Hi,
If you are using your project budgets, you will not need many integration steps.
IF you have a budget integrated, then use that account as charge account when you are creating a PO, if budget is not available for that account or it is not a budget account then system will check for budget at project level.
You can have stand alone budget just for projects without any integration to GL budget and you can still achieve budgetary controls.
Let me know if you need more help.
Mubarak
[email protected]

Similar Messages

  • Making accounts mandatory for folders

    Hi all,
    I have in the standard profile a bunch of mandatory fields (including Account), when i create a folder out of all mandatory fields it only complains for Security Group if left empty. Is there any way I can make it complain about Account too?
    Thanks,

    Hi Vishal,
    Not sure if you have found the solution. But this can be achieved by a transaction variant, via SHD0.
    Good luck.
    Regards,
    Vivek

  • Program Hierarchy & Absolute budgetary control (Functional)

    Hi,
    I am using program hierarchy where I am using financial structure as well as Workplan structure. I have a project at the top which is tracked as a program (say) PRG1. I have three projects (P1, P2, P3) linked to the above program through the workplan at the task level.
    I have budgets pre-defined (say 10000 $) for the program (PRG1) at the beginning of the year. I will enter this budget amount at a task in the program project.
    There will be multiple projects (P1, P2, P3) starting at different times during the year falling within the above program scope whose budget as and when entered should not exceed the budget amount entered at the program level.
    Case :
    01-JAN-09 Program Level Budget entered at the beginning of the year - 10000$
    01-FEB-09 Project (P1) started with a budget allocated from the above program - 3000$
    Requirement is --> System should check against the program level budget and allow entry of this amount at the project (P1) level.
    01-MAR-09 Project (P2) started with a budget allocated from the above program - 5000$
    Requirement is --> System should check against the program level budget and allow entry of this amount at the project (P2) level.
    01-JUN-09 Project (P3) started with a budget allocated from the above program - 3000$
    Requirement is --> System should check against the program level budget and reject entry of this amount at the project (P3) level.
    We had earlier successfully used this kind of solution but with GL Integration Budgets in Release 11.5.10.
    --- the solution is briefly explained in metalink Doc ID: 790613.1
    Since the new family pack M has these features of Program Structures/Hierarchy, can we use them to control my budgets using encumbrances at requisition and PO.
    Request viewers , project functional consultants to pour in their views and solutions. I can share the detailed step by step solutioning done in Release 11.5.10 using GL Budget and Project Budget integration.
    Thanks.

    Thanks Dina for your suggested solution.
    In Release 11i, we were using the solution of entering the TOP Budget amount against a GL Code Combination (Using Budget, Budget Organization definition) in GL. Then in projects, in the project type definition for budgetary control options we have entered -
    Budgetary Control
    Budget Type :     Approved Cost Budget
    Balance Type :     Encumbrance
    Non-Project Budget :     GL Funding Budget
    Encumbrance Type :     PA Encumbrance
    External Budgets :     GL Cost Budget
    Then for each of these low level projects, we enter the project budgets against approved cost budget. We have customized the Work-Flow based Account Generator for the “Project Budget Account” to refer to the GL code combination used in the GL Budget. Then we baseline the budget and generate the encumbrance journal entries which reserve the funds for the project budget and baselines the project budget.
    Next time for the second project, when it checks against the GL budget, we have the total budget minus the budget allocated to the first project. This way we had control of project level budgets not exceeding the amount entered in the GL.
    But now the requirement is to reduce the dependency on GL module for this GL budget entries. Also we want to use Program Hierarchy for the single view that it offers. Since we are entering the budgets at the program level, we dont want to enter it again in GL following the solutioning in 11i.
    Regards.
    Edited by: Phani.Ch on Jun 13, 2009 7:50 PM

  • Oracle Purchasing - Encumbrance Accounting Entries

    Dear Experts,
    Please help me by giving your support to my query..
    What are the accounting Entries system will generate for Encumbrance at the time of Requisition & Purchase Order in Oracle Purchasing
    Thanks
    Bharath

    Refer:
    http://www.oracleappshub.com/oracle-purchasing/accounting-fundamentals-for-techies-encumbrance-part-ii/
    http://oracle.ittoolbox.com/groups/technical-functional/oracle-apps-l/what-all-are-encumbrance-accounting-entries-for-p2p-transaction-1098879
    Regards,
    Ivruksha

  • Defining Account Determination for Real-Time Integr

    Dear all,
    I haven't understood yet about Account determination for the real-time integration of Controlling (CO) with Financial Accounting (FI).
    Please tell accounting process that use this account. And give me a detail example.
    Thanks so much
    Minhtb

    Hello
    This is the new feature in New GL accounting
    During allocations in Controlling, most of the postings created do not affect Financial Accounting. These postings do not update any G/L account transaction figures; they are postings within Controlling. If, however, an allocation in Controlling leads to a change in the functional area or any other characteristic (such as Profit Center or Segment) that is relevant for evaluations in Financial Accounting, a shift occurs between the affected items in the profit and loss statement. For this reason, this information has to be transferred to Financial Accounting. This reconciliation between Controlling and Financial Accounting takes place by means of real-time integration.
    As a result of real-time integration, all Controlling documents that are relevant for General Ledger Accounting are transferred from Controlling to General Ledger Accounting in real time. This means that Financial Accounting is always reconciled with Controlling.
    A document is created in Financial Accounting for each posting in Controlling. This means that the detailed information contained in the CO documents is always available in reports in New General Ledger Accounting. This information can be sorted by the following, for example:
    ●     Functional area
    ●     Cost center
    ●     Internal order
    Real-time integration replaces the reconciliation postings from the reconciliation ledger. Consequently, you do not need a reconciliation ledger.
    If, however, you do not set the Reconciliation Ledger Active indicator in Customizing for the controlling area, you cannot use the reports belonging to report groups 5A* (5AA1-5AW1). You set this indicator in Customizing for Controlling under General Controlling ® Organization ® Maintain Controlling Area. The reconciliation ledger serves as the data source for reports belonging to the report groups 5A*. You find these reports in the SAP Easy Access menu under Accounting ® Controlling ® Cost Element Accounting ® Information System ® Reports for Cost and Revenue Element Accounting.
    Replacement reports are available as follows:
    ●     You find the reports in the SAP Easy Access menu under Accounting ® Controlling ® Cost Element Accounting ® Information System ® Reports for Cost and Revenue Element Accounting (New).
    ●     You can create additional reports in report group 5A21. You can assign the report group to any drilldown report of New General Ledger Accounting using the report-report interface.
    ●     From the report Financial Statements Actual/Actual Comparison, you can call up the report Cost Elements: Breakdown by Company Code. You find the report Financial Statement: Actual/Actual Comparison in the SAP Easy Access menu under Accounting ® Financial Accounting ® General Ledger ® Information System ® General Ledger Reports (New) ® Balance Sheet/Profit and Loss Statement/Cash Flow ® General ® Actual/Actual Comparisons.
    You can define account determination for each controlling area. You do this in Customizing for Financial Accounting (New) under Financial Accounting Global Settings (New) ® Ledgers ® Real-Time Integration of Controlling with Financial Accounting ® Account Determination for Real-Time Integration. In this way, you use the same account determination as for the reconciliation ledger (transaction OK17). You can then use the reconciliation ledger reports to compare FI balances with CO balances.
    Prerequisites
    If you use real-time integration in at least one company code, you need to have activated company code validation for the related controlling area. You do this in Customizing for Controlling under General Controlling ® Organization ® Maintain Controlling Area ® Activate Components/Control Indicators. Otherwise, the reconciliation between Financial Accounting and Controlling at company code level is not possible.
    In Customizing for Financial Accounting (New), you have processed the IMG activities under Financial Accounting Global Settings (New) ® Ledgers ® Real-Time Integration of Controlling with Financial Accounting.
    Activate real-time integration for all company codes between which you want to make CO-internal allocations.
    In the IMG activity Define Variants for Real-Time Integration, do not select all CO line items for transfer. If the same line items are to be transferred as through the reconciliation posting from the reconciliation ledger, select the following line items:
    ●      Cross-Company Code
    ●      Cross-Business Area
    ●      Cross-Functional Area
    ●      Cross-Fund (if you use Public Sector Management)
    ●      Cross-Grant (if you use Public Sector Management)
    Features
    Value flows within Controlling that are relevant for General Ledger Accounting – such as assessments, distributions, confirmations, and CO-internal settlements – are transferred immediately. The FI documents are posted with the business transaction COFI. They contain the number of the CO document. This means that you can call up the CO document from the FI document, and vice versa.
    Activities
    If a document could not be transferred because the posting period was blocked in Financial Accounting or no account was found, for example, the document is included in a postprocessing worklist. You need to check this worklist regularly and process any documents in it. From the SAP Easy Access menu, choose Accounting ® Financial Accounting ® General Ledger ® Corrections ®Post CO Documents to FI.
    Example
    An internal order for business area 0001 is settled to a cost center of business area 0002. The document from this allocation is transferred in real time to Financial Accounting.
    Reg
    assign points if useful

  • Budgetary Controls and Encumbrance Accounting

    My understanding is that if I enable budgetary control in GL then that would force us to enter budgets using journals only (amounts cannot be entered directly). Does budgetary control also force us to use encumbrance accounting? Would PO module then be producing encumbrance if budgetary control is enabled? Can we have budgetary control enabled without forcing the system to produce encumbrance accounting?

    Hi
    You must enable encoumbrance accounting in Purchasing and Payables.
    however, you could setup the budgetary control of GL as Null. that means the system validation of fund check agains GL budget will always pass (no actula limit). In such case, only project budget will have effective fund check.
    Dina

  • Confirmation Control Key Should be mandatory for PO document type

    Hi All,
    I want to know, is there any configuration settings to make mandatory "confirmation control key" for the Particular Purchasing document type's.
    If it is not there what should be the best to achieve this requirement.
    Thanks in Advance,
    Shankar.

    Hi
    I think there is no standard setting to make mandatory document "confirmation control key" for the Particular Purchasing document type's.
    Best way is to maintain in Purchasing view of vendor master record since confirmations rare sent by the vendor.If you want for some perticular materials you can maintain in Purchasing info record.
    Regards
    Ramakrishna

  • Account assignment mandatory for material

    Hi,
    While creating contract i am facing this warning message..i can ignore this message , but what is the root cause for it.
    Error is :
    "Account assignment mandatory for material 100000040 (enter acc. ***. cat.)
    Message no. ME062
    Diagnosis
    There is no provision for value-based inventory management for this material type in this plant. Account assignment is thus necessary.
    Procedure
    Please enter an account assignment category"
    I checked Qty and value update in OMS2 also.
    It is maintained.
    Then what is wrong?
    Uts

    Hi,
    Account assignment determination depend on the valuation class. When your account assinged category is mandatory in that case go and see the account modifier assigned in account assinged category. After that verify the G/L account in OBYC for key GBB and account modifier and respective valuation class assigned in material master.
    If the entery does not exist then system will give you an error message.
    Regards
    Prashanth

  • Account assignment mandatory for material 702 (enter acc. ***. cat.)

    Account assignment mandatory for material 702 (enter acc. ***. cat.)
    Message no. ME062
    Diagnosis
    There is no provision for value-based inventory management for this material type in this plant. Account assignment is thus necessary.
    How to rectify this error

    Go to transaction type OMS2. Check whether the material type u are using is ticked for Value update.
    If not,
    a. Use a different material type
    b. or Use an account assignment category.
    Regards,
    Anantha

  • While Creating PO its saying account assignment mandatory for the material.

    Dear All
    I have created a material with Mechanical Engineering as Industry sector and ROH as Material Type.
    For this material i created PR and PO both the time it said account assignment is mandatory.
    Why this happens?
    I don't want to enter any account assignment category.
    Pls help.
    Regards
    Depin

    Hi,
    Normally purchasing ROH with PO needn't to assign the account assignment category, but if don't create accounting view for the ROH material or create the accounting view without valuation class assigned, system can't find the relevant stock account automatically, so will issue the message just like "Account assignment is mandatory".
    So you should check the material master data, if it's fine, then you will not see the message any more!
    Good luck
    Tao

  • ACCOUNTING DOCUMENT FOR CONTROLLING DOCUMENT

    Hi Experts,
    I would like to know which table provides me the accounting document for the related Controlling document.
    ie. If i gives a controlling document for a table as an input in SE16 i should get the related accounting document . please help...
    Thanks and regards,
    Anand. K

    GLPCP Plan Line Items
    GLPCT Totals Table
    GLPCA Actual Line Items
    GLPCO  Object Table for Account Assignment Elements
    GLPCC   Transaction Attributes
    Regards,
    Sangram
    Moderator: Irrelevant

  • ME21N : account assignment mandatory for bulk material

    Dear guru.
    For a raw material used as bulk in production with material type ROH and quantity/value updating I need that when I create purchase order the system send an error message that account assignment is mandatory.
    I know that for an NLAG or UNBW material type the system send this message.
    For internal reason  I need to maintain material type ROH  with quantity/value updating , do you know a solution , any exit , in order to solve my problem  ?
    Thanks for you help.

    CONS  SAP wrote:
    Dear
    > I need that this component in the bill of material must be managed with position type L and I donu2019t want to do consumption movements.
    > I have verified that I can create a purchase order with account assignment for this material , I need only that the system send a message for these bulk materials.
    > Thanks.
    position type L means it is a inventory managed material.
    why do want the material to be inventory managed and at the same time dont want to record consumption movements?

  • Issthe PO Error message *Account assignment mandatory for material

    At the time of creating the PO after putting the material and plant I get the error message " *Account assignment mandatory for material 10000213". The plant for which i want to raise is 3004 which i have created recently and only in this plant this message is showing. Please help me out
    Edited by: amitekum on Sep 17, 2010 12:34 PM

    you should have searched sdn first for this
    anyways it means that the in tcode OMS2.
    you need to mark the check box quantity and value updation for the material type of your material in combinationwith your plant
    it means this material is acting as consumable material

  • Mandatory default account assignment for HIBE material

    Hi,
    For stock transfer PO we need account assignment Mandatory with default value "K" while creating the stock transfer PO.
    How we can do this?
    With Best Regards,
    Rajkumar

    Thanks for the reply.
    We want the same functionality as described by you.
    The requirement is that, when the stock transfer PO will be created the account assignment for line item of HIBE type (only) should be displayed as "K" i.e. Acct. assig. is mandatory and default equal to "K". With this restriction the user creating the Stock transfer PO for HIBE material will be prompted to enter cost center and GL account. And when goods receipt will be made for the PO,  the HIBE material will get consumed for cost center.
    So, can we made such restrictions while creating stock transfer PO?
    With Best Regards,
    Rajkumar N. Phand

  • Getting error in ME22 " Account assignment mandatory for material"

    Hi SAP Gurus,
    In ME22 tansaction I am entering 1 new line item, and system is not allowing and throwing error as " Account assignment mandatory for material:8121-1045 ( Enter account assignment catagory) but user dont want entering account assignment is mandatory. Please give your input on this issue.
    Thanks,
    Sharan.

    Hi Sharanappa
    The account assignment catagory becomes Mandatory when
    "Value Updating" is Not selected for the particular valuation Area for the Material Type
    For Maintaing the same pls follow the below Path
    SPRO>LOGICTICS GENERAL>MATERIAL MASTER->BASIC SETTING->MATERIAL TYPES-->DEFINE ATTRIBUTES OF MATERIAL TYPE
    Regards
    Vikrant

Maybe you are looking for

  • Mavericks:  Killer of Networked Printing

    I'm a veteran user of PC/Windows after 2y owning a MBP I'm still amazed at how much stuff just is bizarre in the OSX world that worked flawlessly in the Windows world, at least since Win 7 especially.  Very difficult to do the most common tasks used

  • Output doesn't fill 720x480 player screen

    I am running CS4 and when I output to H264 with an output frame size of 720x480 in Encoder, the resulting file will be squished and played back at 640x480.  The properties of the player show it is playing 720x480 and the video plays with black bars o

  • How to copy music from itunes on mac onto itunes on pc?

    Hi all, I have an ibook and a laptop pc. all my music is so far on my ibook, and I would like to copy it all onto my laptop, without having to import every singe cd i burned onto my mac onto my pc again! is that possible? I tried via my ipod, via a u

  • Hspace gone from Property Inspector

    DW is pretty new for me; I've probably done this to myself somehow. I'm following a lesson in a book and it shows an image selected and asks me to click in the Hspace box in Property Inspector and add 40 px. This makes perfect sense to me. I did exac

  • Can we apply Dense Rank

    Hi All, I am working on Oracle BI Publisher. Can we apply Dense Rank on a column directly in the template? I don't want to change the total query for this, is there any way to do in template? if yes please tell me how can we do. Any suggestion would