Materail Master - MRP view 4

Dear experts,
pls explain MRP view 4 - Follow-up matl field?
what use? how to use?
Regards,
Sankaran

Hi,
     A particular material X to be discontinued. Instead of that you want to use some other material Y. For that reason this field will use.
    In MRP 4 view of material X , make discontinued indicator tick. Give effective date.
Give the follow up material no.Y.
Result: From effective date, material X will be replaced by material Y.
Reward if useful.
Regards,
Dharma

Similar Messages

  • Material Master MRP View not be created till Basiv View is created

    Hello All,
    I need an information where i would like to know if an MRP view in a Material master can be restricted without the creation of the Basic View. Basically an MRP view is getting created even though the Basic View of material master is not there and it needs to be stopped.
    Thanks for your inputs.
    Ismail

    Dear Syed ,
    If you want to prevent end users update other material master views , you can apply the concept of SAP note 545380 - FAQ: Authorizations material master , with this you will not more problem with this kind of problem.
    Hope this can help you.
    Please let me know if my thinking about your question is correct.
    best regards,
    Carlos Moçatto

  • MRP view in material master creation

    Hi Guys,
    Can anyone tell me how to change the settings for field dependency. My requirement is to use only the filed for "reorder point" in MRP view and do not enter any other data like MRP type or lot sizing etc.
    I have tried changing the setting for field selection group for MRP type etc but whenever i enter the value in Reorder point field it asks me for MRP type and does not allow me proceed...
    Thank you for your help.
    Regards,
    Siddharth

    Hi
    You cannot change that dependency as it is done through program code and not thru config.
    If you want reorder point only as an info field and not for actual Reorder point planning, I suggest you to explore any other unused information field in the masterial master.
    You can also use classification
    Best regards
    Ramki

  • MRP view maintenance for Material Master

    What is the basic entry for R3 material master, if, I want EBP below condition works:
    Stock in R/3 sufficient: Shopping Carts creates MatReservation.
    Stock in R/3 not sufficient: Shopping Cart still creates MatReservation, and when run MRP (in R/3), it gives Purchase Requisition, with the exact shortage qty.
    Info: We have set customizing in EBP so that every follow-on document for Shopping Cart will be Reservation.
    -Mimi-

    In R/3  , the material should have MRP view and all planning related settings ...
    wr u want to go for consumption based planning or deterministic planning .
    Based on the planning procedure setting in MRP views of the R/3 sytem , PRs will get generated.
    This is what u are looking for .. otherwise post your feedback...
    Regards
    Mani

  • How to delete MRP view data after create in Material master data ?

    Hi all ,
          After user  create a useless MRP view data in Material master data , how to remove it ?

    Hi
    Material master once created cannot be deleted.Only thing u can do is to mark it for deletion
    Go to Logistics > Materials management > Material master > Material > Flag for deletion > Immediately.
    Give the necessary data that is needed for the view you want to delete.
    Press and flag the view you want to delete.
    Now the view is flagged for deletion. This means that it's use is limited and it will be cleaned up or really deleted at the next clean up of the system.
    regards
    Anand

  • Re MRP Views of Materail

    Hi All,
    Actually we are trying to download all view details of material from MM03 T-code.
    We need to fetch the value of the fields Planning Materail (<b>PRGRP</b>) and the Planning Plant (<b>PRWRK</b>) for the MRP view in the MM03 Transaction.
    We tried with MARC and MARA Tables and the tables suggested in some of the previous posts in SDN by others n still we are unbale to find it. If some1 has faced similar problem pls do suggest psbl way to reterevie the data.
    Help and Suggestions will be much appreciated.
    Regards.
    Ramesh.

    hi ramesh,
      try with these tables
       <b>VBBS</b> - Sales Requirement Totals Record
       <b>VBBE</b> - Sales Requirements: Individual Records
       <b>VBAP</b> - Sales Document: Item Data
       <b>PBVPV</b> - Material index for consumption of planning
       <b>MDIP</b> - Material: MRP Profiles (Field Contents)
       <b>LIPS</b> - SD document: Delivery: Item data
    Cheers
    Alfred
    Reward points if it is helpful.

  • Special Procurement MRP View VS. Costing View

    Hi Experts,
    What's the difference between the 2 Special Procurement Key in the MRP veiw and the Costing View?  Should they always be the same?
    Thanks,
    Kumar

    Hi,
    MRP:
    You use special procurement when you want to be able to override the procurement type in the material master or define the procurement type more precisely.
    If the procurement type is in-house, you can nevertheless force the system to ignore the BOM and routing, and process the material as if it were externally procured, by specifying the special procurement as external.
    Costing:
    If you enter a special procurement type in the Costing view of the material master record, it will be used in costing.
    If you do not enter a special procurement type in the costing view of the material master record, the system will use the special procurement type in the MRP view.
    For further Clarification revert.
    Regards,
    S.Babu

  • MRP views in MM02

    I need to create a Screen Variant  and apply to a Z transaction which only allows users access to change MRP Information u2013 MRP1, MRP2, MRP3 and MRP4 tabs. in the Material Master.
    I do not want to give everyone access to MM02 u2013 Change Material Master as this allows them to change all master data within the Material.
    I only want them to be able to change MRP1, MRP2, MRP3 and MRP4 tabs.
    How to make the screen variant for this. I haven't worked on screen variants..Just need details on that. Please help.
    Edited by: yorker on Jun 27, 2011 9:08 AM

    Hi,
    No need of creating any Trasnaction/Screen Variant
    Go to OMT3B - Copy New Screen Seq from 21 and under "Data screens" delete all except MRP.
    Now Go to OMT3E - Here under "User screen reference", assign a Key to all user whom you want to give change option for MRP views. Now In Screen Seq Control Screen, maintain an entry with SRef; Trans as MM02, SRef: User as that Key, SRef: mat Type as *, SRef: Industry as * and assign the new Screen Seq.
    Now Check in MM02.

  • How to create MRP view using BO BUS1001006 & Method CreateViews.

    Guys,
    I need to create MRP view using BO BUS1001006 & Method CreateViews.
    i am not able to unterstand, what i need to specify to create MRP view, other than material number.
    what field i need to send for MRP view.
    Regards.
    santosh.
    Edited by: santosh koraddi on Jun 23, 2010 6:14 PM

    Hi,
    I have a similar question, have done a search and I see this sort of thing has come up a few times but with no definitive answer.... this thread seems close but don't really understand the solution (I'm not an ABAPER)
    I have a material master creation workflow under construction, it uses BUS1001006 and method createviews.
    The issues is that I want to restrict creation of certain views to certain agents, I have a fork in my workflow and its meant to split up the various views for various agents.
    The problem is that if an agent in one of the forks completes their views the workflow tries to get them to completes teh other views which they do not have authoisation to do... anyway the end result is that the workflow thinks all teh views have been created and the workflow items dissappear from the others inboxes.
    How do I setup my workflow such that each agent in each fork only has to complete the views they have authorisation to maintain and leaves work items in the inboxes of other agents for them to complete?

  • Finding if mrp view exists

    hi
    i am working on an enhancement within cif to transfer material master in ecc to scm .
    i need to check if mrp view exists or no for every material transferred.
    now how do i do this coding wise ?  which field or table do i need to check if mrp view has been defined or no.

    Hi,
    Use FM 'SELECTION_VIEWS_FIND'
    Check below thread
    Select a specific view in MM02/MM01
    https://forums.sdn.sap.com/click.jspa?searchID=6788689&messageID=4407517
    Regards,
    Atish
    Message was edited by:
            Atish Sarda

  • MRP View and Plant parameter

    Hi,
      In our one plant, we are not running the MPR , it is use to mfg. of control pannel,  but we dont required the MPR run this,  but the material will be made thorugh production order,  then Finsih material will come in stock  so for this is it necessary to maintian all the MRP view or do the plant parameter settings  or we can skip all MRP view in Material master.
    regards,
    zafar

    In our one plant, we are not running the MPR , it is use to mfg. of control pannel, but we dont required the MPR run this, but the material will be made thorugh production order, then Finsih material will come in stock so for this is it necessary to maintian all the MRP view or do the plant parameter settings or we can skip all MRP view in Material maste
    Maintain a MRP1 view and work scheduling View for the production material with out this you can't able to create a production order , In MRP1 view maintain MRP type as ND- No MRP
    No need to do any Config related to MRP.

  • MRP view mandatory

    Hello SAP Guru,
    My requirement is for ROH material i want to make MRP view as a mandatory system should restrict to save the material master record if MRP view is missing for ROH material. plesae suggest how can we do that?
    regards,

    Dear ,
    1.One way will be select the MRP views frist time and defalut by hitting the Default Tab and SAVE in MM01 entry .
    2.Check in OMT4 /OPJBor Below SPRO path SPRO --> Logistics - General --> Material Master --> Basic Settings --> Define Attributes of System Messages-Keep E/W so that it will flag mesage .
    3.Controlling through MMD1-MRP profile for MRP1-4 view data .
    4.You may use EXIT_SAPLMGMU_001 of enhancement MGA00001 which is triggered put a breakpoint in this function, if MRP1-MRP4 view are not selected  .
    Try and check
    Regards
    JH

  • MRP VIEW For Plant Maintenance

    Hello friends,
    My Client require Minimum Stock of Spare Parts in Maintenance Store and when ever the minimum reserve quantity hit an automatic PR will generate and the purchase deptt. can Procure. so what will be the MRP View for Plant Maintenance in this scenerio and what will be the configration.
    Thanks
    Neeraj Gupta
    Edited by: neerajj0 on Jun 11, 2010 11:33 AM

    Hi,
    Material Master will be maintained by MM people. For Spare parts, material type would be ERSA. Maintain the MRP type for Reorder Point Planning in MRP1 view of Material Master & Reorder Point Qty in MRP1 view.
    While running MRP, spare parts also will be planned.
    Regards,
    Maheswaran.

  • Mrp view 2

    Hi guys,
    I am working with kmat material and while doing material master data in MRP view 2 procurement are showing E grayed one ie in display mode but i don't want that so plz suggest me how to remove that display mode ie grayed one
    thanks
    jaiswin.

    Hi
    For the material type KMAT it is always inhouse production as per Std SAP.That is why it is like that.
    If you want to change that go to Materila mster master config in attributes for material types step & do config.
    Regards
    YMREDDY

  • MRP Views Settings

    Dear Friends
    To run Forecast based MRp for a Finished product i need the Following Settings
    1) MRP views settings for Finished product and their BOM raw materials
    2) where have to enter the Forecast values
    3)How to Run MRP- basic settings
    what are pre step before run MRP.
    It would be very helpful if u respond quickly, i have to implement in 2 days.
    thanks
    Shivani

    Hi Shivani,
    I think you are talking about consumption based planning.
    Following are the Pre Requisites before running MRP
    u2022Define MRP types
    Path: SPRO u2013 IMG u2013 MM u2013 Consumption based planning u2013 Master data u2013 MRP Types
    This will determine the MRP procedures, forecast usage and select automatic calculation of either safety stock / re-order  point
    u2022Define MRP areas
    Path: SPRO u2013 IMG u2013 MM u2013 Consumption based planning u2013 Master data u2013 MRP Areas u2013 Define MRP areas
    We define this for combination of plant, SLoc and Vendor.
    Note: MRP area and plant must be the same.
    u2022Maintain MRP relevant data at Plant/SLoc level using TCode MM01
    - MRP 1, MRP 2 and MRP 3 are for plant level data:
       You need to maintain here the MRP type, forecast model and the period indicator.
       In MRP1, you can maintain the Re-Order point and Lot Size
       In MRP2, you can maintain Safety stock and planned delivery time parameters.
    - MRP 4 is for SLoc level data.
    u2022 Create MRP profiles (using Tcode MMD1)
      Using this, you can maintain general parameters for materials. The MRP parameters defined here will be independent of the   
      material master.
    u2022 Set material status for cross site / plant in material master.
      Material status for Cross site will be assigned in the u2018Basic datau201D view whereas Material status for u201CPlantu201D will be assigned in 
      MRP 1 view.
    After having all these pre-requisites maintained, you can run the MRP as Single Item or Multi Level.  Check TCode MD01 / MD02 / MD03 / MD04
    Hope this helps you.
    Let me know if you need anything further.
    Regards,
    Nikita

Maybe you are looking for