Move change request from a maintenance project  to another project

Hello all,
we want to close a maintenance project A and create a new maintenance project B. We have a lot of change request they aren`t finish, so we want to move them to the new maintenance project.
The following steps we have done:
1. Doing all phases of the maintenance cycle of project A.
2. Close maintenance cycle project A.
3. Create a new project B.
4. create a new maintenance cycle for project B.
Now, we have the problem, that all change request from project A and maintenance cycle A didn't move to the new project B and cycle B.
If you create a new maintenance cycle in project A, all open change requests move to the new cycle. But we want to move them to a new project and a new cycle.
Have anybody a suggestion how to do this?
Kind Regards
Marc

Hello Marc,
there are a couple of methods in a class that might help you if you DO have to do it... but SAP will not support you in case you have any problem.
you can take a look to methods of class CL_HF_HELPER.
Methods :
SET_BO_LINK_TO_CHNG_DOC is used to set link between SDMJ and SDMN
SET_BO_TASKLIST_OF_CHNG_DOC is used to set link between SDMJ and tasklist 
as there are those methods, to create links SAP, provides some others that are supposed to break them (If i remember well they are not activated or finished but you can still have a look !!)
Those methods are
DELETE_BO_LINK_OF_CHNG_DOC
DELETE_BO_TASKLIST_OF_CHNG_DOC
RECREATE_BO_LINK_OF_CHNG_DOC
RECREATE_BO_TLIST_OF_CHNG_DOC
Hope this helps
One more time... be carefull with those methids... I think it s quite dangerous to handle those kind of things without SAP's support.
Also, one mote thing... since many many customers have asked for this functionality; SAP is trying to develop the whole thing (with adjustments of Checks functionalites of ChaRM) for the next releases. Maybe that will be part of the next release
Regards
Khalil

Similar Messages

  • Moving Change requests to new Maintenance cycle after approval

    Good Day
    I was wondering, is there an easy way to move any give change request from one maintenance cycle to another one. An example would be.
    I have a change request that currently has 1 ABAP, 1 Config and 1 Security transport assigned to our current maintenance cycle. I have been requested to move the change request (along with all the transports) to a future maintenance cycle.
    Is it just a case of re-assigning the change request to the future cycle, ?
    Regards
    Don Newton

    Hi Don,
    It's a very interesting question... I think that a lot of people here need this functionality and SAP finally hear that from us.
    This new functionality came with SP15. You should have a look to SAP notes 1071412, 1134993 and 1141086, it may help you to solve your problem.
    regards,
    Stéphane.

  • Creating Change Request from project structure

    Hello.
    Have somebody maked somthink like creating Change Request from Implementation project configuration structure? I want to initiate new change request directly from busines process step in transaction SOLAR02 for example.

    Hi
    Change request is created via action Create change document from support desk message
    so in solar02 tcode...goto issues/messages tab and create a message then
    crm_dno_monitor you can create a change request as i said and all the necessary data like ..system data,ibase etc is copied to ur change req from support message .
    Regards
    Prakhar

  • How can I move an original Version from one Project to another Project?

    How can I move an original Version from one Project to another Project?

    From the Aperture User Manual:
    To move an image into a different project
    Drag the image [from the Browser] into another project in the Library inspector.

  • How to import a Change request from One application to another application.

    Hi,
      In SRM Dev system I have created a Change request (Transport Request) and released to the QA system.The Change request has imported successfully to the SRM QA system.
    Now the Case is:
    The Released Request in the SRM Dev system has to be Export to the CRM Dev system.
    Is it possible to Export the Released Change Request from SRM system to CRM system?
    If possible then can you provide me with the solution.
    Thanks in Advance
    Dharma

    Hi,
    Your system admin knows how to do it. System admin should define transport route. Please check it in transaction STMS.
    Regards,
    Masa

  • Unable to release the change request from se01

    HI All,
    Recently i had applied Rsecnotes as per sap recommendation in EWA Report and I implemented successfully in DEV System. But, When i try to release the change requests from SE01 in (DEV System)
    it is giving the error message "Object Func<objectname> is inactive". I have unlocked all the request and checked but still problem exsist.
    Please help me to release the request and implement in the landscape.
    Thanks,
    Rajesh N

    Hi,
    Activate the object using se03 and then relaese the request
    thanks

  • Creating Change request from an Issue

    Hi, all.
    We have created new transaction type for change request (SDCR  at default) and have specified it for usage in parametre CHANGE_REQUEST in DNO_CUST04.
    However, creation of a change request from a issue (problem) ignores this customisation. As has shown code research - the constant there is used.
    Whether there are to it reasons or notices in the documentation?
    Whether there was for you such problem and how you solved it?
    Regards,
    Konstantin

    You need to maintain Transaction Types Mapping. Map your target procedure type (ZDCR) to your source procedure type (e.g. SLFN or ZLFN).
    Do this in IMG task "Define Mapping Rules for Copy Control"

  • How can I move a task from a Summary Task to another Summary Task in the same task list?

    Hey, I tried to move tasks through the SP UI from one Summary Task to other in the same task list, but I didn't find possibility for it.
    Then I spent time to learn the SP Client Object Model and now I can read tasks form the list. I see every task has a "FileRef" and a "FileDirRef" field. If I think right these fields show the relation between list elements for example between
    a Task and a Summary Task elements.
    I changed these fields' values and I tried to Update the ListItem but I got this error message: "Invalid data has been used to update the list item. The field you are trying to update may be read only."
    I really need to move tasks what were created below a wrong Summary Task so please explain a method or pattern how I can do this. (I can create a new Task below to any Summary Task and I can set field values but I hope there is a way to really move tasks (I
    mean I should change the right field values somehow.).
    I can reach the Task List both on the server and client side so I'm very interested in every solution. PowerShell solution is also good for me.
    I'm using SharePoint 2010 SP2.
    Thank you for your answer and your time. :)
    Csaba Marosi

    Hi,
    According to your post, my understanding is that you want to move a task from one summary task to another in the same task list.
    We can do it like this:
    We can create a Gantt View for this task list, then copy your tasks inside a summary task, then navigate back to the other summary and paste, then go back to original and delete.
    Here is another way for your reference:
    SharePoint vs Powershell – Moving List Items between folders
    http://sharepointstruggle.blogspot.in/2010/07/sharepoint-vs-powershell-moving-list.html
    Best Regards
    Dennis Guo
    TechNet Community Support

  • Can I move/copy songs from one itunes account to another itunes account on the same iMac?

    Can I move/copy songs from one itunes account to another itunes account on the same iMac?

    You move the song files to /Users/Shared/ and then into iTunes from the other Mac OS X user account.
    If you want to change the iTunes Store account associated with them, you need to redownload them from that account.
    (60812)

  • Transport a request from one server(quality) to another server(production)

    Hi All,
    I want to transport a request from one server(quality) to another server(production)
    Can we transport a request from quality to production programatically i.e. by using programing logic.
    Regards,
    Swarup

    Hi,
    It cannot be done programmatically. Although it can be automated by basis guys. They configure it in TMS (Transport Management System). You can check it using STMS. (if you are authorized to view it).
    Transport path are defined in TMS.
    For Automated Transport configuration is done in TMS.
    Generally automatic Transport are not setup between quality and production. Changes are first tested in Quality and then Transported by basis team either periodically / individually.
    In case of manual transport Transport Request can be imported in production using STMS_IMPORT transaction in production. (Basis guy will do it for approved Transports)
    If there is no direct connectivity - Basis people copy "data" file and "co" file and Transport it to target server (This is generally not the case in Quality - production as Transport path is always defined).
    Regards,
    Mohaiyuddin

  • How to Move Music Library from one external HD to another

    I had about 60GB of music on an external hard drive, nicely organized and "linked to" from iTunes (just upgraded to version 5). I recently purchased a larger external hard drive and basically copied the contents of my older external drive to the new one, preserving all folder structures from the root of the drives down (but the name of the drive itself is different.) I was hoping I could just do a search/replace of the "iTunes Music Library.xml" file in my Music/iTunes folder, to replace the name of the old drive (volume) with the new one. I did, and iTunes launches fine, preserving my playlists, song ratings, etc... but whenever I try to play any of the songs, it says it can't find it (I can manually point iTunes to it, but I don't want to do that for 15,000 songs...) Strange thing, though, is that if I quit out of iTunes and re-open the Library XML file, all the paths have been reset to their original location!! What am I missing? Thanks in advance,
    Jesse

    I just want to add that the iTunes folder (with the library xml file and such) is on my local hard drive, in the typical Music/iTunes location. I don't want to simply re-import the songs 'cuz I'd lose playlist contents and ratings, and I don't want to "consolidate" the library because I want to keep my music folders and filenames as I currently have them. Basically, I just want iTunes to realize the songs have simply changed location from one external drive to another... thanks again.

  • How can I move purchased apps from one itunes account to another account?

    How can I move purchased apps from one itunes account to another account?

    You can't. The apps must be purchased separately.

  • Is there a way to move photos directly from one iPhoto library to another iPhoto library?

    Is there a way to move photos directly from one iPhoto library to another iPhoto library?

    Not using iPhoto - Aperture can or iPhoto Library Manager can
    LN

  • Hi I have 2 apple id's one which has pulled through everything except my calendars and one which has pulled through just my calendars. How do I move my calendars from one apple id to another?

    Hi I have 2 apple id's one which has pulled through everything into icloud except my calendars and one which has pulled through just my calendars. How do I move my calendars from one apple id to another so that I can see everything in icloud with one apple id?

    Having read some other posts I think I have answered my question. If I was somehow able to terminate my old (unwanted) account and Apple ID I would no longer be able to access the material I bought with that ID-  so I'm stuck. I have to learn how to manage that situation.
    This is unfortunate for Apple consumers. Life is complicated for families these days and this "rule" although it is in place to prevent cheating and fraud makes things unnnecessarily difficult for me and my family as in my niaevity (sic) with the online world I bumbled into this situation. Not everyone is out to rip off Apple - one of the worlds richest corporations- or the entertainers who market their work through iTunes.I would just like to be able to enjoy the entertainment I pay for where and when I like to on whichever computer is available to me. And I'm not terribly computer literate.   
    It would have been nice to have had the opportunity to speak just once to a real person in the employ of Apple to explain my situation to them.

  • How do i move a picture from one pdf-file to another already created pdf-file with adobe reader?

    How do I move a picture from one pdf-file to another, already created pdf-file, with adobe reader?

    Reader doesn't have editing capabilities.

Maybe you are looking for

  • Associative Array error

    I am using a couple associative arrays in my code and comparing the data in one, and if it is an asterisk, I change it to use the data in the other. Here is the meat of my code. I am running into an error at the bolded line saying I have too many val

  • Persisting serialized bean in EJB 3.0

    Hello, I'm seeing some surprising results in EJB 3.0 when executing an update to some bean that is unmarshalled from a remote client. Perhaps I'm misunderstanding the API, but I reached the conclusion, from documentation and various online discussion

  • Trying to get BT line in my name, so I can get Sky...

    I will try and keep this short so everyone can understand! I moved into a new house on 4th May. On the 24th April, I ordered a sky package of tv, broadband and phone. Everything went thru ok, and I was told everything would be up and running within 4

  • Issues to edit in Photoshop from Lightroom , why?

    HI everyone, In order to edit some images on my new website http://www.monportraitphoto.fr I was getting into my archives that are all in a big Adobe Lightroom catalogue. After choosing the good pictures in my catalogue I tried to make the classical

  • How to Retrieve Server Name for creating connection pool during startup!

    Hi All, I am going thru the edocs documentation of weblogic for creating the connection pool and the datasource dynamically. The URL I referred to was as under http://edocs.bea.com/wls/docs81/jdbc/programming.html There is a sample given in the above