Lead time for Item / Weekends

Hi
I am confused about the lead time to be entered for the item planning/MRP.
Do I include weekends when entering lead times in Items master data or not?
2 weeks = 10 days or 14 days?
In MRP I can select to respect Holidays. Does that also influence calculation of weekends as well or are weekends respected anyway?
Thanks
Franz

Hi Gordon,
Thanks.
My Holiday dates settings are:
- Weekend from Saturday to Sunday
- Ignore weekends for payments (but this is really for payments only and has no influence on MRP, I assume)
- The table lists holidays like easter or X-mas, only
As you said: This would mean that Item Master Lead time needs 'working days' to be entered.
If I get that straight, it is important to select to respect holidays in MRP with this setting. Otherwise the due dates for orders in recommendation report will end up too short/too close to the real date needed and a purchase order may be placed too late.
Franz

Similar Messages

  • Lead time for Purchase items

    I had read that Lead time for Purchased items is calculated per 7 working days / week, by default. However, when I checked this, I found that the MRP planned orders were always considering our mfg calendar that has 5 working days / week.
    Anyone tried this.

    Industries & Product which have stabilsed have the same measuring yard and standards. This is also applicable for calendar working days, otherwise we need to device the 'interface' because the results would be weird, specifically when we speak of 'supply chain'.
    <BLOCKQUOTE><font size="1" face="Verdana, Arial">quote:</font><HR>Originally posted by erik anthonsen ([email protected]):
    this is correct. it is up to individuals to change the amount of days that the company manufactures as their standard. if your facility is running 7 days a week-----use 7 days at setup<HR></BLOCKQUOTE>
    null

  • Lead Time in Item Master

    Hi
    Does Lead Time in Item Master respect weekends and only count working days?
    Meaning, for two weeks do I enter 10 or 14?
    Thanks
    Franz

    Hi Franz
    As far as I know, NO. You only have the option to include holidays in the MRP wizard itself which will then calculate against lead times. Best would be to test on a test database with both scenarios (with 10 or 14, and tick/untick holidays in MRP) and see what the results are.
    According to the Online Help the above is correct:
    Consider Holiday Table for Production Planning Factors in holidays and weekends in lead time calculation, as defined in the Holiday Details window. Holidays and weekends increase the lead time interval for MRP calculations.
    Consider Holiday Table for Purchase Planning Factors in holidays and weekends in lead time calculations, as defined in the Holiday Details window. Holidays and weekends increase the lead time interval for MRP calculations.
    Kind regards
    Peter Juby

  • TS1702 The Calendar app that came on my i4S Phone does not sync the correct time for items posted on my Yahoo Calendar.  Actually, they post exactly 4 hours earlier than the correct time on my Yahoo Calendar.  Does anyone have a "fix" to correct the "time

    The Calendar app that came on my i4S Phone does not sync the correct time for items posted on my Yahoo Calendar. Actually, items post exactly 4 hours earlier than the correct time on my Yahoo Calendar.   My i4S is in the correct New York time zone.  Help?

    I posted this question a while ago and didn't receive any responses but there are a lot of people who have viewed it and 10 have said they have the same question so I thought I would update you that I added my nanny to my exchange server account (created an email for her) and I send all invites to that email address and they work.  So sending invites from an exchange server account to a non-exchange server account apparently is a bug so to solve it, get on an exchange server I guess.

  • Lead time for POs

    hello, I am new to this bog, but can anyone help me with a t-code for getting the lead time (planned delivery time) report i.e. how can we identify if a PO has materials with longer lead times for a set of purchasers/vendors ?

    We experienced such a problem ... using only BEx functionalitites means (at the end) using Virtual KF ...
    Considering the complexity calculation to be made this is a time consuming approach that has even an high response time (in terms on minutes ... depending on the amount of data)
    During Data Load create two more technical KFs to store intermediate values of the formula (X^2 and a counter ...): this because of the fact that BEx formulas work AFTER Aggregation.
    Hope it helps
    GFV

  • Lead Time for manufacturing and its corresponding Quantity in Material Mast

    Hi all ,
    Do we have any feilds in SAP Material Master
    which are useful for
    1) Lead Time for manufacturing
    2) Manfactured Lead Time Quantity
    if the mateials are produced inhouse.
    thanks
    ksr

    Dear,
    There are no such a fields in material master, But in MRP 3 view you will get theotal replenishment lead time field.
    Which use for the produced in-house if the replenishment lead time is included in the availability check:
    This is nothing but the  in-house production time and, if available, the goods receipt processing time.
    Also refer this link to calculate the in-house production time correctly,
    Total Manufacturing time for assembly
    Regards,
    R.Brahmankar

  • Lead Time for Purchasing Material & Manufacturing Material

    The query is related to the process of Material Requisition planning.
    I need to know from where exactly the system picks up the lead time for generating Purchase requistions?
    - For purchased material (lead time from placing order to actual recipt of material, time needed for QC checking till its release)
    - For own manufactured material (lead time at each work center in the recipe along with actual time required for a particular process)

    Hi
    for your information for  any material the data for the lead time comes from the material master
    http://help.sap.com/saphelp_46c/helpdata/en/fd/45b7ee9d6411d189b60000e829fbbd/frameset.htm
    if you click on the link you can get the entire process.
    as you can see SAP picks up the deatil from the MRP2 view of the material master.
    hope this  is helpful.
    regards
    Vignesh.

  • I have been charged several times for items I have not ordered or received...Paradise Cove App

    I have been charged several times for items I have not ordered or received...Paradise Cove App.
    On a few dates I have attempted to purchase items on Paradise cove...then been billed several times for items I never received.
    please remove these charges.
    Tony Starace

    Select the content which is causing a problem and use the 'Report a problem' button in Your Purchase History on your computer.

  • Different Lead times for supplier in MRP calculation

    Dear All,
    We have different suppliers for a material. Different suppliers have different lead times and Min.lot size. Our requirement is when we run MRP system should suggest Pld.Order quantity for the supplier and also take lead time accordingly. I have done splits for suppliers by using Quata arrangement but system is only taking planned delivery time from material master record.
    I also defined info records for the vendor and define lead time but still system is taking Pld delivery time from materials master.
    Please help
    Majid Ali khan.

    Hi,
    Go to OPPQ, enter your plant then click on External Procurement, there tick the check box Scheduling: Info Rec / Agreement.
    This will ensure that the PDT is read from info-record if it exists.
    Hope it clarifies.
    Regards,
    Vivek

  • Lead time for Purchase Orders and Goods R. (EKBE-EKET)

    Hi all,
    has anyone already implemented a logic for calculating
    the lead time between delivery date (EKET-EINDT) and the
    goods receipt date (EKBE-BUDAT) for extraction to BW?
    I have the problem, that i have more than one schedule line. There you cant link the GR (EKBE) to the relevant schedule line (EKET). How can i implement the FIFO solution (FirstinFirstout)?
    Example:
    EKET
    DocNr_Pos__ETENR__Quantity____EINDT
    6700___10__1_______100________20060601
    6700___10__2_______300________20060701
    EKBE
    DocNr_Pos__Nr__Quantity__Budat
    6700___10__1_____200_____20060603
    6700___10__2_____200_____20060702
    Result should be:
    DocNr_Pos_ETENR__Quantity__Deliverydate__ZBUDAT(from ekbe)
    6700___10__1_______100________20060601___20060603
    6700___10__2_______300________20060701___20060702
    20060702 therefor because the the full quantity arrived at
    this date.
    Thank you very much for your help or any codings, best regards
    Frank

    HI Horny,
    Can you use the Following Tables:
    S039 - > LETZTABG - Date: last (i.e. most recent) goods issue
    EKPO -> EBELN - Purchasing Document Number.
    You can create View by using these two tables (Material Number is the Common) and uploade the data.
    Hope this will be helpful for your question.
    Thanks
    Rajesh
    Message was edited by:
            rajesh

  • Addional lead time for Sales BOM kitting process

    When a Sales Order BOM Sales Order is scheduled, we would like to have a lead time added for the Shipping kitting step.  So the pick date will be X number of days before the ship date.
    Is there a way to do this is ?
    Thanks,
    Doug Karien.

    Hi DK,
    Go to Ent structure > Definition > LE > Define shipping point, choose your shipping point, click on detailsand check there, "Rounding work days" filed may provide you some soln.
    Regards
    SD

  • Lead time for iMac with SSD?

    Has anyone ordered/received a 27" iMac with SSD?  When I configure that machine on the apple store website, the estimated shipping changes from less than one week to 4-6 weeks.
    However, if I configure the same machine on MacMall their estimated shipping time changes from same day to 5-7 days.  I'd prefer to order directly from Apple as we get a (small) corporate discount, but a 4-6 week lead time is pretty rough to swallow.
    A phone call to the Apple Store indicates they are having difficulty sourcing the SSD's. 
    Has anyone had any recent experience trying to order this config?
    Thank you
    Mike

    Thanks for the advice and the links. yes, I would like to speed up ps as much as possible.
    I wonder if putting the scratch disc on the same drive as the OS would cause them to interfere with each other? Even if they are on different partitions, they would not be able to be accessed at the same time, or could they? That's why I was wondering if I should place scratch disc on the internal HDD -- but then I don't know how much to partition for it (or to partition at all?)
    ALso, I read on a few places that too much read/write on the SSD wears it down over time? Is this more of a theoretical concerns - it does not make sense to me since it has no moving parts!
    thanks again for the advice ... I'm gonna go digest those links

  • Lead time for iPhone 6 silver 64G from Apple?

    I ordered an iPhone 6 silver 64G from AT&T. It has been 4 weeks. The delivery dates are tomorrow (11/12 through 11/21). I'm hoping I get it soon.
    Has anyone on the forum ordered this specific model from Apple lately? What was the expected lead time? I have heard from friends that they have seen 64G iPhone 6's in stock in the Apple store. Can this be true? I would pick the one that is hardest to find...
    Thanks in advance.

    Alfredo Jahn wrote:
    I ordered an iPhone 6 silver 64G from AT&T. It has been 4 weeks. The delivery dates are tomorrow (11/12 through 11/21). I'm hoping I get it soon.
    Has anyone on the forum ordered this specific model from Apple lately? What was the expected lead time? I have heard from friends that they have seen 64G iPhone 6's in stock in the Apple store. Can this be true? I would pick the one that is hardest to find...
    Thanks in advance.
    Ask AT&T.
    Sorry your question doesn't fall into a technical question which is what this forum is for.

  • Different lead times for suppliers

    Dear All,
    We have different suppliers for a material. Different suppliers have different lead times and Min.lot size. Our requirement is when we run MRP system should suggest Pld.Order quantity for the supplier and also take lead time accordingly. I have done splits for suppliers by using Quata arrangement but system is only taking planned delivery time from material master record.
    I also defined info records for the vendor and define lead time but still system is taking Pld delivery time from materials master.
    Please help
    Majid Ali khan.

    I also maintained plant parameter -- external procurement -- tick on planned delivery time from info records with this setting to make system to consider different planned delivery times.

  • Lead Time for Procurement Materials

    Hi Gurus,
    Can you elaborate on hierarchy for procurement lead time materials. If there is lead time given in Material Master as well as Info record and Source List. Then which lead time will be considered by the system for procurement?
    Also clarify what is the significance of Source list for Material Master?
    Regards,
    Pradeep

    Hi
    System takes more priority for lead time mainatained in Info record ahead of material master's planned delivery time. Along with planned delivery time, purchase processing time maintained in OMEW and GR processing time in Material master.
    Source list defines the vendor/list of vendor who supply material for a plant in the given validity period. A vendor can be fixed or blocked. FIxed vendor makes MRP to create source assigned PO. later it can be made as PO automatically.Scheduling agreement with sourcelist and MRP relevency indicator 2 can give automatic schedule line.
    Regards
    Antony

Maybe you are looking for

  • Clearing of invoice with rounding off difference

    Hi I am trying to clear invoice via Tcode F-53. The invoice is booked with tax code (V1 : ED + VAT) for the amount of 1022.08. When i process the payment for 1023. I have made necessary configuration to post the difference to sundry balance w/off acc

  • As 2.0 class objects- how to swap depths of a movie clip

    How do you bring an object to the top? if it's just a movie clip, I could do a swapdepths, but if it's a movieclip that's part of an AS 2.0 object, how do you swap depths of the whole object? I create 2 objects (same class) which each have a moviecli

  • How to use gmail with JavaMail

    JavaMail 1.4 is capable of sending and reading messages using gmail. All that's required is to properly configure JavaMail. I'll illustrate the proper configuration using the demo programs that come with JavaMail - msgshow.java and smtpsend.java. Let

  • IPhoto won't go in dock

    Have a friend that has a iMac the won't let iPhoto put a icon in the dock. Other things will go in it but not iPhoto. He is running Snow Leopard. Not sure about anything else. thanks .

  • BW query relevant to MC.1 in R/3 MM

    Hi Guys, Can anyone tell me if there is any BW standard query which will show exact output as in MC.1 report in MM at R/3 side? If no then how can we do it? Any help rewarded. Regards, vaibhav.