Material was not bound to the material ledger

Hello,
When I run the entry markers (TCODE MIGO) the error message appears C+470 - Lack of connection material 16243 to 16243 at the center material ledger.
Diagnosis:
An error occurred when creating or modifying the view of evaluating the material. The material was not bound to the material ledger.
System activity:
The update operation is canceled.
Procedure:
Contact SAP support.

I checked that note, I changed the type of material in MMAM ROH to Hawaii, but the LM still active disabled.
Then I went in again and ran for MMAM HAWA to ROH, and the asset continues LM disabled.
I need to activate the LM active for this material.
I'm working with version 6.0.
Hugs

Similar Messages

  • MM01 -- Update Was terminated while copying the material from one plant

    Hi Experts,
    While I am trying to copy the material from one plant like ETPE to another plant ETPZ , its telling that material created.
    But when we try to display the created material in MM02 for plant ETPZ , it says that material does not exist.
    Note : After creating the material , if we try to move any transaction code it shows the error message box and  says that Update was terminated .
    Kindly help us to resolve this.
    Regards,
    Vijay

    Hi rob,
    we have put the debugging , if there is any badi , enhancement the debugger would have gone to exit or enhancement line but its not going to any where.
    and I have checked in sm13 ..
    its giving the error like update was terminated
    from funtion module : MATERIAL_UPDATE_DB
    Report name :      LGRAPU37
    row : 360.
    ABAP/4 processor: POSTING_ILLEGAL_STATEMENT
    but if we go and see in the row 360 ...
    CALL SCREEN 100 line only
    is there , even if we put the breakpoint in this line , while we are debugging , debugger is not going to that line .
    Note : if we see the screen 100 it shows the empty screen.

  • Licence   is not included for the material - J1IH

    Hi All
    We are working on ECC 6.0.
    While doing J1IH ( Additional Excise) with Subtransaction Type 01, we are getting a warning message as -
    Licence   is not included for the material
    Message no. 8I993
    However if we process without any Subtransaction Type, no warning is flashed.
    Please let me know the reason for the same and what could be done so that system doesnt prompt it?
    Regards
    Kapil

    Hi
    Check SAP note 1223591
    Regards
    Antony

  • Licence   is not included for the material

    Hi,
    I have maintained account ddetermination for DIEX ETT for sub transaction type 22. When I am doing Additional Excise in J1IH system is giving the warning message as "Licence   is not included for the material" and it is not picking any G/L accounts. Where as without subtransaction , it is picking concerned G/L accounts. Please suggest, what I have to do?
    Regards,

    Hi
    Check SAP note 1223591
    Regards
    Antony

  • Finish material is not showing at the time of confirmation

    Dear all ,
    Finish material is not showing in the goods movement tab .So that movement type 101 is not possible at the prod ord confirmation .
    Goods movement is accepting in mb31.
    So plz suggest me

    Abhay,
    I think you are asking for Auto GR,whereby upon confirmation GR will happen automatically in the background
    Required Setting
    In the routing ,to the last operation assign PP03(Auto GR-Std SAP) as the control key instead of PP01
    After that while doing confirmation for last operation in CO11N,there if you click the goods movement tab you will be able to see the finish material with movmnt type 101
    Hope the above is clear
    Reward points if useful n close the thread
    Regards,
    SVP

  • Assessable value not maintained for the material X

    Dear all,
    i have maintained material chapter ID,Plant and materialchapter id  combination ,assessable value , cenvat determination, and vendor excise details in the transaction J1ID .
    Even after maintaining all these conditions , i am not able to save the po,while saving the po i got a error message that assessable value not maintained for the material X..
    Points will be rewarded for useful suggestions.
    Thanks in Advance.
    velu+91-9789991357

    Hi,
    Search using approriate keywords in SDN, u get most of the details, i have now done the same searched and have pasted below .
    Try ME2N.
    Click on the "dynamic selections" icon and add the release indicator as an additional selection. Enter the release indicators that you class as "awaiting approval" and you will then have your list.
    The ME2* series of transactions are not that much use prior to 4.7, the layout is poor. But if you have 4.7 or later you can get the screen to use the ALV format and this transforms the ME2* (i.e. ME2L, ME2M, ME2N etc.) transactions into VERY useful reports.

  • Material does not exist in the warehouse number

    Hi
    I am new to WM. I am in the process of learning. While learning i encountered an error indicating that the material does not exist in the warehouse number. i hava configured the required organisational structure configuration for WM,
    Is anything i have to configure for material or material type it belongs to the warehouse number and if it is yes where can i configure the same.?
    Regards
    Siva

    What is the exact error message and code and in which transaction is it occuring?
    The material has to be maintained at the following views:
    - Basic Data
    - Sales: General/Plant
    - Purchasing
    - General Plant/Data Storage
    - Warehouse Management
    - Accounting
    Make sure the material exists at each and every  Storage Type you use.
    You might also need to check the following settings:
    IMG > Logistics Execution > Warehouse Management > Interfaces > Inventory Management > Define Storage Location Control
    And delete any un-necessary Warhouse to Plant assignments in
    IMG > Enterprise Structure > Assignment > Logistics Execution > Assign warehouse number to plant/storage location

  • Price was not picking from the Condition type for Item Category 'P'  in PO

    Hi Experts,
    I Created one condition type based on Material and WBS which price was fixed based on this
    I used the Purchase Order having Item <b>Category ‘P’ or ‘Q’</b> Price should pick from the condition type where I mapped the WBS Element and Material.
    The Net price was not picking from the Condition type Record.  Why? What should be the Problem?
    Whether my logic is correct or not?
    <u><b>
    The Scenario:</b></u> I want to fix the Material price base on each WBS Element for a Project. For each WBS Element the Price will be various for same material.
    Please help on this.
    Thanks
    Muthukumar

    Hi,
    In standard configuration you cannot set item delivery date as a pricing data.
    Maybe you shoud look at SAP enchancement - in dedicated structures you can pass additional item data (structure KOKMP).
    IMG link:
    Materials Management -> Purchasing -> Conditions -> Define Price Determination Process -> System Enhancements
    hope it helps.
    regards,
    wojciech

  • Auto To working for one material and not working for other material

    Hi,
    Hope everybody is doing fine.
    I have configured the auto TO. Its working fine for one material and not working for the other material. I checked the material master and wm 1,2 views have the same fileds / values. What could be wrong?
    I didn't setup the back ground processing job. Is that is affecting it?
    thanks for any help.
    regrads,
    KHAN

    Thnaks,
    You are right but then what could be wrong? Its working for one material and not working for otehr material? Any clue?
    Appreciate your time charlie

  • Make field in Material master mandatory based on the material group

    Hello all,
    I need to make the field "post to inspection flag" mandatory based on the material group while creating the Material master.
    I found options for making the field mandatory based on Material type,Industry sector and plant NOT based on the material group.
    Could anyone please provide suggestions on setting up the field as mandatory based on material group while creating material master
    Thanks,
    Sre

    Hi Sre,
    You can make Material Group field as Mandatory while Creating Material Master.
    SPRO>Log General>Material Master>Field Selection>Maintain Field Selection for Data Screens
    Select Screen # 48
    In the Field selection (Field Ref.) of (MARA - MAKTL) screen , Change the settings from Optional to Required Entry for T Codes MM01, MM02 or you can select the Material Type ;
    Please note this  by choosing this selection the fields of Profit Center and  Division will also become Mandatory.
    Hope this helps,
    Best regards
    Amit Bakshi

  • C2 223 A valid bill of material could not be found for material 5089

    Hi Experts
    I have Production orders that use a phantom material 63955 with Std costing control.  This material uses three materials (5089,5233 & 5235) of moving average control.
    Material 63955 is a HALB and uses all the numbers 5089,5233 and 5235 which are ROH.
    With costing material 63955 with CK11N or CK40N, the error is
    C2223 A valid bill of material could not be found for material 5089 and the same for 5233 and 5235
    Diagnosis
    Material 5233 is marked as a phantom assembly. When the system tried to explode a valid bill of material for material 5233, it could not find one.
    System Response
    The system generates a normal reservation for 5233.
    Procedure
    Check the bill of material for material 5233
    The 5* numbers do not have a bill of material and are purchased externally.
    What must I do now please?  These materials cannot be costed.
    Kind regards
    Dawn

    Hi..
    You  check whether material 5233 have procurement type ‘E’ or ‘X’ and
    special procurement type ‘50’ in MRP2 view of Material master.
    Material 5233 with the above conditions is Phantom assembly.
    If Material 5233 is material master for external purchasing, Material 5233
    should have procurement type ‘F’ and special procurement type  space.

  • A valid bill of material could not be found for material

    Hi,
    Our's is SAP release 605. While doing sales order cost estimate (CK51N) we are getting following error message:
    A valid bill of material could not be found for material 1000000012
    Message no. C2223
    Diagnosis
    Material 1000000012 is marked as a phantom assembly. When the system tried to explode a valid bill of material for material 1000000012, it could not find one.
    System Response
    The system generates a normal reservation for 1000000012.
    Procedure
    Check the bill of material for material 1000000012.
    We have checked BOM and everything seems correct. please suggest where I am doing mistake.
    Regards,
    Bijay

    Dear Bijay kumar,
    Material 1000000012 is marked as a phantom assembly,so it must be set with a procurement Type E and special procurement
    type 50 in the MRP2 view of the material master or else at BOM level.So as a standard behaviour the system is expecting a
    BOM for the phantom assembly 1000000012.Check in T.Code CS03 whether you are able to find the BOM components for this
    material 1000000012.If BOM is not found means you have to create a BOM for this pahantom assembly because during the GI
    for the main assembly/product the system consumes the components of the pahantom assembly and not the phantom assembly
    (as in general there wont be any stock maintained for this material 1000000012).
    So check with this and revert back.
    Regards
    Mangalraj.S

  • In IPhoto '08, Photos under Library, I'm no longer able to view a screen of thumbnails.   I'm only able to view a single photo at one time.  This was not true in the past.

    In IPhoto '08, in Library/Photos, I'm no longer able to view a screen of thumbnails.   I'm only able to view a single photo at one time.  This was not true in the past.

    Note the slider lower right of the iPhoto Window. Drag it left.
    Regards
    TD

  • Using a Variable in SSIS - Error - "Command text was not set for the command object.".

    Hi All,
    I am using a OLE DB Source in my dataflow component and want to select SQL Query from the master table  I have created variables v_Archivequery
    String packageLevel (to store the query).
    <Variable Name="V_Archivequery" DataType="String">
         SELECT a.*, b.BBxKey as Archive_BBxKey, b.RowChecksum as Archive_RowChecksum
         FROM dbo.ImportBBxFbcci a LEFT OUTER JOIN Archive.dbo.ArchiveBBxFbcci b
         ON (SUBSTRING(a.Col001,1,4) + SUBSTRING(a.Col002,1,10)) = b.BBxKey
         Where (b.LatestVersion = 1 OR b.LatestVersion IS NULL)
        </Variable>
    I am assigning this query to the v_Archivequery variable, "SELECT a.*, b.BBxKey as Archive_BBxKey, b.RowChecksum as Archive_RowChecksum
    FROM dbo.ImportBBxFbcci a LEFT OUTER JOIN Archive.dbo.ArchiveBBxFbcci b
     ON (SUBSTRING(a.Col001,1,4) + SUBSTRING(a.Col002,1,10)) = b.BBxKey
    Where (b.LatestVersion = 1 OR b.LatestVersion IS NULL)"
    Now in the OLE Db source, I have selected as Sql Command from Variable, and I am getting the variable, v_Archivequery .
    But when I am generating the package and when running I am getting bewlo errror
     Error at Data Flow Task [OLE DB Source [1]]: An OLE DB error has occurred. Error code: 0x80040E0C.
    An OLE DB record is available.  Source: "Microsoft SQL Native Client"  Hresult: 0x80040E0C  Description: "Command text was not set for the command object.".
    Can Someone guide me whr am going wrong?
    Please let me know where am going wrong?
    Thanks in advance.
    Thankx & regards, Vipin jha MCP

    What happens if you hit Preview button in OLE DB Source Editor? Also you can use the same query by selecting SQL Command option and test.
    Could you try set the Delay Validation = True at Package and re-run ?
    If set the query in variable expression (not in value), then Set Evaluate As Expression = True.
    -Vaibhav Chaudhari

  • Reporting (Project Publish) job is failing with 'The given key was not present in the dictionary'

    I am using Project Server 2010 with SQL Server 2008 R2.
    I have a PWA Instance which was running fine. I have a big number of projects and I do not keep site for all the projects as we do not need project site in our business.
    Everything was running fine but during last few days, some of the jobs like Reporting (Project Publish) and Reporting (Project Delete) job is failing with the same error details for all the projects. I am not able to trace where the data is wrong/corrupt
    and how to resolve it.
    The error detail and ULS Log is given below anod I would appreciate if someone can guide me where the problem is and suggest me any solution.
    QUEUE ERROR DETAIL:
    General Reporting message processor failed:
     ReportingProjectChangeMessageFailed (24006) - The given key was not present in the dictionary.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='4f36afe0-43dc-4143-befc-0452da416e69' QueueMessageBody='Project UID='b95c52ba-bc00-4301-aab5-890d0b057c29'.
    PublishType='ProjectPublish'' Error='The given key was not present in the dictionary.'.
     ReportingProjectChangeMessageFailed (24006) - The given key was not present in the dictionary.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='071aeb7b-540e-45fa-b40b-a94a5d2e8e04' QueueMessageBody='Project UID='b95c52ba-bc00-4301-aab5-890d0b057c29'.
    PublishType='ProjectPublish'' Error='The given key was not present in the dictionary.'.
     ReportingProjectChangeMessageFailed (24006) - The given key was not present in the dictionary.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='55445e77-51e3-40d8-a62f-e6db0b897444' QueueMessageBody='Project UID='b95c52ba-bc00-4301-aab5-890d0b057c29'.
    PublishType='ProjectPublish'' Error='The given key was not present in the dictionary.'.
     ReportingProjectChangeMessageFailed (24006) - The given key was not present in the dictionary.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='3ab5a1ba-0915-45bb-a078-4b4b7c38af51' QueueMessageBody='Project UID='b95c52ba-bc00-4301-aab5-890d0b057c29'.
    PublishType='ProjectPublish'' Error='The given key was not present in the dictionary.'.
     ReportingProjectChangeMessageFailed (24006) - The given key was not present in the dictionary.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='b27acd8f-6cde-47d4-bd53-5930e84dc940' QueueMessageBody='Project UID='b95c52ba-bc00-4301-aab5-890d0b057c29'.
    PublishType='ProjectPublish'' Error='The given key was not present in the dictionary.'.
     ReportingProjectChangeMessageFailed (24006) - The given key was not present in the dictionary.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='b7250544-2a11-4887-8dcd-378b34b33ae1' QueueMessageBody='Project UID='b95c52ba-bc00-4301-aab5-890d0b057c29'.
    PublishType='ProjectPublish'' Error='The given key was not present in the dictionary.'.
     Queue:
     GeneralQueueJobFailed (26000) - ReportingProjectPublish.ReportProjectPublishMessageEx. Details: id='26000' name='GeneralQueueJobFailed' uid='0706d212-f737-43ea-b694-c420488d57bb' JobUID='ca238fcf-d91b-46d6-a9c2-15f2cc35230d' ComputerName='WebSrv1' GroupType='ReportingProjectPublish'
    MessageType='ReportProjectPublishMessageEx' MessageId='1' Stage=''. For more details, check the ULS logs on machine WebSrv1 for entries with JobUID ca238fcf-d91b-46d6-a9c2-15f2cc35230d.
    ULS LOG:
    Timestamp               Process                                
     TID    Area                           Category                     
     EventID Level      Message  Correlation
    01/19/2015 19:05:07.44 Microsoft.Office.Project.Server (0x1D30) 0x23FC SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureScalar -- MSP_FULL_PUBLISH_DELETE). Execution Time=117.485513497555 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:07.66 Microsoft.Office.Project.Server (0x1D30) 0x2C94 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureScalar -- MSP_FULL_PUBLISH_DELETE). Execution Time=192.534598230475 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:08.16 Microsoft.Office.Project.Server (0x1D30) 0x1CFC SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureScalar -- MSP_FULL_PUBLISH_DELETE). Execution Time=448.362263674397 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:08.36 Microsoft.Office.Project.Server (0x1D30) 0x17E0 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureScalar -- MSP_FULL_PUBLISH_DELETE). Execution Time=162.22152253546 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:09.00 Microsoft.Office.Project.Server (0x1D30) 0x0898 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureScalar -- MSP_FULL_PUBLISH_DELETE). Execution Time=557.699412860413 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:09.36 Microsoft.Office.Project.Server (0x1D30) 0x1F20 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureScalar -- MSP_FULL_PUBLISH_DELETE). Execution Time=253.695754010613 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:09.67 Microsoft.Office.Project.Server (0x1D30) 0x0D68 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureScalar -- MSP_FULL_PUBLISH_DELETE). Execution Time=239.76302803952 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:10.64 Microsoft.Office.Project.Server (0x1D30) 0x3324 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureScalar -- MSP_FULL_PUBLISH_DELETE). Execution Time=973.469925841736 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:11.92 Microsoft.Office.Project.Server (0x1D30) 0x2DB8 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureScalar -- MSP_FULL_PUBLISH_DELETE). Execution Time=1275.5063556303 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:12.96 Microsoft.Office.Project.Server (0x1D30) 0x0A1C SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureScalar -- MSP_FULL_PUBLISH_DELETE). Execution Time=1041.55499409959 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:13.15 Microsoft.Office.Project.Server (0x1D30) 0x0518 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureScalar -- MSP_FULL_PUBLISH_DELETE). Execution Time=133.891034879385 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:13.35 Microsoft.Office.Project.Server (0x1D30) 0x14EC SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureScalar -- MSP_FULL_PUBLISH_DELETE). Execution Time=207.250205426327 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:14.69 Microsoft.Office.Project.Server (0x1D30) 0x10B4 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureScalar -- MSP_PUBLISH_PROJECT). Execution Time=267.137845971639 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:14.93 Microsoft.Office.Project.Server (0x1D30) 0x14E0 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureScalar -- MSP_PUBLISH_PROJECT). Execution Time=209.552772167485 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:16.10 Microsoft.Office.Project.Server (0x1D30) 0x2AB4 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureNoResultWithOutputParameters -- MSP_SRA_ValidateServerLevelSRA).
    Execution Time=717.808222684698 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:16.67 Microsoft.Office.Project.Server (0x1D30) 0x2AB4 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (FillTypedDataSet -- MSP_SRA_GetData). Execution Time=307.24482978413 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:17.58 Microsoft.Office.Project.Server (0x1D30) 0x2AB4 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureNoResultWithOutputParameters -- MSP_SRA_ValidateServerLevelSRA).
    Execution Time=123.306566048297 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:19.12 Microsoft.Office.Project.Server (0x1D30) 0x25F4 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureNoResult -- MSP_WEB_SP_QRY_CreateSavedTasksForProject). Execution
    Time=111.699445284922 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:19.61 Microsoft.Office.Project.Server (0x1D30) 0x2AC8 SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope (ExecuteStoredProcedureNoResult -- MSP_WEB_SP_QRY_Statusing_BuildTaskHierarchy). Execution
    Time=449.279962592357 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:19.79 Microsoft.Office.Project.Server (0x1D30) 0x26D0 Project Server Server-side Project Operations 8tci Monitorableser1 PWA:http://epm.company.com/PWA, ServiceApp:SharedServices1_PsiServiceApplication, User:Domain1\User1,
    PSI: [QUEUE] System.IO.FileNotFoundException: The site
    http://epm.company.com/sites/Workspaces2/PROJECT_1 could not be found in the Web application SPWebApplication Name=SharePoint - 80.     at Microsoft.SharePoint.SPSite..ctor(SPFarm farm, Uri requestUri, Boolean contextSite, SPUserToken
    userToken)     at Microsoft.SharePoint.SPSite..ctor(String requestUrl)     at Microsoft.Office.Project.Server.BusinessLayer.Project.OpenProjectWeb(Guid projectUid)     at Microsoft.Office.Project.Server.BusinessLayer.Project.SetPwsProperties(Guid
    projectUid)     at Microsoft.Office.Project.Server.BusinessLayer.Queue.ProcessPublishMessage.ProcessMiscellaneousPublishMessage(Message msg, Group messageGroup, JobTicket jobTicket, MessageContext mContext) ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:19.79 Microsoft.Office.Project.Server (0x1D30) 0x26D0 Project Server Server-side Project Operations 8tcj Monitorable PWA:http://epm.company.com/PWA, ServiceApp:SharedServices1_PsiServiceApplication, User:Domain1\User1,
    PSI: [QUEUE] MiscellaneousPublishMessage failed on project b95c52ba-bc00-4301-aab5-890d0b057c29 ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:27.42 Microsoft.Office.Project.Server (0x1D30) 0x3088 Project Server Reporting atwj Monitorable Error is: ReportingProjectChangeMessageFailed. Details: Attributes:  Project UID='b95c52ba-bc00-4301-aab5-890d0b057c29'.
    PublishType='ProjectPublish'  The given key was not present in the dictionary.  . Standard Information: PSI Entry Point:   Project User: Domain1\User1  Correlation Id: ae078058-f794-47ca-b1ad-0834f7a07f4d  PWA Site URL:
    http://epm.company.com/PWA  SSP Name: SharedServices1_PsiServiceApplication  PSError: ReportingProjectChangeMessageFailed (24006) ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:27.42 Microsoft.Office.Project.Server (0x1D30) 0x3088 Project Server Reporting atwr High PWA:http://epm.company.com/PWA, ServiceApp:SharedServices1_PsiServiceApplication, User:Domain1\User1, PSI: [RDS] ULS
    Event: ReportingProjectChangeMessageFailed was associated with exception: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.     at System.ThrowHelper.ThrowKeyNotFoundException()    
    at System.Collections.Generic.Dictionary`2.get_Item(TKey key)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.SubDal.InitializeSprocParameterTypeData(Dictionary`2& routineParameterInfos)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.SubDal..ctor(DAL
    dal, DataStoreEnum store)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.get_Reporting()     at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.RDSBaseMessageProcessor.GetRefreshOperationStatus(MessageAreaType
    messageArea)     at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.RDSBaseMessageProcessor.CheckIfAllowedToProceed(ReportingBaseMessage msg, MessageContext msgContext, Group messageGroup, JobTicket jobTicket)    
    at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.ProjectPublishMessageProcessor.HandleMessage(Message msg, Group messageGroup, JobTicket jobTicket, MessageContext mContext) ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:28.47 Microsoft.Office.Project.Server (0x1D30) 0x31F8 Project Server Reporting atwj Monitorable Error is: ReportingProjectChangeMessageFailed. Details: Attributes:  Project UID='b95c52ba-bc00-4301-aab5-890d0b057c29'.
    PublishType='ProjectPublish'  The given key was not present in the dictionary.  . Standard Information: PSI Entry Point:   Project User: Domain1\User1  Correlation Id: ae078058-f794-47ca-b1ad-0834f7a07f4d  PWA Site URL:
    http://epm.company.com/PWA  SSP Name: SharedServices1_PsiServiceApplication  PSError: ReportingProjectChangeMessageFailed (24006) ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:28.47 Microsoft.Office.Project.Server (0x1D30) 0x31F8 Project Server Reporting atwr High PWA:http://epm.company.com/PWA, ServiceApp:SharedServices1_PsiServiceApplication, User:Domain1\User1, PSI: [RDS] ULS
    Event: ReportingProjectChangeMessageFailed was associated with exception: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.     at System.ThrowHelper.ThrowKeyNotFoundException()    
    at System.Collections.Generic.Dictionary`2.get_Item(TKey key)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.SubDal.InitializeSprocParameterTypeData(Dictionary`2& routineParameterInfos)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.SubDal..ctor(DAL
    dal, DataStoreEnum store)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.get_Reporting()     at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.RDSBaseMessageProcessor.GetRefreshOperationStatus(MessageAreaType
    messageArea)     at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.RDSBaseMessageProcessor.CheckIfAllowedToProceed(ReportingBaseMessage msg, MessageContext msgContext, Group messageGroup, JobTicket jobTicket)    
    at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.ProjectPublishMessageProcessor.HandleMessage(Message msg, Group messageGroup, JobTicket jobTicket, MessageContext mContext) ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:29.51 Microsoft.Office.Project.Server (0x1D30) 0x2B00 Project Server Reporting atwj Monitorable Error is: ReportingProjectChangeMessageFailed. Details: Attributes:  Project UID='b95c52ba-bc00-4301-aab5-890d0b057c29'.
    PublishType='ProjectPublish'  The given key was not present in the dictionary.  . Standard Information: PSI Entry Point:   Project User: Domain1\User1  Correlation Id: ae078058-f794-47ca-b1ad-0834f7a07f4d  PWA Site URL:
    http://epm.company.com/PWA  SSP Name: SharedServices1_PsiServiceApplication  PSError: ReportingProjectChangeMessageFailed (24006) ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:29.51 Microsoft.Office.Project.Server (0x1D30) 0x2B00 Project Server Reporting atwr High PWA:http://epm.company.com/PWA, ServiceApp:SharedServices1_PsiServiceApplication, User:Domain1\User1, PSI: [RDS] ULS
    Event: ReportingProjectChangeMessageFailed was associated with exception: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.     at System.ThrowHelper.ThrowKeyNotFoundException()    
    at System.Collections.Generic.Dictionary`2.get_Item(TKey key)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.SubDal.InitializeSprocParameterTypeData(Dictionary`2& routineParameterInfos)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.SubDal..ctor(DAL
    dal, DataStoreEnum store)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.get_Reporting()     at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.RDSBaseMessageProcessor.GetRefreshOperationStatus(MessageAreaType
    messageArea)     at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.RDSBaseMessageProcessor.CheckIfAllowedToProceed(ReportingBaseMessage msg, MessageContext msgContext, Group messageGroup, JobTicket jobTicket)    
    at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.ProjectPublishMessageProcessor.HandleMessage(Message msg, Group messageGroup, JobTicket jobTicket, MessageContext mContext) ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:30.56 Microsoft.Office.Project.Server (0x1D30) 0x1D20 Project Server Reporting atwj Monitorable Error is: ReportingProjectChangeMessageFailed. Details: Attributes:  Project UID='b95c52ba-bc00-4301-aab5-890d0b057c29'.
    PublishType='ProjectPublish'  The given key was not present in the dictionary.  . Standard Information: PSI Entry Point:   Project User: Domain1\User1  Correlation Id: ae078058-f794-47ca-b1ad-0834f7a07f4d  PWA Site URL:
    http://epm.company.com/PWA  SSP Name: SharedServices1_PsiServiceApplication  PSError: ReportingProjectChangeMessageFailed (24006) ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:30.56 Microsoft.Office.Project.Server (0x1D30) 0x1D20 Project Server Reporting atwr High PWA:http://epm.company.com/PWA, ServiceApp:SharedServices1_PsiServiceApplication, User:Domain1\User1, PSI: [RDS] ULS
    Event: ReportingProjectChangeMessageFailed was associated with exception: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.     at System.ThrowHelper.ThrowKeyNotFoundException()    
    at System.Collections.Generic.Dictionary`2.get_Item(TKey key)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.SubDal.InitializeSprocParameterTypeData(Dictionary`2& routineParameterInfos)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.SubDal..ctor(DAL
    dal, DataStoreEnum store)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.get_Reporting()     at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.RDSBaseMessageProcessor.GetRefreshOperationStatus(MessageAreaType
    messageArea)     at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.RDSBaseMessageProcessor.CheckIfAllowedToProceed(ReportingBaseMessage msg, MessageContext msgContext, Group messageGroup, JobTicket jobTicket)    
    at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.ProjectPublishMessageProcessor.HandleMessage(Message msg, Group messageGroup, JobTicket jobTicket, MessageContext mContext) ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:31.60 Microsoft.Office.Project.Server (0x1D30) 0x2170 Project Server Reporting atwj Monitorable Error is: ReportingProjectChangeMessageFailed. Details: Attributes:  Project UID='b95c52ba-bc00-4301-aab5-890d0b057c29'.
    PublishType='ProjectPublish'  The given key was not present in the dictionary.  . Standard Information: PSI Entry Point:   Project User: Domain1\User1  Correlation Id: ae078058-f794-47ca-b1ad-0834f7a07f4d  PWA Site URL:
    http://epm.company.com/PWA  SSP Name: SharedServices1_PsiServiceApplication  PSError: ReportingProjectChangeMessageFailed (24006) ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:31.60 Microsoft.Office.Project.Server (0x1D30) 0x2170 Project Server Reporting atwr High PWA:http://epm.company.com/PWA, ServiceApp:SharedServices1_PsiServiceApplication, User:Domain1\User1, PSI: [RDS] ULS
    Event: ReportingProjectChangeMessageFailed was associated with exception: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.     at System.ThrowHelper.ThrowKeyNotFoundException()    
    at System.Collections.Generic.Dictionary`2.get_Item(TKey key)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.SubDal.InitializeSprocParameterTypeData(Dictionary`2& routineParameterInfos)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.SubDal..ctor(DAL
    dal, DataStoreEnum store)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.get_Reporting()     at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.RDSBaseMessageProcessor.GetRefreshOperationStatus(MessageAreaType
    messageArea)     at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.RDSBaseMessageProcessor.CheckIfAllowedToProceed(ReportingBaseMessage msg, MessageContext msgContext, Group messageGroup, JobTicket jobTicket)    
    at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.ProjectPublishMessageProcessor.HandleMessage(Message msg, Group messageGroup, JobTicket jobTicket, MessageContext mContext) ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:32.66 Microsoft.Office.Project.Server (0x1D30) 0x24DC Project Server Reporting atwj Critical Standard Information:PSI Entry Point:   Project User: Domain1\User1  Correlation Id: ae078058-f794-47ca-b1ad-0834f7a07f4d 
    PWA Site URL: http://epm.company.com/PWA  SSP Name: SharedServices1_PsiServiceApplication  PSError: ReportingProjectChangeMessageFailed (24006) RDS: The request to synchronize change(s) to project Project
    UID='b95c52ba-bc00-4301-aab5-890d0b057c29'. PublishType='ProjectPublish' failed.  Message: 'ReportingProjectChangeMessageFailed'. Message Body: The given key was not present in the dictionary. Error:(null) ae078058-f794-47ca-b1ad-0834f7a07f4d
    01/19/2015 19:05:32.66 Microsoft.Office.Project.Server (0x1D30) 0x24DC Project Server Reporting atwr High PWA:http://epm.company.com/PWA, ServiceApp:SharedServices1_PsiServiceApplication, User:Domain1\User1, PSI: [RDS] ULS
    Event: ReportingProjectChangeMessageFailed was associated with exception: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.     at System.ThrowHelper.ThrowKeyNotFoundException()    
    at System.Collections.Generic.Dictionary`2.get_Item(TKey key)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.SubDal.InitializeSprocParameterTypeData(Dictionary`2& routineParameterInfos)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.SubDal..ctor(DAL
    dal, DataStoreEnum store)     at Microsoft.Office.Project.Server.DataAccessLayer.DAL.get_Reporting()     at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.RDSBaseMessageProcessor.GetRefreshOperationStatus(MessageAreaType
    messageArea)     at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.RDSBaseMessageProcessor.CheckIfAllowedToProceed(ReportingBaseMessage msg, MessageContext msgContext, Group messageGroup, JobTicket jobTicket)    
    at Microsoft.Office.Project.Server.BusinessLayer.ReportingLayer.ProjectPublishMessageProcessor.HandleMessage(Message msg, Group messageGroup, JobTicket jobTicket, MessageContext mContext) ae078058-f794-47ca-b1ad-0834f7a07f4d

    Without seeing the history, one possibility might be some corruption in the reporting database. Assuming that you are following best practices for SQL DB management, and this is not a DB neglect problem, then I would try to force a refresh to see if that
    helps. You can do this by executing a custom field backup and then restore. Note: Do not do this during production hours. Let us know if that provides any therapy.
    Gary Chefetz, MCITP, MCP, MVP msProjectExperts
    Project and Project ServerFAQs
    Project Server Help BLOG

Maybe you are looking for

  • Customer and vendor open items

    Hi All,             What is customer and vendor open items.

  • "No SIM" error message on iPad Air

    This "error" appeared out of the blue.  I did not drop my iPad and I had used it earlier in the day with no issues. Later the same day: Found a YouTube video that gave instructions on how to open the SIM card slot.  Powered my iPad off, made sure my

  • Calling userdefined selection screen

    Hi all, here i am having scenario like first calling a selection screen with push button, when click the button it should call anyother selection screen and execute that with selection parameters please let me know anyone

  • Acrobat 9 Std-how to append new pages to existed/opened pdf file

    i am using Acrobat 9 standard version. when i used the scanner to create a pdf, but the file had many pages so i could not finish it before lunch. Therefore, i had to append new pages to the opened file. In past, 7 standard i could choose append to t

  • Instead of Compressor went Quicktime conversion (still problems)

    Hi, Thanx for all the suggestions regarding compressor. I didn't even consider doing Quicktime conversion for my DVDSP2. I did this last night with a two pass knowing it would take along time. After about 9 hours with some 18 to go ( the piece is 78