Mass update for production and planned order MRP controller

Hi Gurus,
It's anyway possible to mass update MRP controller for Production orders and  Planned orders. If any please provide me step by step process.
Thanks,
B.Deethya.

I feel You have changed the MRP controller in Material master and want to incorporate same in production order & plan order.
For Planned order Run MRP with delete and recreate mode, system will create a new plan order with MRP controller in Material master
For production order, Mass change is not possible, create a simple BDC or LSMW, And change the MRP controller

Similar Messages

  • Colective Settlement and "CLSD"Status for Production and Maintenance Orders

    Hi dear experts,
    Is that possible to use transaction KO8G for collective settlement of Production Orders? Apparently it only works for Maintenance Orders.
    The same applies for transaction CO99 for getting "Closed" status in Orders. Apparently it does not take the Production Orders, even if the selection "With CO Production Orders" is active. Is there any additional configuration we should do?!
    We would like to do settlement (and mass set "Close" status after) for Production and Maintenance Orders at the same time.
    Thanks in advance,
    Lígia Moreira

    Hi,
    You can use CO88 for settlement of production orders. Normally, CO99 should take production orders if the flag is switched. Do you receive any error when you do it?
    Regards,
    Eli

  • Exception message for PrdOrd and Planned order

    Hi Gurus,
    It possible based on prdord and planned ord we need to get the Exception message information. It's there any standard transaction code or any sqvi report?
    Note:
    Exception Message:
    10 - Reschedule in
    20 - cancel
    05 - Opening date in the past
    26 - Excess in individual segment
    Please find this information in MD04 (single order). i am looking for same time multple orders with exception message report.
    Thanks and regards,
    Deethya.B

    Hi
    You can use MD06 with refrence to you plant and MRP Controllers. Also you can define your own traffic lights so that based on these you get your exception messages.
    Hope this helps,
    Regards,
    Ravi

  • Modeling dummy product and planned orders

    Hi SAP Gurus,
    I have requirement where i need to model particular business requirements on subcontracting and the same is resulting in need of modeling of dummy product and dummy planned orders. Please share your inputs on what would be impact of dummy product and dummy planned orders in ECC. and also how to make sure that it does cause any issues in costing.
    I am modeling subcontracting requirement and i need to create following master data.
    All the below products are at plant P.
    P has the components as Q_D
    Q_D has the components as Q
    Q has the components as R
    Where Q_D is the dummy product produced at plant P.
    P and Q are subcontracted items to the vendor V.
    P is the finished good, Q and Q_D are Semi finished goods, R is raw material.
    When we plan we are creating Purchase orders for P and Q. And Q_D is made inhouse and we need to create planned order for it. how do we handle the planned orders created for Q_D. we dont want them to convert to production orders. we want a way to clear off these dummy planned orders once we close the POs of P and Q.
    Please advise.
    Thanks.
    Jagadeesh

    Hi senthil,
    Check if the forecast date is beyond PPDS horizon.
    Also in product master on PPDS tab, you should maintain 4 in PP Planning procedure.
    Bye.
    Nitin

  • Production and planned order not scheduling

    Dear Experts,
    Created new plant ,scheduling parameters,order type parameters ,confirmation parameters.
    Scheduling parameters: Detailed Scheduling ,Forward etc.
    created BOM, Routing,WC.
    Maintained Work center Scheduling Tab formulas entered,Routing Machine,setup time entered.
    System showing at the of creating production order Scheduling Start time and end time is same.
    scheduling not done in production order.
    Anyone explain process for scheduling
    Regards,
    Naresh Reddy.

    Hi Naresh,
               The problem is mainly due to the work center scheduling formulas only. Maintain the scheduling formulas as SAP001 for setup and SAP002 for machine. In OPU3 check the automatic scheduling check box, adjust dates as 'adjust basic dates , adjust basic requirements to operation date' and recreate the production order.
    Let me know if u are still facing the same problem after doing these settings.
    Regards,
    Krishna Chandra

  • Planned Order for stock and planned order for customer requirement

    Hello everybody
    I want to make a different, in MD04,   between the planned order for stock and the planned order created for a customer requirement
    Thank for your help

    Hi,
    True planned order are generated for both the cases but the planned order generated for sales order will have sales order number in the below column and for stock will show independent requirement. Mainly no sales order reference will be there for make to stock scenario.
    Hope it will help.
    Regards,
    Alok Tiwari

  • Updation for Production and Proportion unit in MM02 transaction

    Hi expert,
    Requirement is i need to change proportion/prod unit in MM02 i found one Bapi the Bapi name is 'VBWS_UOM_MAINTAIN_DARK' but it is not working can you provide test data for this and last chance i wrote BDc the values are fetching in debug mode but it is not reflecting in MM02 trnasactions. experts can you please give any solution for this.
    Thanks.

    Hi
    material master purchase order long text
    you can use through BDC or LSMW it is possible,
    here we need to check in lsmw  Direct input mentod Program name "/SAPDMC/SAP_LSMW_IMPORT_TEXTS"  object name (0001) method(0001) program type (D).
    Header we have ---  MATNR and TEXT ID
    Item ---LINE(Text line).
    in header- for NAME and ID map the source fields MATNR and TEXID respectively.
    OBJECT and SPRAS pass the constants.
    in Item--for TEXTFORMAT pass the constant '*' and for the TEXTLINE map the input field LINE of the ITEM structure.
        or else u can check in SE37 'CREATE_TEXT'   , in that function module check it object Id , name , spras, lineitem,  language "E"
    here i mention example of text flat file,
    H  100-100 best
    longtext1

  • Program PPBICO40 for conversion of planned orders to production order

    Hi,
    The program PPBICO40 is for conversion of planned orders to production orders in the background job.But while set up of variant it is asking me for peson who created error folder and recipient.I want to know the significance of these two fields and how these are useful.
    Please throw some light on this.
    Thanks in advance,
    Ravi

    Dear,
    PPBICO40 the non-convertible planned orders are put together in one batch input session and can be postprocessed with batch input tools. It is possible to create a separate error session for each MRP controller.
    Error folder for each MRP controller: creates a separate error folder for each MRP controller.
    Receive folder according to view: If the indicator is set, the error folder is not deleted after processing in batch input.
    Creator of the error folder: User who is entered as creator in the error folder .
    Send mail: Sends a mail to the respective MRP controllers during the creation of a batch input session. If the indicator 'Error folder per MRP controller' is not set, the mail is sent to 'Recipient (alternative)'.
    Express document: sends mail as an express document.
    Recipient (alternative): Recipient of the mail, if no recipient is specified in the material requirements planning master record of the MRP controller responsible .
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Set new Required Field for MD14 and MD15 for conver from Planned order to P

    Dear all,
    I would like to set new required field (Purchasing Organization)  in T-CODE MD14 and MD15 for convert from Planned Order to PR. What's should I do?
    Please help, I 'm new for MRP.
    Best Regards,
    Kate

    Hi Kate,
    You are not on the right track; MD14 and 15 will choose the PLANNED ORDER population for the conversion. In planned orders there's NO PURCHASING ORGANIZATION DATA (normally)!
    So even if you managed to put the field on the screen, it will not do anything that makes sense.

  • Production and Service order Release Log updation

    Hi,
    Can any one help me how to update the release log of Production and service order.
    I have a requirements to add new custom logs to the production and service order release process.
    sudha

    As far as I know the standard behaviour is that the PR is created upon order save and not upon the status of the order or items changing to released.
    To get around this you can set user status and use status management to prevent the PR getting created or use the BADI CRM_SRV_FIND_LOG_SC to supress creation of the PR.
    Hope this helps.

  • Table for process order and planned order in apo

    I would like to know the table for stratagy profile for particular process order and planned order.
    in /sapapo/rrp3 there is one filed RECEIPT/Reqt.Element ( process order ) for this  field which table it is coming and i required particular strategy profile for that process order .
    Please help me the table in apo.

    Hi Venkat,
    This value is stored in structure /SAPAPO/RRP_ORDREQ_STR
    under the field name EXTRA.
    You can check the details of the same in transaction se11
    Regards
    R. Senthil Mareeswaran.

  • Settings for the relation of requirement type and planned order type

    Dear Gurus
    Where we maintain the settings for the relation of requirement type and planned order type?Actually I have maintained strategy 60 for a particular material (planning material) so the requirement type is vsev and along with that the planned order type is coming is vp i.e non convertible planned order.That is ok the system is behaving right.But nowhere I can find the setting of vp with vsev how the system is picking vp?
    Regards
    Sandip Sarkar

    Hi!,
    That is an inbuilt sytem setting and you can't change that.
    Regards,
    Uday

  • BAPI or FM for scheduling a planned order (like MD11 or MD12)

    Hi guys.
    We are working with a group of materials and planned orders, in order to modify and create new planned orders depending on the stock per each material. So we use MD12 to 1) modify the quantity in the order, and MD11 to create new planned orders for the rest of stock for this material.
    For process of creation we don't have problems (BAPI_PLANNEDORDER_CREATE makes its work well ), but when we want to schedule the new planned order created before via FM or BAPI, we cannot see any results in MD12.
    I mean, when a planned order is scheduled via menu button, a new tabstrip appears in the transaction with dates. So this similar action we've tried using CX_PLANNED_ORDER_SCHEDULE or CX_CRP_PLANNED_ORDER_SCHEDULE but there was no change.  If we execute the Schedule button action, in table PLAF (master of planned orders) apears a new number in field PLAF-BEDID related to MRP.
    So guys, could you please help us how to get this issue? As last option is BDC, but BDC's and me are not good friends because its performance. So please, any suggestions?
    Thanks in advance!
    Raul Romero

    Hi guys...
    Sorry for the long time without an answer, which I'm sharing you now:
    1. In order to perform the proccess of scheduling, you have to record the steps from menu bar in your batch input. I mean: (1) set values into fields CRHARBPL-LOW () and CRHWERKS-LOW
      PERFORM set_batch USING: 'X' 'RCCRY000' '1000',
                                      space 'BDC_CURSOR' 'CRHARBPL-LOW',
                                      space 'BDC_OKCODE' '=PLNG',
                                      space 'CRHARBPL-LOW' p_arbpl,
                                      space 'CRHWERKS-LOW' 'PR01'.
    (2) After you ordered your list of planned orders or production orders, loop your internal table and per each order record these commands (these simulates the popup option to select the order you want for scheduling and mark it in the dynpro you are processing):
      LOOP AT gtd_tabofplan INTO gvc_tabofplan.
        PERFORM completa_bi_campos USING: 'X' 'SAPLPLAT' '4000',
                                        space 'BDC_OKCODE' '=Z021'.
        PERFORM completa_bi_campos USING: 'X' 'SAPLCY19' '0120',
                                space 'BDC_CURSOR' 'CYMARK-VALUE(02)',
                                space 'BDC_OKCODE' '=BACK',
                                space 'CYMARK-VALUE(02)' gvc_tabofplan,
                                space 'CYMARK-MARK(01)' space,
                                space 'CYMARK-MARK(02)' 'X'.
        PERFORM completa_bi_campos USING: 'X' 'SAPLPLAT' '4000',
                                space 'BDC_OKCODE' '=SL25'.
      ENDLOOP.
    (3) Set the SAVE operation.
      PERFORM completa_bi_campos USING: 'X' 'SAPLPLAT' '4000',
                              space 'BDC_OKCODE' '=SAVE'.
    Hope you' ve succeeded in this task, let me know if you've another questions.

  • Mass update of product master (lock material record)

    Hi! Does anyone know of any program that I can use to carry out mass update of product master in SRM? I am specifically looking at locking the materials. I originally intended to use LSMW and create a recording for it. However, the recording didn't work - when I clicked on the open button so that I can key in the product id, it returns back to the recording / LSMW transaction with the screen data. I did not even have a chance to proceed further.
    Any idea would be appreciated.
    Regards
    SF

    really . though you are ECS mode .
    material master must be there  right ?
    How your SRM PO will reflected ( indeed really creates in ECC i.e copy of srm PO).
    confusion here
    can you create a SC for local material and order a successful PO ?
    i know there is a product check in catalog web services - in SRM product master not necesary but your ECC must have material master right..
    Muthu

  • Dependant Requirements and Planned Orders

    Hi,
    For dependant requirement, question is whether once the planned orders (of independent requirements) are converted to production orders, then only will the dependant requirements be converted to planned orders…or it is converted once independent requirements are converted to planned orders? I.e. independent requirements are blown down all the way in MRP.
    Thanks.
    Rgds,
    Sue

    Hi,
    Let us take some example so that it is easier to explain.
    Material A - Finished Good
    Material B - Raw material
    PIR generated for A - 100 Nos , MRP is run and Planned order created for A - 100 Nos. Now
    For Mtl B Dep reqt is generated for 100 Nos.
    If No stock is available then a planned order for 100 nos generated.
    IF Stock is availabel then no planned order is generated.
    When production order is created for Mtl A then the "dep reqt" status of Mtl B changes to
    "ordres"(order reservation)status.U can check this MD04.
    Thanks and regards,
    Rajesh

Maybe you are looking for

  • EBP PO : Unable to duplicate/copy  item,GR_NON_VAL issue

    Hello, I am using SRM 5.O . In Process PO when I go to create the PO with more than one line item following issue comes : When I entered one line item and check its ok when I click on  <b>Duplicate Selected</b> Item or <b>Copy</b> push button than ch

  • REFInd problems

    Hey everyone, So I am a noob to Arch.  I am trying to install Arch on my Lenovo z580 laptop and nothing I try works.  I did several test installs on VirtualBox before trying to install Arch on my actual hard drive and I managed to get every one of my

  • Can MOPZ be used without installing Diagnostic Agent.

    Hi, I need a clarification. In Solution Manger 7.1 Version, can I use Maintenace Optimizer (MOPZ) to download SP's for a Managed System without prior installing Diagnostic Agent on the Managed System? If Yes, please write a brief procedure as below.

  • Deleting recent Adobe download

    3 Days ago, I did a very silly thing!  I installed the latest Adobe reader in order to download an attachment which I could not open in a mail.  Ends up, I did not even need that attachment!  Now, Adobe is blocking daily sites I use in my teaching jo

  • Gcc is joh, g++ is no

    Hi, I'm trying to compile this: #include<stdio.h> #include<stdlib.h> #include <ctype.h> #include<string.h> #include <sauv_oracle.h> void err_report(Cda_Def *cursor) { sword n; text msg[512]; /* message buffer to hold error text */ if (cursor->fc > 0)