I have created two new internal variables in report writer in order to use them in planning layout of TA KP67:
- previous year: marked as internal variable: calculated as: &1CGJAHE-1 (2008)
and
- future year: marked as internal variable: calcualted as: &1CGJAHE+1 (2010).
In report painter these variables are assigned to key figures and are not shown on the selection screen again as they are calculated internally.
But in planning layout of TA KP67 cost activity planning these variables are also assigned to key figures like actual costs or fixed planned costs and are indicated as acceptable for input on the selection screen but shouldn't - so how it is possible to define internal variables in co planning layouts as really internal which do not come up if the planning layout is executed via TA KP06?
Thanks and regards,
Christian

Hello Christian,
when I understand your request correctly, you want to plan for several years like 2008, 2009 and 2010 but you just want to enter one year. Right?
For the column with the current fiscal year you can use a standard variable like GJAHR. For the other columns you define the year in the column as variable with value "GJAHR-1" (last year) and with value "GJAHR+1" (following year). On the selection screen of the planning transaction you will only have one field for the current year and the fiscal year for the other columns is calculated accordingly when you run the planning.
Hope this helps.
Cheers,
Daniela

Similar Messages

  • How to use Value Variable in Report Painter Column defined as Formula

    Hi Gurus,
    In report painter, how can I add one field (exchange rate) in selection screen, so that user can provide the exchange rate to be used, then execute the report, the exchange rate will used to multiple local currency amount.
    The reason for this is we want use provided exchange rate to convert the amount from once currency to the other currency.
    Alternatively I am studying the functionality of "Value Variable" and found that I can perform the task from this. I have created the value variable but when I am using the variable in Report Painter columns as "&ZVALVAR", system is giving me error. I read the help and it states that use the variable with "&" and do it as it is mentioned.
    Can anybody suggest what I need to do to make it workable.
    Thanks

    I did try using the presentation variable, but that does not work too. I am setting session variable in the dashboard prompt (select 'request variable'). When I use presentation variable, it hard codes the value of the variable name.
    sql is
    select date from work_order where facility = @{p_facility}
    the physical log sql is
    select date from work_order where facility = 'p_facility'

  • Variable in report painter

    Hi,
    I have a customized variable in report painter which pulls data from standard table, profit centre (GLPCT).  The data is included dummy profit centre. 
    How can block or should not allow dummy profit centre data to flow to the report?
    Please advice.

    Hi,
    Easier option is to create a profit center group excluding the dummy profit center and assign it in the report painter instead of the variable.
    Other option is at the time of executing the report, exclude the dummy profit center with out making any changes in the report.
    Regards
    Sudhakar Reddy

  • Report Painter problem with empty selection variant

    Hello,
    I use the cost center selection variant for the column definition in Report Painter as characteristic value. This selection variant get only the cost centers which are valid from 1.1.2003 to 31.12.2004. The column of the report created by Report Painter which uses this selection variant display value without taking into account limitations follow from this selection variant. I expect value zero for year fiscal year 2007 in this column, because the cost centers are invalid in 2007 year but the report displays different value. The problem appeared after upgrade from 4.6C to ECC 6.0.
    Best Regards
    ZD

    My problem with Report Painter occurred when I was creating my own report based on 1VK library.
    In my example I used in the column definition characteristic Cost
    Center, which is determined by selection variant, and Basic Key Figure
    equal SWKG-Costs. For system date (18.07.2007) there are no valid
    master data for the characteristic Cost Center but when I execute
    report for fiscal year 2007 the column display no-zero value without
    taking into account value of Characteristic Cost Center. I expected
    zero value in this column because there are no postings for Cost
    Centers (no valid cost centers were selected) in financial year 2007.
    Could you help me with this problem ?

  • Adding variable in Report painter

    Hi Gurus,
    I am creating a new report using Report painter. Though, it is working fine, I want to bring one of the field for selection. How to add variable ? I created a variable but I am trying to insert this variable in the report painter... I am unable to find any way.
    Awaiting your help.
    thanks in advance.

    Hi,
    Go to Global Parameters Definitaion in report painter, variable will be used only along with the field, just in global paramerters enter your desired field and click in next column, system will show you a pop up select your variable for that field...
    now its just done run the report and test it!
    If you still not make it refer to standard report of such kind, you will surely get it....
    Regards,
    Sayujya

  • Creating variables in Report Painter

    Hi ...
    I would like to know ... how do I create variable ? I know it is via T CODE GS11, but when run tht, in the next screen it pops up for variable ? What variable do I need to enter ? is this predelivered Eg : CE-PK, or can we create one ? Please advise
    Also, I would like to I have a requirement for a report whereby the format is like this .....
    SALES       CURR MONTH (06/2006)  LAST YEAR          
    - Sales IT
    - Sales 1
    - Sales 2
    COGS
    - cogs 1
    - cogs 2
    - cogs 3
    COS
    - cos 1
    - cos 2
    - cos 3
    GROSS PROFIT
    Whereby, SALES = sales it + sales 1 + sales 2, COGS = cogs 1+cogs 2 + cogs 3, COS = cos 1+ cos 2+ cos 3. also GROSS PROFIT = SALES + COGS + COS
    The abpve report is inclusive of Cost Centre and Profit Centre, how acn I utilize the libraray in Report Pianter to create such report, is this possible in Report Painter whereby including Cost center and Profit Centre in one single report
    Pls assist me
    Nathan

    When you create your variable first enter the variable name. Second enter the reporting "table" to use. Third enter the "field'. Press enter. Next enter a default value for your field. Save you variable. It is now ready to use in your report painter.
    Using the PCA reporting tables gives you the profit center but not the cost center. You can only use one reporting table per report. you will need a cctr report for that.
    First create your own libray from GLPCT. Next create your report using your new library. The report painter can do the calculations that you have shown.
    You create a formula in the row or column to calculate your sub totals.
    pls assign points if helpful as a way to say thanks.

  • Formula Variables for Report Painter

    Dear Experts,
    I have a Report Painter Report which displays month wise report in columns and now i want the report to be displayed based on the period mentioned in selection screen.
    Can someone please advice how do I do the same with use of Formula Variables.
    Regards,
    Rahul

    Go to the selection screen and press F1 and go to technical details to name the name of the screen field. example: 8A-VON (period from) and 8A-BIS (period to).
    In your report designer, you enter the those variable for the "period" characteristic and tick the variable ON/OFF checkbox.

  • New variable in Report Painter - GRR2

    Hi,
    Can i create a variable with a value of table PROJ, the value is in Z field of table PROJ?
    I need to create a formula in report painter to take the field value PROJ table and multiply by the actual costs.
    Many thanks.
    Regards.

    Hi,
    Easier option is to create a profit center group excluding the dummy profit center and assign it in the report painter instead of the variable.
    Other option is at the time of executing the report, exclude the dummy profit center with out making any changes in the report.
    Regards
    Sudhakar Reddy

  • Report Painter: How to change Selection screen.

    Hi All,
    I would like to know  the Process, how to add one more filed in the selection of the Report.
    Now  i have,
    selection.
    mat1:----
    mat2:----
    mat3:----
    date:----
      like that , Now i want to add mat4 in the Report Painter.
    thanks in adv..
    regards
    Prabhu

    Hi Mann,
    Thanks for reply.I have one doubt .
    1. I have already created variable for  characteristics figures,
    say exp
    col1->char001->&mat1
                        &mat2
                        &mat3
    now i want to add one more &mat4 for this chat.Figures.
    2.What is differance b/w set and Basic sets.How can i find basic sets of a Set.
    3.How can i att's chat.figures to Basic sets.
    plz help me to reslove this issue.
    regards
    Prabhu

  • Formula Variables for Report Painter- Syntac error in formula, Please Help!

    Dear Experts,
    I'm creating the report where I need to calculate annualized P&L. The formula is as follows : (P&L account/Period(variable ))12*
    I need to capture the From_period, which is entered by the user on the selection screen when running the report and use it as a variable in the formula above. Example: If User insert From Period 3, then the formula should be *P&L accoun / 3 * 12*
    I have tried so many different way but nothing seems to work. one of the ways i tried was:
    In the general selection Im using set variable 6P-S-PERIOVB.CCSS for period which consists of variable V_PERIO and B_PERIO.
    So Im trying to create a folowing formula:
    IF 1 >= u2018PER_FRu2019 AND 1 <= u2018PER_TOu2019 THEN 1 ELSE 16
    IF 2 >= u2018PER_FRu2019 AND 2 <= u2018PER_TOu2019 THEN 1 ELSE 16
    Unfortunately I keep getting Syntac error in formula. Please help me I'm really desperate to solve this issue after 5 days of unlucky research.
    Thank you in advance
    Regards
    Ernesta

    Thank you all for your help. The issue was that the variable was assigned to the different table as the library. After I changed it, it worked fine.
    Regards
    Ernesta

  • Formula Variables in Report Painter- Syntac error in formula

    Dear Experts,
    I'm creating the report where I need to calculate annualized P&L. The formula is as follows : (P&L account/Period(variable ))*12
    I need to capture the From_period, which is entered by the user on the selection screen when running the report and use it as a variable in the formula above. Example: If User insert From Period 3, then the formula should be *P&L accoun / 3 * 12*
    I have tried so many different way but nothing seems to work. one of the ways i tried was:
    In the general selection Im using set variable 6P-S-PERIOVB.CCSS for period which consists of variable V_PERIO and B_PERIO.
    So Im trying to create a folowing formula:
    IF 1 >= u2018PER_FRu2019 AND 1 <= u2018PER_TOu2019 THEN 1 ELSE 16
    IF 2 >= u2018PER_FRu2019 AND 2 <= u2018PER_TOu2019 THEN 1 ELSE 16
    Unfortunately I keep getting Syntac error in formula. Please help me I'm really desperate to solve this issue after 5 days of unlucky research.
    Thank you in advance
    Regards
    Ernesta

    so, I would use parameters.....
    P_fr_MO(2) TYPE N DEFAULT '01',
    p_fr_yr(4) type n default '2011'.
    Then, to set my range, i would do something like....
    data: lv_to_mon(2) type n,
             lv_to_yr(4) type n.
    if p_fr_mo eq '01'.
      lv_to_yr = p_fr_yr.  "12th month, same year...
    else.
    lv_to_yr = p_fr_yr + 1.  "any other month puts us into next year.
    endif.
    case p_fr_mo.
      when '01'.
       lv_to_mon = 12.  "always for 12 month period...
    when others.
       lv_to_mon = p_fo_no - 1.  '''example 10/2010 to 09/2011.
    endcase.
    then concatenate the from and to variables into what format is needed to read the data...
    on the other hand, if the user gives us from and to, we have a different problem....one then has to calculate what part of a year they have and create a factor for multiplying any data values....
    for instance if user says Jan (01) to (03) March, then I know that to month - from month + 1 is the number of months I have....
    then 12 / that number is the factor to multiply the results by....
    example...
    data : factor(5) type p decimals 2
              months(3) type n.
    if p_to < p_from.  "adjust if I cross a year boundary....Oct to Jan becomes 13 - 10 + 1 or 4 months.
    p_to = p_to + 12.
    endif.
    months = p_to - p_from + 1.
    factor  = 12 / months.  " factor   12 /4 months = 3 times the values obtained  = 1 year.
    something like this....hope this is helpful to you.
    Edited by: DaveL on Oct 18, 2011 6:24 PM

  • Formula variable in Report painter

    Hi
    Normally when ever you create a formula varibale for year or period system will
    check the period and year from current system year and period(S001 and S002)
    I am looking for a solution where i can create variable which is independent of
    current year and period.
    Lets Say if i give 2006 and period 7(of 2006)system has to give results
    in the predefined columns like 2006 of period 7 and 2005 of period 7 and 2004 of period 7 and 2003 of period 7(I have 4 columns)
    Can any one tell me how to create this using the formual variable,which will allow
    me to select in the input screen any period and year and display the results  as per my own requirement.
    Thanks
    Lily

    Hi Ramachandra
    Sorry for late reply
    As per your reply,i am not still clear,can i put in more clear my question again
    Selection screen 
    Year-2006
    Period-6
    I have 5 columns ,can you specify me the formula for 5 columns in your reply.
    Column1- (it has to display 2nd  quarter of 2006)
    Column2-(it has to display 1nd  quarter of 2006)
    Column3-(it has to display 4nd  quarter of 2005)
    Column4-(it has to display 3nd  quarter of 2005)
    Column5-(it has to display 2nd  quarter of 2005)
    Pls specify me FYEAR and Period from and period to which formula variable i need
    to use,how many variables i need to create for this purpose.
    Keep in view that selction screen i can give 2006,or 2005 or 2007,but system has to display 5 quarters back data in in 5 columns.
    This is urgent,can you pls help.
    Thanks
    Lily

  • Report Painter - ERP Financials - Question on Value Variable useage

    I want to use a value variable that works in Report Writer (table GLPCT, field MSL [quantity] but cannot select MSL as a variable field in Report Painter to insert the same variable (it is not a selectable characteristic) using the same Library and Table.
    Is there a way to make the field selectable in Report Painter in order to select a value variable that uses the field MSL ?  It is a valid field in the Library that I am building the report in.
    In building the columns, I can select characteristic fields such as:
    Ledger
    Record Type
    Version
    Fiscal Year
    Profit Center
    Functional Area
    Account number
    Period
    etc
    but not MSL Quantity.  Is there configuration to make this (or any field) accessible to Report Painter ?
    Any advice is welcome.....
    Thanks......

    Quantity is a key figure. When you create the column values you would get this from the key figure drop list.

  • Report Painter - Use of Constants / Local Formula Variable

    Hi,
    I am using constant and/or local formula variable in report painter in FSI.
    I could use both the values for calculating percentages, ie. it can be used for multiplication or division. However, when I try to use it for addition or subtraction, I am getting the error message no. KH206.
    In all cases, I am using different values in the formula, i.e. a absolute figure and a GL based figure.
    I am not able to understand, why it even allows me for calculating percentage.
    Can anyone help me in using a absolute figure for input and thereafter use it in addition / subtraction.
    I would prefer an immediate solution to this as I am in the final stages of this report.
    Full points guaranteed.....

    Hi Kash,
    Thanks for your reply..
    Can you elaborate bit further. You mean to say I should create a Constant with some value.
    Thereafter how should I bring that in the form. But, How do I enter the Constant in the Formula... There is no key for entering any text in the formula.. there are only ID (the values which we bring in the form and which can be selected for the formula) and numbers which can be entered.
    So how do I enter the name of the Constant?
    I tried just keying in the name of the Constant, and I could check the formula also, However, while saving the form, I am getting an error,
    Element WCaplimit Bis letztem ATag bis &$BISD is not defined correctly -> check definition
    Message no. KH206
    Diagnosis
    In element WCaplimit Bis letztem ATag bis &$BISD the system adds quantities and values or different currencies.
    Can you please revert back with step by step solution?
    Appreciate your prompt reply.... Thanks

  • Report Painter: Error RG102 when executing report

    Hi All!
    I need help with an error I'm facing with Report Painter...
    When executing a report with a large amount of variables and columns I'm receiving the error:
    Message no. RG102: Syntax error in GP3NDZHLG3MURI7VJEVF29KI876800, row 0
    If in the General Data Selection instead of using a Variable for the Version I use a fix value, it works OK. However, other reports are working properly with the same Gen. Data Selection.
    Does anyone has an idea of the cause of this report?
    Thanks!

    Hi All,
    I will try to clarify a little bit on my Issue.
    First of all, it's not a BW issue, but a Reporting Problem with the Report Painter for the Consolidation (EC-CS).
    The row is configured with a Set of Data regarding a Consolidation Item that includes all the P&L Accounts. It is configured to 'Expand'.
    Regarding the columns, I have a large number, between 40 and 50 mixing Ratio with Characteristics and Formulas. Within them, I'm using as well variables for Period, Consolidation Unit and so on.
    In the Selection Screen I have configured the following paramters
    Version - 100
    Dimension - T1
    Cons chart/acct - C1
    Ledger - US
    Cons group (Set and Variable) ZSETUNV
    Year for CG breakdwn (Variable) ZEJERAM
    Period for CG breajdw (Variable) ZPERAM
    With all the above-mentioned configurations the report works great. However, if in the Selecion Parameteres I try to replace the Version (Instead of having fix value 100, to have a variable ZVER) in order to deal with several versions in the same report when I save and execute I receive the posted error:
    Message no. RG102: Syntax error in GP3NDZHLG3MURI7VJEVF29KI876800, row 0
    Does anyone has an idea if there is a Maxium of Variables for Report Painter or any idea which may be the origin of this error?
    Thanks again!

Maybe you are looking for

  • How to use Javascript, C#, or Java to automatically fill out a PDF file using ACROBAT PRO

    Hi. I have purchased a copy of acrobat pro and am currently using it to try to create a method of populating certain fields in a PDF file. This particualar scenerio is a printable cerficiate, it has a spot for the persons First Name, Last Name, and o

  • Iphone 3g wont come on

    My iphone 3g 8gb wont come on after i did a reset. it will act liek its starting up with the apple symbol and when it goes away its turned off once again. i plug it up and it wont charge. plugged it in the computer and still doesnt recognize it. its

  • How to create bulk users in 11i EBS

    We have requiremnet for create nearly 150+ users 11i EBS accounts, is there any way to automate this..?

  • Dll problem

    I have had to format my system disk. Therefore, i have reinstalled all the programs i needed and all the drivers. However, the vi I need asks for a specific dll (pixcm32.dll). I manually specified the location. And the VI returns an error message. It

  • HP Pavilion g7 Notebook PC - Can't get internal mic to shut off or sync with webcam

    I'm not really sure what happened. I was trying out my headset with inline mic on my PC and it didn't work the only thing that worked was my internal mic. I did disable my internal mic at one point but turned it back on when I realized that didn't ma