LTP Planning for Subcontracting Purchase Order
Hi All,
I am doing LTP run for the Finished Material.
Finished Material is having few open subcontracting Purchase order's.
When I take the LTP run in MS02, system is considering the Open PO's and adjusting (netting) it with the Planned independent requirements of finished material. This is ok.
But the planning is not creating depending procurement proposals for the child items.
It is subcontracting PO of finished material, system suppose to create the dependent requirements.
In the MRP run it is working fine in MD02. But not working in LTP planning run in MS02 Transaction.
Rgds / Shailendra
Edited by: Shailendra Hadkar on Apr 7, 2010 10:44 AM
Hi All,
I have found one BAdi u201CMD_CHANGE_MRP_DATAu201D for showing up Subcon requirements in MS04 for child materials.
This BADI "MD_CHANGE_MRP_DATA" requires to implement using method "CONSIDER_RESB".
But implementation of this BADI using method "CONSIDER_RESB" will open up Dependent requirements/reservations of phantoms in phantom assembly planning and other reservations also.
How I can implement this BADI for specific Subcon requirements or Specific MRP element??
Regards,
Shailendra
Please refer below post by Nethi Venkata R...
LTP Doubt
Similar Messages
-
Problem for Goods Receipt for Subcontracting Purchase Order
Dear all,
Presently, we are using SAP version 4.6C and we need to introduce GR for
Subcontracting Purchase Order. We have developed a ABAP program to handle
subcon Goods Receipt by uploading flat-files from our subcontractor. The
scenario is as follows :
Goods Receipt for Subcontracting Purchase Order
1. In the ABAP program, function BAPI_GOODSMVT_CREATE will be used for goods
movement.
2. Data provided to the function are as follows :
- Posting date
- Document date
- Material number
- Plant
- Storage location
- Batch
- Movement type (101)
- Quantity
- Purchase order number
- Purchase order item
- Movement indicator (B - Goods receipt for purchase order)
3. The function will do data verification and automatically determine GI
item for subcon stock:
- Movement type (543)
- Special stock (O - parts prov. vendor)
- Material
- Quantity
- Plant
Our problem is that :
Only the GR item in the interface is to be transferred and the GI item is
determined by the system. So, the quantity for subcon stock cannot be
changed using this BAPI. Then the system will continue processing the goods
receipt and create material document.
Manually, by using transaction code MIGO, the user can display the subcon
stock data and then change the quantity.
By using transaction code MB01, after the user fills in all the GR fields,
the system comes to line item 002 (subcon stock data) and then quantity can
be changed.
As per user requirement, quantity for GI item must be same with the quantity
that has been transferred to subcon vendor in Delivery for Subcon
(transaction code VL02N).
We cannot achieve this requirement by using the BAPI mentioned above. Would
appreciate any valuable help from anyone who is able to help us on this
matter. Are there any other BAPI's that can help us to achieve the same
result ?
Thank you in advance and best regards.As far as i understood the problem I suggest u to create the
BDC according to user actions that are performed in he manual
operation.
I can't say that the BAPI performs the exac solution what you want.
I have done some BDC work using MB01 and suggest you to be careful
and try to keep the complete in the logic as some chages in rows in BDC will
change the complete scenario.And throw correct quantity val in correct
material
row.
This methodology will help u even in mass uploads.
Or in case of automation u can perform the call transaction BDC in
background mode.
so As per my understanding bdc program is the solution. pls try and let me
know. -
Good receipt problem for subcontracting purchase order
Good receipt problem for subcontracting purchase order
with account assignment type E.
After update to ECC 6.0. Do good receipt for subcontracting purchase order with account assigment 'E'.The system show the error message(KI235)----Two cost elements (Change in Stock (Subcontracting)&Outside processed fee) haven't CO account assignment.but the field status for sale order is option entry , when I default cost center for the cost element in OKB9.the system post the material document and generate the following accounting document.
Doc.Type : WE ( Goods receipt ) Normal document
Doc. Number 5000056065 Company code 1000 Fiscal year 2007
Doc. date 2007.12.04 Posting date 2007.12.04 Period 12
Calculate Tax
Doc.currency HKD
tm PK Account Account short text Tx Cost Ctr SaleOrder Amount
1 89 13500000 Stock-Work in proces 1007823 10 274.4
2 96 21210010 GR/IR Clearing 1007823 10 205
3 91 41010102 Chg in Stock(Subcon) 10901099 1007823 10 274.4
4 86 41031000 Outside processed fe 10901099 1007823 10 205
5 99 13500000 Stock-Work in proces 1007823 10 69.4
6 81 41010101 Cost of Prod (Subco) 1007823 10 69.40
My problem is:
When use MIGO to do good receipt for subcontracting Purchase order, for consumption account((Change in Stock (Subcontracting)-41010102&Outside processed fee--41031000) ,why the system dont recognize the sale order filled as CO account assignment?Dear fanny chen
Did you get a solution for your open question?
I`m facing the same problem, so any help yould be appreciated.
Regards -
Posting of Components made compulsory for Subcontracting Purchase orders
Hi
I am working in ECC 6.0. In case of Goods receipt for subcontracting Purchase Orders, does the child quantities automatically changes when i change the default quantity of Header material according to the BOM relation ? I found it is not happenning.Please inform is this standard?
Also i can post the documentfor header material without the components,by manually changing the quantities for Child items .Kindly give a me suggestion by which this can be controlled.
Regards
ArvindHi,
1.
The component changes as per the header material in MIGO when you want to do GR. Please take care that the components musn't be exploded when you change the qty of the BOM header material. If they are exploded, collapse them ("close the explosion"), after that change the qty of header material and when you explode the components again you should get the proper quantities (this button is in the line of BOM header material).
2.
As per my best knowledge, in standard system you cannot restrict/control the change of component quantities. The cause of it might be that the quantity of components may differ from the rates defined in the BOM and the user HAVE TO CHANGE the quantities as per the real consumption.
Solution might be training. If the user intentionally changes the component quantities, this is a HR issue..
Regards,
Csaba.
Edited by: Csaba Szommer on Dec 26, 2008 5:14 PM -
Message type for generating IDOC for SUBCONTRACTING PURCHASE ORDER
Hi All,
I have to generate IDOC for PO creation or change .
I am using IDOC_OUTPUT_ORDERS and IDOC_OUTPUT_ORDCHG.
The messagetype.idoctype I am using is ORDERS. ORDERS05 and ORDCHG. ORDERS05.
Now the confusion is regarding whether this message type will work in case of SUBCONTRACTING PURCHASE ORDER as well ?
As I have gone through some websites and came to know that I will have to use PORDCR1.PORDCR102 specially for subcontracting.
And programs we need to use is BUS2012_ICH_R3 instead of RSNASTED and Form Routine SEND_PORDCR1 instead of EDI_PROCESSING.
Purchase Order Collaboration scenario - Not generating IDOC in ECC
http://www.erpgenie.com/faq/edi_purchasing.htm on this site question no 8.
Subcontract PO IDOCs
I hope your experience will help me .
Please reply ASAP.
Edited by: uttam27 on Dec 4, 2011 1:47 PMThere is a generic function to create change pointers for all message typs - 'CHANGE_POINTERS_CREATE_DIRECT'. This is triggered only if you configure your message type to create change pointers from BD50.
Once you activate it do any change to orders you can see change pointer tables BDCPV filled. Then BD21 will read the changes and generated outbound idocs accordingly. -
Batch determination for subcontract purchase order component.
Hello
Is it possible to do batch determination for the subcontract purchase order componet, then bring the component batch to the outbound delivery directly from purchase order? If no standard, any user exit or BADI... can do this also good for us.
Thanks
HailiangHi
Yes I can manual input batch number, but I want the system select the batch in stock base on the batch classification. I can not find the batch determination function the the component detail screen.
Best Regards
Hailiang -
Bapi for subcontracting purchase order
Hi,
is there a BAPI allowing to create a subcontracting purchase order?
Best regards.Hello,
BAPI_PO_CREATE and BO: BUS2012.
BAPIEKPOC = ITEM_CAT (3 - Subcontracting)
Regds, Murugesh AS -
Creation of delivery for subcontract Purchase Order
Hi All,
I am trying to create delivery for subcontract PO. ME2O transaction creates delivery but doesn't link PO to delivery . Is there any SAP table where we can see link of subcontract PO to delivery created throug ME2O?
Business don't want to use MB1B transaction because it doesn't create delivery inturn doesn't create any paper work(Pick list or Packing list).
Is there any way to create delivery based on subcontract PO?
Thanks in advance.
Sonali.You have to do Sub con PO setup in Img customization. You can be able to print all ur required documents during MB1B also. Presently I am doing exact the same setting for my present project. Complete Configuration required under
Img->MM->IM and PI->Output Determination.ABAP help will be required to design the layout for pick list and packing list.Let me know if you need more information.
Cheers! -
BAPI for GR against subcontracting Purchase order
Hi Friends,
I need to make the GR against the Subcontracting Purchase order, for that I need the BAPI. can I use BAPI_GOODSMVT_CREATE.
The problem is how to find out the BOM Materials. Can anybody provide me the source code for the reference of GR for Subcontracting Purchase Order.
Thanks in advance.
KrishanHi krishan,
Refer to the link below for sample code of
BAPI_GOODSMVT_CREATE:
http://www.sap-img.com/abap/bapi-goodsmvt-create-to-post-goods-movement.htm
also refer to the link below for BAPi's:
http://www.sapbapi.com/bapi-list/
With luck,
Pritam. -
Subcontract purchase order release strategy
Iu2019m trying to customize a release strategy for subcontract purchase order (SC) but PO document is not taking any release strategy.
Now Iu2019m not sure about SAP standard allows to have a release strategy for subcontract purchase orders (SC)?
Thanks for your help.Hi,
1. Please check this link (it is for PR but I think might be useful):
http://www.sap123.com/showthread.php?t=59
2. Remark: You can use user exit EXIT_SAPLEBND_002, M06E0004 if you want to make your release startegy sensitive for item category - however this was not question.
3. On additonal data tab of the characteristics (assigned to the class), can you see table CEKKO and its field name in the suitable fileds? (CT04)
4. Does your strategy work for other purchase orders (with other document types)?
5. Please check classification settings under your release startegy, whether the values defiend there are in harmony with the values defined in the subcon-PO (I mean purch doc. category, purchasing group, order type, plant). SPRO > MM > Purchasing > PO > Release procedure for POs > Define Release Procedure for POs - here choose release strategies...
Regards,
Csaba -
Components for the Subcontract Purchase Order
Hello All,
I am trying to create a subcontract Purchase Order, I have created a subcontract Purchase Info Record using ME11 for the Finished Goods and also defined the BOM using CS01.
When using ME21N, I have defined the line item as L Category. In the Item Detail -> Material Data tab, there is a "Components" and "Explode BOM" button. When I click on the "Components" button, I see the list of raw materials defined in the BOM. I know for subcontracting that we are able to enter the components manually or can be generated via BOM explosion. I would like to ask how can I enter the components manually as when I try to delete an item it said not able to do so.
Can anyone please help.
Thanks.Hi..
In Subcontract PO, BOM can be deleted by selecting all BOM line items then go to Edit and select Delete tab .
To enter the component manually click on Collective Entry Tab in PO BOM and after that you can enter components manually.
So 1st delete the BOM and then add BOM manually by above procedure.
But as a standard Practice CS03 BOM only to be changed and then explode the PO BOM.
Regards
Vishnu -
Subcontracting Purchase Order from ECC sent to APO creates a Plnd Order
Subcontracting Purchase Order from ECC sent to APO creates a Plnd Order with the same Purchase Order# in APO.
We want to influence the source of supply for this internally APO created planned order.
For this, I would like to know what user exit can be used, I have already looked at
(1) BADI: SOURCE DETERMINATION
(2) CIF INBOUND EXTERNAL PROCUREMENT on APO side.
Any other user exits or has someone worked on this scenario.
Thanks
Kumarsources of supply for planned orders can be changed with the following BADI method:
Definition name /SAPAPO/RRP_SRC_EXIT
method RRP_USEX_SOURCE_FILTER -
How can I select alternative BOM when creating subcontract purchase order?
In our business, a finish good material always has different production versions at the same time. Each of production versions has its own alternative BOM. When I create a planned order, I can select wanted BOM through specifying production version.
But, when I creating subcontract purchase order, there is no field for me to specify the production version or which alternative BOM I prefer. In this case, I need to create a planned order at first. And then, convert the planned order to purchase. Only through this way, I can create a subcontract purchase order with my wanted BOM.
So, I wonder if there is any way to select alternative BOM directly when creating subcontract purchase order.
Thanks a lot!
Regards
RobbieDear Mr. MM
can you give me additional information about your solution?
BUT I would not expect the sytem to offer you during the Purchasing cycle the different Production Versions as it is not meant to be. I remember having the same requirement some time ago and we solved it the way I described above, additionally we created a Pop up window with a user exit during the PO creation which offered the different production versions and if the one linked with the quota arrangement, the standard PV, is used in the PO.
We also have the same problem, we activated businessfunction SCM_GEN_02 so that it is possible to have several production versions for one supplier, but unfortunatly it is not possible to change the production version in the purchase order. (business function does not seem to be very integrated)
So i would be very interested in your solution because acually it seems that i have to modify the sap standard.
Thank you and best regards
Lisa -
Open Po quantity in subcontracting Purchase Order
Hi,
In case subcontracting purchase order,If order quantity 10 and recept quantity is 05 then in delivery shedule tab I didn't got any open purchase order quantity means 05 quantity why?
Thanks and Regards
Anil PatilHi Anil.
Please check the following fields in schedule line:
- 'Scheduled qty': 10
- 'Delivered' (quantity): 5
(This means the goods were partially delivered for the PO)
If your situation is this you don't have to expect SAP to create new shedule line I think.
I think you have to modify the schedule line manually if you want a 'Delivery date' different from that was defined in the line of the PO item.
BR
Csaba -
Link from delivery to subcontracting purchase order
Hi Guys,
anyone know how to pick up the link from a delivery (LIKP / LIPS) and the subcontracting purchase order (EKKO / EKPO) which was used to create it?
I'm not sure such a link exists - the PO does not appear in the document flow of the delivery, and the delivery does not appear in the history of the purchase order.
My users want to print the PO number on the delivery document (not unreasonable?) but I can't find a link anywhere...
Mick KellyHi Mick,
I assume that you mean the outbound delivery created in transaction ME2O to deliver components to your subcontractor.
There is no link possible between the subcon.PO and this outbound delivery. Because the component requirements in ME2O can be the result of multiple subcon.PO's. When you create the outbound delivery, it contains components for the cumulated requirements (so that can be for multiple PO's). That's the reason that there is logically no link possible between PO and the outbound delivery.
Kind regards, Dick Hendriks.
Maybe you are looking for
-
HP LaserJet 6p and NetGear PS-101 Wireless Setup Driver Issue???
Does any one out there know how to make this combination work? I use it on my wireless network all the time for PC's but can not get it to function properly on my iMac. The NetGear is plugged in the back of mp Laser Jet and a Cat 5 connects to my Bel
-
Creation of Target group.
Hi All, I having one urgent requirement, we have maintained the Ztable for maintaning the information of Vehicles against Business partners. The Fields in the said Ztables are Vehicle type, vehicle Reg Number and BP number. I want to send the mails u
-
How can i make the report previewer show a PDF file instead of HTML?
Hi there, i made a report which can be called within a form by a button. This report is a PDF-report. I also have an option in the application to start the report from the menu. Then i get the Launch Report Form by Headstart. Here i can fill in for D
-
I need to figure out how to get the mail page to load properly in Firefox. Can anyone help? I have been having to open Explorer to get my Yahoo mail
-
Can I run a podcast and an app at the same time?
Can I run a podcast and an app at the same time?