual inventory.
    In the case of disassembly the components enter the inventory with the same cost as the items currently there. If the component is managed by FIFO, the cost of the oldest layer is used.
    The cost of returned components does not change; it is the cost of the last one that was issued.
    The product cost calculation is determined by the item management method.
    Standard – When the product is managed by standard cost, no calculation is made, and the cost is copied from the item master data upon report completion.
    Moving Average – When the product is managed by moving average, two figures are required for product receipt into inventory: receipt quantity and total value added to the inventory. The total value is the product cost, which is the sum of all component costs used for those products.
    FIFO – When the product is managed by FIFO, each report completion opens a new cost layer for the product in the inventory. The quantity in the layer is the quantity of the products just reported as completed. The cost of the products is the sum of all component costs used for the completed products divided by the quantity of the products.
    On every report completion, the system checks the following three quantities for each manually issued component:
    Issued Quantity – The quantity already issued to the production order.
    Used Quantity – The quantity already used for the completed products (completed products multiplied by the base quantity of the component).
    Needed Quantity – The quantity needed for the products that were just reported as completed (quantity of products reported as completed multiplied by the base quantity of the component).
    If the Used Quantity is greater than or equal to the Issued Quantity, this means that all items issued for the production order have already been used, and the Needed Quantity is yet to be reported as issued from the warehouse. Since the cost of the items that were actually used for the products is unknown, SAP Business One takes the current prices from the inventory.
    If the Issued Quantity is greater than the Used Quantity, SAP Business One finds the cost of the components that were issued and not used, and uses them in the calculation of the product cost. When finding those components, the issuing order of the components is taken into account, meaning that the first components to be issued are the first to be used. The components following those that were used are the first to be used for the cost calculation.
    If the sum of Needed Quantity and Used Quantity is greater than the Issued Quantity, meaning that not all needed quantity was issued, SAP Business One needs to make an assumption for those items’ costs, so it takes the current prices from the inventory.
    Upon the completion of a production order, on the Production Order Window: Summary Tab, you can check the product cost figures of the production order.
    Regards
    Kennedy

  • How can we delete the production order against sales order

    Dear All
    i

    Dear Gopi,
       In CO02, go to functions tab and select deletion flag active and save the PO. Once you activate the deletion flag GI, release and  operation confirmation will be deactivated.
    See below link to get more understanding.
    Delete Production Order from CO02
    Regards / US

  • Release of Multiple Production Orders

    Hi All,
    Does anyone know of a process that would enable the release and close multiple production orders?
    Best regards
    Earl

    Hi Gordon,
    I was sure that was the case. However, I thought I would put it question out there hoping that someone may have devised a solution. SDK it is.
    Best regards
    Earl