Linking P6 Material Cost to Unifier Schedule

Hi Friends,
I have linked P6 Schedule to Unifier Schedule but I am unable to transfer Material Cost from P6 to Schedule sheet or the Cost Sheet.
Any help is appreciated.
Regards
Kedar

Did you went trough 'Projects > Activities > Actions > Import/Export > Send to Primavera Unifier'? ie: - P6 = Planned Total Cost (Projects > Activities > “Planned Total Cost” column - Unifier = Schedule Sheet > “Non labor Costs” column Regards, Matías G. Uribe.

Similar Messages

  • Link between Material, Cost center to Work Center.

    Hi Experts,
    Can you provide me the following.
    Link between the material and work center.
    Link between Cost center and Work Center.
    Thanks in advance.
    Jyoshna.

    Extend the cost center validity from 01.01.2008, there won't be any harm. It may take from the beginning of the calendar year.

  • Material costed, production order with no target cost

    I've a case of production order and I don't where to find information to solve it.
    I've a product A costed from March. Standard cost is correct.
    I'm creating a production order now. The cost estimate is calculated during the delivery.
    I've confirmed order by CO15. I've created a variance by deleting 2 items in bom of order. And confirm less than wanted on other component. But I don't think these variances are linked to my problem.
    In CO02 and cost analysis : target cost of my product equals 0.
    I've checked my prod cost variant and choices are : std price, L price from PIR, moving average price.
    Thanks for your helps
    Christophe

    How can I see that ? I've checked that material cost has taken the bom during the cost explosion. Components are also costed.
    I've noticed that target cost appears after variance calculation for product.

  • How to include Material Cost in the SD report

    Hi,
    I am working on Cube 0SD_C03 for the Sales and Distribution Report "Sales Contribution - Product Wise u2013 KPI" where I have to show the following information which are given below.
    1. Total Sales Qty.
    2. Total Sales Value
    3. Total Material Cost
    For third one I do not know how to include this in this SD report.
    so please tell me about this if anybody has idea about this?

    Hi Francisco,
    Note:
    your xml should only have
    <URL>http://dbxserver.dbxprts.com:7778/pls/apex/f?p=134:1:::NO::P1_ID_CONSTANCIA:1183</URL>
    Show me your sample XML , i can help you.
    What is your expected output ? PDF or HTML ?
    here it is.
    option1:
    If the XML data includes an element that contains a hyperlink , then you can use that element to create dynamic hyperlinks at runtime.
    a. insert hyperlink from word menu
    b. In the Type the file or Web page name field of the Insert Hyperlink dialog box, enter the following syntax:
    c. {ELEMENT_NAME_WHICH_HAS_URL_LINK}
    where ELEMENT_NAME_WHICH_HAS_URL_LINK is the xml data element name
    option2:
    create a form field, you can add it
    <fo:basic-link external-destination="http://www.google..com">
    <fo:inline text-decoration="underline">google Link</fo:inline>
    </fo:basic-link>
    or
    <fo:basic-link external-destination="{ELEMENT_NAME}">
    <fo:inline text-decoration="underline">google Link</fo:inline>
    </fo:basic-link>
    or
    <fo:basic-link>
    <xsl:attribute name="external-destination"><xsl:value-of select="ELEMENT_URL"/>
    </xsl:attribute>
           <xsl:value-of select="LINK_NAME"/>
    </fo:basic-link>

  • Raw Material Cost Estimate - No split between cost component

    Dears,
    I need to execute a material cost estimate considering the Purchasing Info Record (PIR) where 3 different conditions are present:
    1) PB00
    2) FRB1
    3) RUC1
    The scope is:
    - linking PB00 to cost component 1
    - linking FRB1 to cost component 2
    - linking RUC1 to cost component 3
    Cost components are already created.
    I did following steps:
    - creation PIR with these 3 conditions (transaction ME11)
    PB00  10,00 EUR @ 1 KG
    FRB1   2,00 EUR @ 1 KG
    RUC1   3,00 EUR @ 1 KG
    - link condition types to origin groups (transaction OKYO)
    FRB1 linked to FRB1
    RUC1 linked to RUC1
    - link origin groups to cost component (transaction OKTZ)
    PB00, is linked to cost component 1 without origin group, but using only account coming from T030 table 
    FRB1 is linked to cost component 2 using origin group FRB1 and the same acocunt used for condition PB00 coming from T030 table
    RUC1 is linked to cost component 3 using origin group RUC1 and the same acocunt used for condition PB00 coming from T030 table
    At this moment, when I try to execute the cost estimate with transaction CK11N, the split is not done, and all condition types (all amounts) are linked to cost component 1. The set-up done in OKYO is not considered by the system.
    In the material master there's any origin group, if I try to fill in origin group FRB1 all condition types (all amounts) are linked to component 2, and if I try to change the origin group in the material master from FRB1 to RUC1, all condition types (all amounts) are linked to component 3 --> this means that the set-up done OKTZ is correctly considered by the system to link the origin group to the cost components.
    The problem is that the system reads the origin group from the material master, instead of transaction OKYO.
    How can I solve this problem?
    Thanks and Regards,
    Jody

    Pl verify following two things -
    Check valuation variant.
    Strategy sequence should have 'L - Price from purchasing info-record' and Sub-strategy should be 'A Quotation price via condition table' or 'B PO price via condition table'.
    OKYO setting should have valuation variant associated with your costing variant, along with other details (dont leave that field blank).
    Let us know if that works.
    Regards,
    Subodh

  • Material Cost estimate realted issue and question

    Hello,
        we have a multi level BOM, I have makre and released for one sub level material in the BOM, there are few other sub- materils which need to be costed, can i do the cost estimate for the highest level of BOM or do i need to do first for each sub- component in the BOM, also for the one sum- companent wchi is realesed can that be changed.
    please let me know.

    Hi
    Both are in one way the same.
    Material cost estimate can be calculated as
    1. Material with quantity structure
    2. Material without quantity structure
    You can get more insight into it at the following link
    http://help.sap.com/saphelp_47x200/helpdata/en/7e/cb938143a311d189ee0000e81ddfac/frameset.htm
    Regards,
    Suraj

  • Material cost estimate with quantity structure and without quantity structu

    What is the difference between material cost estiame with quantity strucutre and without quantiry structure?

    For the quantity structure pl read the following link
    http://help.sap.com/erp2005_ehp_02/helpdata/en/7e/cb938143a311d189ee0000e81ddfac/frameset.htm
    For without quantity stucture
    http://help.sap.com/erp2005_ehp_02/helpdata/en/7e/cb938143a311d189ee0000e81ddfac/frameset.htm

  • Material cost estimate with quantity structure (tcode: CK11N)

    Hey dear friends.
    I donu2019t know in which forum I should put my question above.
    In fact, Iu2019m new to SAP PM module.
    Iu2019m trying to create material cost estimate with quantity structure (tcode: CK11N) for a material u201CXu201D.
    This material is manufactured.
    While running the transaction CK11N, I got an error message.
    After analyzing this error message, Iu2019ve realised that somebody had assigned wrong activity types to cost centers which are linked to this material in tcode: CR03, tab: costing.
    So Iu2019ve changed and assigned the right activity types.
    Then, Iu2019ve tried to run the tcode CK11N again. But the system still brings the wrong activity types and seems to ignore the ones that Iu2019ve assignedu2026
    It seems like the old activity types still linked to the cost centers somewhere else than in tcode CR03u2026
    Any idea about what am I mising ?
    Thank's in advance.
    Bahia.

    Dear Bahia,
    If its rate routing means,i guess you must be working in REM scenario.
    So goto CA22,delete the existing operation and then assign the same work center in a new
    operation,check what activity types is it proposing in the rate routing,if its reflecting correctly means
    save the datas.
    Also goto KKF6N--->click the change mode icon and then calculator button to create a preliminary cost
    estimate and then save the datas.
    One of our forum friend has asked you to check the production order read PP master data once
    again,but understand there is no production order concept in REM scenario,only planned orders.
    Then come back with your queries.
    Regards
    Mangalraj.S
    Edited by: Mangalraj.S on Jun 17, 2009 12:05 PM

  • Material cost estimate with Quantiy structure

    Hello All,
    Can anyone please help in the following problem. When we do material cost estimate with quantiy structure, system is throwing message as "source of supply cannot be determined".
    Maximum points will be assigned to the suitable answer.
    Thanks in advance.
    Srinivas

    Hi, Srini,
    Please check in material master data whether this material is in-house produced or externally procured, which can be found in MRP view.
    Please also check your costing variant and valuation variant for material cost estination, I think possibly you chose stratey L FROM Purchasing Info Record. If not, ignor it.
    If it's externally procured, SAP logic is that firstly it will check the source list, then determine the quota arrangement and find proper vendor for the selected material. The error message is possibly caused by missing vendor or wrong quota reason. So please follow the SAP logic to check data one by one.
    Please check the following link on vendor determination in online help document.
    http://help.sap.com/saphelp_erp2005vp/helpdata/en/7e/cb938143a311d189ee0000e81ddfac/frameset.htm
    Please specify if you also used mixed costing for material.
    Good luck!

  • Material cost estimate and mateiral cost estimate with quantity structure

    Hi sap guys,
    What is the difference between material cost estimate and material cost estimate with quantity structure

    Hi
    Both are in one way the same.
    Material cost estimate can be calculated as
    1. Material with quantity structure
    2. Material without quantity structure
    You can get more insight into it at the following link
    http://help.sap.com/saphelp_47x200/helpdata/en/7e/cb938143a311d189ee0000e81ddfac/frameset.htm
    Regards,
    Suraj

  • Material cost estimate using recursive BOM

    Hello everybody.
    I want create material cost estimate (CK11N) using a recipe with recursive BOM. When I execute the transaction CK11N the following message is display Costing of cycle 00001 does not converge
    Do you know what is missing?
    Thanks in advance.

    Dear,
    Message no CK740?
    Please do check the link below......
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/f8/a3e333bf3d11d189900000e8214595/content.htm
    and OSS note : 858384
    Regards,
    R.Brahmankar

  • How to capture Material costs, profit margins in pricing

    Guys,
    What is the way to capture material costs, profit margins and other sub-totals into the pricing procedure?
    Thank you.

    Hi
    For capturing the material costs, you can use one of VPRS, EK01 or EK02 condition types. The usage of these condition types and their significance can be seen in some other thread here. There are lot of threads on these condition types.
    You can also go to these links given below.
    http://sap.ittoolbox.com/groups/technical-functional/sap-log-sd/condition-type-ek01-ek02-1396383
    http://www.jt77.com/system-dynamics/model-08388.html
    http://www.jt77.com/system-dynamics/model-05254.html
    http://www.jt77.com/system-dynamics/model-04469.html
    http://www.sap-img.com/sap-sd/difference-between-condition-type.htm
    This should also tell you something about profit margin.
    For subtotals, there is a separate column in pricing procedure and  you can mention which subtotal a condition type or subtotal should correspond to. The subtotals range from 1 to 9 and then A to Z. The purpose of these subtotals can be seen by putting an F1 in that column or through some oss notes.
    Hope this helps you.
    Rewards if this helps.

  • Material cost relating to shipment

    Hi,
    Can some one help in this?
    I have to find out the Material cost relating to particular shipment. From what i know this seems to be coming from condition records EK01 or EK02. I think this has to be taken from the KONV table but i dont know how  to find out the same and what would be link between the shipment number (TKNUM) and the condition table KONV.
    Thanks in advance,
    Arshad

    Hi,
    You don't have the direct link between shipment number and condition table.But it is linked with shipment cost document number FKNUM ( Tbale VFKP).
    Shipment cost document number for a shipment number can be obtained from the table VTFA ( Field VBELN).
    Select the KNUMV ( Document cond.No ) from the VFKP table and select the reqd values from KONV table.
    I hope this helps you!
    Thank you.
    Regards,
    Karun M

  • Purchase Rebate is adding to Material cost value field

    HI,
    When i execute purchase rebate scenario, that amount is adding to Material cost value field in COPA report. Kindly tell me what isthe problem and where is the link between this.
    Thanks
    KB

    In customizing the integration of other modules with COPA you have keep in mind the sign logic because it may be different for values coming from different modules.
    Example: In our system revenue-reducing sales conditions come to COPA with a negative sign. In postings that come directly from FI to COPA, a negative sign means earnings. So we cannot assign any Fi account for direct posting to COPA to the same value field as SD conditions, because the sign logic doesn't match. We have to use different value fields and then get the formulas right in creating COPA reports to get the correct result in COPA.
    I think your problem here is of the same kind: Rebates from purchase seem to come with the same sign as cost of goods sold AND go to the same value field, although one consitutes cost and the other a reduction in costs.
    I think you have to get your rebates to post to another value field. Are those rebates an MM-condition or do they go to COPA through an assignment of FI-account to a value field?
    Regards
    Nikolas

  • View labor and material costs in plant maintenance work order

    Hi
    I am aware we can bring in the costs in the work order through Activity types and assigning the costs to the acitvity type.
    Is there anyway we can bring in the actual cost for the work performed by the associate? should we link the work center to HRMS?
    Please advise. I need your valuable input for all the points below.
    Main points that need to be addressed:
    1. Each associate that is capable of confirming hours to a work order needs to be assigned an hourly rate that is reflective of the actual cost for the work performed by this associate. These hours are then tracked through the work order to give a cost for labor assigned to that particular job.
    2.Any materials used in the performance of the required task(s) dictated by the work order will be assigned to that order. These materials can be assigned through SAP purchase requisitions, tool crib spot buys, or procurement with a purchase card.
    3.Standard reports need to be created so we can track the total maintenance costs for any level of the equipment hierarchy as currently set up in SAP. When this report is created it should show the total maintenace costs for all the levels of the equipment hierarchy broken down into labor cost and material cost.  I am using Tcode IW37N and IW40 . Is there any suggestion?

    Greetings Chandra,
    1) You will need to create Work Centres for your associates and create the Activity Types. You can default the Activity Type for each Work Centre and maintain the rate for the activity via t-code KP26 planning.
    2) Planned and unplanned Purchase Requisitions for Components with category N will debit the order with material costs. But what do you mean by "tool crib spot buys" and "procurement with a purchase card"? You may need to develop a solution to do such postings to the Order (or for purposes of Cost controlling, manual activity allocation similar to confirming work may be desired such as Manual Activity Allocations via CO transactions (KB21N), unless you can cover that with Purchase Requisitions and POs with "F Order" account assignment.
    3) MCI8 Cost Report should be suitable for you, once you set up the Value Categories & Cost Key Figures.
    See
    PMIS Cost Analysis Reporting Overview
    Maintenance Cost Key Figures in MCI3 and MCI8 Reports
    PM Order Value categories and costs display

Maybe you are looking for

  • Can't find "Libraries" under Windows drop down menu in Adobe Illustrator CC on Mac?

    I was searching forums to solve my issue (as stated in the subject) but could not figure out why I am unable to see "libraries" on my freshly updated Illustrator CC w/ Creative Cloud. I am attempting to use an image captured in Adobe Shape but am una

  • How to do equivalent of Mainframe batch jobs in Oracle

    Hi Everybody , We are considering to move our application from mainframe to Oracle , our present day application relies heavily on mainframe batch jobs for report generation and other purposes, I was wondering what are the similar batch options we ha

  • USB Headset Prob

    Hello, I installed a SB X-Fi XtremeGamer a few hours ago and I encountered some problems. The card and the software included work normally when normal speakers are connected, however, my USB headset (Speed-Link Medusa 5. USB) does not seem to coopera

  • Premiere Pro CC very buggy timeline

    Hi everyone! I can't seem to find a relevant answer to this problem I've been having with Premiere Pro CC. Basically, I have a timeline with four video angles (not trying a multiclip edit; they are just in the timeline) and a few sources of audio. As

  • Regarding sqlserver

    Hi, what is the difference between stored procedure and function in performance wise?