Moving avergae price updation in material master for project stock

Dear All,
My query is pertaining to updation of MAP( moving average price) for project specific procurement ( as project stock) for valuated project stock.
As  definelty the cost of procurement gets consumed by project .but i want to know does the project stock procurement still updates the moving avergae price or not.
Ex:-Suppose MAP in material master is 10 USD ( with qty 1)and i procure the same material ( qty 1)for project with account assignment Q for 9 USD . now will the MAP in material master becomes 9.5 USD or it remains 10 usd.?
Please reply urgently
Regards
Amit

Hi Amit,
If your Project Stock is valuated, then, the valuation data for it is stored in a different table: QBEW.
The normal, anonymus warehouse stock (the unrestricted use stock which is not assigned to any project or to any sales order) has its valuation data stored in MBEW.
The "Accounting 1" view in the Material Master MM03 ONLY displays the data of MBEW.
In the material master you will never see the valuation data of the valuated project stock (table QBEW) or the valuated sales order stock (valuation indicator "M" - table EBEW).
The valuation data for the tables QBEW and EBEW can be seen in SE16 or in the transaction MBBS.
Also note that these valuated special stocks are managed independently of the normal stock. If, for example, you change the Moving Average Price of your normal stock in MBEW, this will not have any influence on your project stock, as the data is under a totally diferent table QBEW.
I hope this helps you,
Esther.

Similar Messages

  • Material Master For Project

    Dear All,
    How we configure material master for Project stock
    Pl Help Step By Step
    or any document
    Regards
    Ranu

    Hi,
    While creating material master for project, you can select views as per relevance. While creating PO you should be clear whether you want to inventroze the stock or not. You can use account assignment as Q for matrial with Inventory.
    regards,
    Vinay

  • Price updation in Material Master after confirmation

    Dear Gurus,
    When we create a production order for Semi finished which is maintained with Moving Average Price(MAP) in material master and we do confirmation of the order with "CO15'.
    My client wants after goods receipts against 101 movement type the price should be up date in Material; Master immediately.
    Regards
    RAM

    Hi,
    I think this cant be done.
    > My client wants after goods receipts against 101 movement type the price should be up date in Material; Master immediately.
    How much MAP should be after GR? From where this value will come?
    The accounting entries are passed on the basis of price maintained in the material master. The MAP is the input to the business activity. So as per my understanding the MAP cant be updated with GR against a production order.
    Also, the costing run would update the standard price, and wont be helpful as the indicator would be 'V' in material master.
    Hope it clears.
    Regards,
    Rohit.

  • Moving Average Price does not get updated for Project Stock

    Hello Experts
    We have an Engineer-to-Order implementation for our client. Accordingly procurement is done per project. Each Project issues its PRs which are then converted to POs and recieved into Project Stock.
    While assigning the material to the Network activity in Project (using material component) the system uses the price found in the material master (MAP or STD) as a planned cost appended to the project.
    Problem:
    while procuring the material, when we receive it into Project Stock (Mvt 101 Q + ) the Moving Average Price in the material master does not get updated. this way all newly created material master will never have a moving average price, thus whenever we try to assign them to the project we receive an error message (Cost for Material Component ###Mat.Num### cannot be determined.
    Question:
    How can I get the system to update moving average price (for all types of stock) based on procurement for project stock.???
    Your help is kindly appreciated.

    I'm sorry for the confusion
    Case:
    The T-code is CJ20N Project Builder in PS module
    we are assigning material components to network activities under a certain WBS element in the project.
    there is a function in the Project Builder to calculate the cost of a network. it uses the costing variant assigned to the network which is PS02 (We get the error here)
    The costing variant has a valuation variant which lists a series of strategies  to get the material price. Planned 1 if not then STD if not then MAP. (you can choose between many options via a drop down menu) you can choose 5 consequent options.
    The MAP that the valuation variant is coded to get is the Plant Stock MAP -- Or the Project Stock MAP but only Per WBS element.
    The MAP that the Actual postings update is the Project Stock MAP only Per WBS element.
    This means that if you use a material component to purchase material 123 Acc.As. Q for WBS X for 10 $ then you try to assign a new material component with the same material 123 to WBS Y, the system will not get a MAP. because it's stored in QBEW per WBS element.
    This way the system will never get the MAP right.
    However, we don't always use project stock to procure for projects, for some requirements we can assign and use plant stock as well for Projects. that way we need the MAP from plant stock.
    In the Valuation Variant you can use a User Exit Strategy. The user exit's name is COPCP005
    My Suggestion is:
    Use the User Exit COPCP005 to calculate the { Total value / the total quantity (MAP) from QBEW + Total value / total quantity (MAP) from MBEW } / 2
    which is the MAP for both plant and project stock together, since that we are going to use both.
    Q: Is this correct !?

  • Moving average price based on valuation type for material

    Gurus help needed.
    we want to maintain the moving average price of the material in the pricing, and this depends on the Valuation Type. We have 3 valuation types.
    If valuation type is blank then one MAP(Moving average price) value will come and if nn one map will come and for nn one map will come.
    We have copied VPRS conditon type to YVRP and changed conditon category as T( Moving cost).
    But in pricing the YVRP price is not picking from valuation type which is blank.
    Where can  i make the settings to tell the system to pick the moving average price from the material master where the valution type is blank always based on the condition.
    Do we need to creat a routine? If so is there any standard routine which we can use or make minor changes to it?
    If it is a new routine please tell me how to start with VOFM?
    Note : We need the value to come automatically from material master same as VPRS.

    Hi
    The first method is not to set the pricing condition VPRS as statistical.
    Simply remove PR00 and it will work fine if you always use VPRS as your pricing base inside the pricing procedure.
    VPRS will reads both prices based on the price control in the material master. 
    Price control S for standard price. 
    Price control T for moving average price. 
    It is this simple if you do not have any other "Prices" in the price procedure. 
    However, if you are using one pricing procedure where for some items you price using VPRS and some others using PR00, then you should use requirement routines to enable the correct price condition type at the right time. 
    The second method involves more work as you need to write a formula (VOFM) to get that information. 
    This is how it goes :- 
    1. Set VPRS to be the first step in the pricing procedure and to be subtotal B (as standard). 
    2. Set PR00 with alt. calc. type formula, which sets the value of PR00 to be equal to the subtotal B.
    Step 1 VPRS statistical, subtotal B, reqt 4 
    Step 2 PR00 Altcty 600 
    With regards
    baalakrushnan.da

  • Price change in material master

    Hi,
    When does the moving average price change, if the PO price or the invoice price is different from the one in material master. Is it after the creation of PO, GR or invoice?
    Thanks and regards
    Aparna

    Hi,
    Moving Average price = Total Value
                                       Total Stock
    Moving average price updates once you make GR and IV
    If you are making GR & IV for new po , then new moving average price of that material will be :
    Total stock = stock already present in plant + GR made stock of that new po
    Total Value = Total Value of the material in plant + Invoice amount for that new po
    Thanks & Regards
    Prashanth.venkategowda

  • Moving average price updation when goods receipt posted

    Hi,
    Please let me know in which tables the moving average prices changes get updated when goods receipt is posted. Also let us know the process as to how moving average price gets updated in the accounting1 view in material master.

    Hi,
    Its updating in the table MBEW.
    To see the log of moving averae price updation, use report S_P00_07000139.
    Example :
    Stock quantity : 10No's.
    MAP : 100Rs.
    GR : 10No's@12Rs
    Now MAP will become 11Rs (220/20)
    Regards,
    Prabu

  • Material procurement as Project stock

    Hi,
    I have assigned a Non Stock Material (N) to WBS activity ---> converted the PR (created for network) to PO --> now i want to do GR for this PO and update the material recieved as Project stock on the correspondign WBS.
    I am using movement type 501Q when doing GR, and i expect that the corresponding WBS should automatically be populated or i should be able to add the WBS manually? but WBS field in MIGO screen when doing GR is greyed out?
    Any pointers to address this will be helpful?
    Thank you.
    Regards,
    Jatinder

    Hi,
    >>>>>>
    But now for one project i dont want to take material from store, but want the material to be supplied by supplier directly at project site, also i dont want to show the material supplied as directly consumed but want to show it first as WBS stock and then do GI to show consumption? how can we achieve this??
    <<<<<<<
    If you are intended to ship directly to site, then change procurement scenario as Drop shipment. In that case material never see the warehouse, what I mean no GR. Hope this make sense.
    for other requirement, discuss with your WM guys who should have fictious GR for that material. In that case you have to use material account assignment as Q (project stock). the only thing is you are not physically bringing material into warehouse but still you have GR for that material.
    Why you want to follow suck kind of routing, directly use drop ship procurement scenario which makes your life easier without any risk. By doing this you encouraging some kind of malpractices in system where users may misuse.
    Any have its your call and take decision accordingly.
    Regards,
    PSR

  • Production order variances not updating in material master

    We have activated Material ledger-
    Price determination selected-2(transaction based)
    Finished goods standard price--832.50
    Price control in material master-S (Standard Price)
    Variances per kg: 265.50 is shown in Moving Price field in Material master-
    Why it is not adding to standard Price-
    How to add 265.50 per kg(variance) and increase the Finished goods valuation (in the balance sheet)
    Thanks in advance
    Joseph David

    Hi,
    After activating ML, if you maintain FG Material Price Control-S with Price Determination-2, the shown Moving Average price is ONLY FOR STATISTICAL/reporting PURPOSE, The goods movements and Material Inventory valuation will not be updated/valuated with Moving Average Price, it will still be done as per Standard Price only.  If you want to get the full advantage of  ML activated realistic/actual valuation of your inventory and goods movements, you need to change the Material Price Determination to u201C03u201D. Then as per SAP standard ML process, preliminary valuation for the material will be u201CStandard Priceu201D and all Price differences will be accumulated in ML categories and after period/month-end activities, the goods movements and inventory will be evaluated with u201CPeriodic Unit Priceu201D i.e., averaging by taking into consideration all Material Price differences.
    Regards
    appalas

  • Subcontracting-moving average price update in finished good

    Dear all,
    We are having make to order scenario in which we are sending raw material or semifinished goods to subcontractor through purchase order .The price control is v in material master ,when processing is done at subcontractors end we are doing goods receipt with movement type 101 it takes price from purchasing info record .When i am analysing sales order  it shows material/semifinished costs+processing charges,but in material master of finished product it does not update material master stock and value. kindly provide me solution as to how moving price gets updated in material master of finished product.
    Thanks and regards
    vijay

    hi.
    ya I am doing against sales order as we are having make to order scenario,we are sending raw material to subcontractor from our own stock and then my movement type 912 e we are sending to subcontractor ,I am receiving finished goods after processing charges for which migo transaction is done .After seeing sales order cost in tcode kkac i am able to see raw material cost+consumption charge.But as we are having mto scenario it remains as sales order stock and nothing gets updated in material master.My problem is if customer does not takes delivery of my finished product then i have to detach finished goods from that sales order through movement type 411 e and through movement type 412 e attached to another sales order,but since price have not been updated in material master of finished goods it picks up original price which was maintained as re.1 .Kindly provide me solution in above scenario
    Thanks and regards
    vijay

  • Moving Average Price Updation

    Hello Friends,
    When we Purcahse materials for Project Stock "Q" during goods recepit the MAP is not getting Updated/Recalculated.Because of this when we do the planning for this material it takes the value in MM manually entered,it may be even Zero "0" price also.
    How we can make the settings such that the MAP gets calculated for Project stock "Q" stock also.
    Thanks,
    RamananPV

    Hi Ramanan,
    'Q' stock materials constitute a separate stock segment, distinct from plant stock. This will not update moving average price of plant stock materials which are in a different segment. Hence when you create a PR in new project, prices are taken from the materil master at the plant level.
    If you are making multiple procurement of the same material component for the same project segment, perhaps, you will see the updation in that stock segment.
    Hope I have got your problem correctly and  my understanding is ok.
    Muraleedharan.R

  • Material valuation with respect planned price 1 in material master

    Dear All,
         The costing variant PPC1 has been used for released cost estimate. In my scenario I want to create one more variant say ZPC1 where to calculate the value of the material from the planned price 1. In this case
    1.     What should be the validity date mentioned in the material master for valuation
    2.     The variant has been configured as
    a.     Costing Type – 12 Mod Std cost Est
    i.     Price Update – No Update
    ii.     Save Parameter – With Start of Period
    iii.     Misc – Cost Sheet
    b.     Valuation Variant – 001 Planned Valuation
    i.     Material Valuation - Planned Price
    ii.     Standard Price
    c.     Date control
    i.     From Date : Start of Current Posting Period
    ii.     To Date : End of Current Posting Period
    iii.     Qty Struc Date : Current Date
    iv.     Val Date : Current Date
    d.     Qty Structure Control (As PPC1)
    3.     When I run the standard cost estimate with variant ZPC1 the system calculates the standard price of the material even when the price is mentioned in the planned price1. 
    How the variant should be created to capture the planned price for calculation when using the variant ZPC1.
    Kindly help me in this regards
    Regards
    Vasantha

    HI,
    The requirement is to execute the cost estimate quaterly for planned price 1.
    So we are planning to create separate costing variant to pick the planned price 1 of RM.
    Clinet has the Excel file with the details of RM and Price combination but the prices are not available in SAP.
    We are looking for the Mass transaction to upload the prices in Planned price 1.
    Kindly help.
    Thanks,

  • Price zero in material master:MM01

    When I create a material , system is asking moving avg price, std price (Accounting 1 view). It is mandatory. In some cases I want to maintain price as zero which system is not allowing. How to make system to accept proce as zero for a material.

    Dear,
    With a standard price S in Material master you can enter price as Zero but as soon as you enter Zero goes & SAP treat is as a blank field & issues a message "Enter a price" .However even if you don't enter price, you can save the material.
    Or You can manually maintain the price for Material in t-code MR21 as zero.
    Regards,
    R.Brahmankar

  • Moving average price of the material is negative

    Hi GUrus,
    Can anybody please expklain me why we get the moving average price of the material to be negative. PLz xplain with an example clearly. Thanks in advance
    Thanks
    Anusha

    Dear,
    Please rfer the OSS Note 753286 you will get the reason for it.
    The invoice price is constantly less than the goods receipt price.
    The invoice verification tries (in stock coverage) to subseqently debit resp. to credit the difference between value of goods received and invoice item value to the stock.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Mass maintainenance of material master for the field MARC-NCOST,SOBSK

    Hi
    While maintaining two fields NCOST and SOBSK for hude materials using MM17 transaction, the transaction executed properly while saving the transaction. There is no warning and error messages for all materials. But it was not updated in material master or in tables. for other field relavent to MRP updated correctly.
    when I am maintaining manually for each material it is taking the value update the same.
    Please explain the problem why it was not updating and let me know the solution.
    Regards
    Kishore

    Hi,
    Thanks for ur response.
    I am getting green light. Please note the application message given below.
    "The material cannot be maintained since no maintainable data transferred
    Message no. MG160
    Diagnosis
    You wanted to maintain an existing material master record as follows:
    By changing it
    However, you have not yet maintained the material master record for the organizational levels and data fields specified, or user departments selected. You can therefore process this data only in Create mode.
    By extending it
    However, you have already fully created the material master record for the organizational levels and data fields specified, or user departments selected. You can therefore process this data only in Change mode.
    In both cases, this message can appear if there is no maintainable user department left. This occurs if you have not set the Check required fields indicator when transferring data (program RMDATIND). Although the absence of an entry in required fields does not then necessarily result in an error, the number of maintainable user departments is reduced accordingly.
    Procedure
    Depending on the cause, maintain the material master record in Create or Change mode, or also transfer the missing required fields."
    where can I find IDoc list for this transaction.
    Regards
    Kishore