MRP minimums suggest wrong purchase orders

Hi,
We have a problem with a customer that is usign the MRP the message is in SAP and turn it to de SDN forums for a correction in a future release. In the following DRQ you can look for the DRQ and message that have the detail of the wrong behaivor.
Description of requirements: (Please provide a detailed description)
This case was reported because if we run the MRP wizard tool using minimums it doesn´t recognize the PO created. When we create a new PO to satisfy the minimum required or any sale order which their lead time required is less than 21 days after the PO created (it means that the items will not arrive at time to satisfy to the client) the system do not recognize this PO created and still requesting it u201Cnu201D times to satisfy this demand because it will never satisfy it, and that´s because the lead time with most of our suppliers are 21 days and some articles which are expired or will be soon, still requesting until the items arrives at the warehouse and be registered in the system.
Most of our articles (70% aprox.) come from foreign suppliers and the lead times that we have with them are 21 days; so as you can see is very necessary for us that the MRP tool run well because that means that the responsible to make the purchases will trust in the MRP recommendations to make the purchase process faster than it is right now and principally because we want to control our stocks to reduce it at least in 40-50%.
Valid as of: (Date that this legal requirement is applicable)
No legal requirement.
*Business needs: (Please describe the impact on your business, if the
functionality is not realized)*
the system can create false purchase orders, this alters the integrity of the information to make actual purchases

Mauricio:
Hola, mi es Osel y trabajo en un partner de Chile.
¿Respondió alguien a tu requerimiento?
Gracias
Osel

Similar Messages

  • MRP not considering open purchase orders when planning for open sales order

    Dear Experts,
        1.I have open sales orders as well as planned Independent requirements for finished goods for the current month. Also I have open puchase orders for raw materials which is part of the Bill of material of the finished goods for the current month.
    Please what do i need to do to make MRP consider my open purchase orders when the system is planning for the open sales orders.
    2 what tcode can I use to delete all purchase reuisitions in the sytem

    There was no response to these questions so i had to close it to make space for another

  • MRP: how to avoid Purchase orders/ Production orders generation

    Hello,
    I would like to know how can I avoid the generation of purchase orders / production orders for MRP execution. I am interested in knowing which are going to be my future needs for a material running the MRP, but I am not interested in generating any new Purchase order / Production order.
    I've been changing some parameters in the MRP 2 tab: procurement type, but I think that it is also related with MRP type or MRP group or both. With the procurement type I've only been able to change the purchase requisitions to planned orders and viceversa.
    Any suggestions?
    Thank you

    Hi Cristian,
    W/o MRP run you cannot get the requirements at lower level.
    Please understand:
    FG - Stock 10, IndReq 20; Halb - Stock 5; RM - Stock 2
    > MRP run >
    FG - Stock 10, IndReq 20, PldOrd 10
    Halb - Stock 5, DepReq 5, PldOrd 5
    RM - Stock 2, DepReq 3, PurReq 3
    So, via MRP run the requirements are calculated with planning proposals together. As I told you this is material requirement planning, this is the very purpose of MRP.
    If you only want to display the stocks and requirements, create a query / riport for this purpose and use the appropriate filter.
    Csaba
    (sorry, refresh button helps only if you change the PO, PrdOrd, etc > one level under the material you can see the effect)
    Edited by: Csaba Szommer on Sep 2, 2008 1:42 PM
    Edited by: Csaba Szommer on Sep 2, 2008 1:43 PM
    PLEASE NOTICE THAT W/O MRP-generated-PldOrd YOU WON'T GET THE DepReq.
    Edited by: Csaba Szommer on Sep 2, 2008 1:50 PM
    Edited by: Csaba Szommer on Sep 2, 2008 1:51 PM

  • Wrong purchase order item in inspection lot record

    we have a purhase order in which item no. 1 & 2 have the same material code .
    GR  has been done against item no. 2 in MB01.  Also the usage decision has been done
    in QA11 for the inspection lot no. generated. Now when we see  the purchase order data in
    inspection lot in qa13 the value in  purchase order item no. is  1,whereas the GR has been
    done against item no. 2.
    Please tell why the inspecton lot is picking wrong reference of Purchase order item.

    Thanks Jürgen L.     for your reply.
    I have made some test cases on development server but they are showing correct reference.  To me also  it looked program bug,

  • Wrong Purchase order please help

    Frdns
    i posted PO with wrong vendor,
    so is there any way i can change the vendor on the same PO or i can cancel the PO ?
    Please help
    Thanks

    If you haven't done a goods receipt then you probably should delete the PO. You may want to post this message in the "Materials Management" forum as well.

  • POR u2013 Wrong purchase order response status

    Hello experts,
    We use SRM server 550.
    We customize the POR in the EBP. We donu2019t use SUS.
    After creating the POR against the PO we want to search PO under the status "confirm by vendor" but when we look for order under this search we do not see results.
    We also see the POR in status "in process" under the PO document history.
    When we get partly POR, for example we get 5 pieces in the POR and in the PO we have 10 pieces. 
    Do we need to execute a any program or WF object or BADI for the option to look the PO under the status "confirm by vendor"?
    Thanks.
    Isiaki

    Hi
    Did you set up your tolerances in SRM and then you need to activate the POR Workflow for the system to automatically process the POR if this quantity variation is acceptable to you .Otherwise it will create a work item for approval.
    Regards
    Virender Singh

  • MRP and purchase order delivery date

    Hello
    Question about MRP
    we would like that the MRP run takes into account purchase order with a delivery date in the future
    Say the MRP run 10th of Oct we want that all purchase orders open with a delivery date in the future takes into account the quantity that needs to be ordered TODAY
    EXAMPLE
    Minimum stock 5
    Wse stock 0
    Purchase order delivery date D+1 10
    Lead time is 5 days
    So if you run MRP the systems proposes 5 to order today but they do not want  to order 5 because there is a coming purchase order D+1 of 10
    Does anyone knows how the pruchase order of 10 is taken into account in the MRP run ?

    Unfortunately, one of the weakness of SAP MRP is if a purchase order and/or production order is late, MRP will tell you to order it again instead of expediting.
    We have overcome this and other issues with our own economical planning enhancements. If you are interested you can contact me with your contact information

  • Purchase order Picks Wrong GL

    Hi Expert,
    Can you guide us, There some 5 purchase order ,out of that  3 purchase order picking wroght GL account but 2 purchase order picking Wrong GL account.
    Where as we have same material for every purchase order including the Valuation class
    So please guide us, why Purchase order picking wrong purchase order. and how can we correct the GL account in purchase order.
    Regards
    Santosh Kumar

    Hi Expert,
    Can you guide us, There some 5 purchase order ,out of that 3 purchase order picking wroght GL account but 2 purchase order picking Wrong GL account.
    Where as we have same material for every purchase order including the Valuation class
    So please guide us, why Purchase order picking wrong purchase order. and how can we correct the GL account in purchase order.
    Regards
    Santosh Kumar
    Santosh,
    Make your question 1st. You have been telling PURCHASE ORDERS and nothing else. Pls know what you want.
    Suraj

  • MRP automatic create Purchase Order ?

    Is anybody knows can MRP create Purchase Order directly skip P.R ?
    Thanks !

    Hi,
    This is possible through PR only.
    Tick the automatic PO and Source List fields in purchase view of the material master for the vendors on whom you would like to release PO automatically. Create a purchase info record. Create source list. In the last column in the details screen of the source list check the field relevant for MRP set the correct parameters for running MRP. But PO can not be created automatically after MRP run.
    The automatic PO creation flag enables you to run a batch job that will convert all selected Purchase Requisitions to be converted Purchase Orders in the background.
    You may consider scheduling agreements if you want MRP to kick out Purchase Orders. Set the flag in the source list for the scheduling agreement to "2" enabling MRP to kick out delivery schedules for future requirements. If you want to fix the schedule within a certain period you have two options.
    1. Using firm zone - firms all orders within this period . Refer additional data screen of the scheduling agreement at the vendor material level.
    2. Planning time - all new orders outside of the planning time fence - refer MRP 1 view of the material master
    Above document i cpied from link <b>Arif Mansuri  <b>New to Materials Management / Warehouse Management?</b></b>
    Raghu

  • MRP RUN ON PURCHASE ORDER

    Hello
    i want to run mrp for inter plant purchase order, in this case i don't want to create sales order for the purchase order received from alternate plant, is it possilble to run mrp on all purchase order item without creating sales order to it?
    Regards
    Nishj

    Hi,
    I think a STO (Stock Transport Order) flow should meet your need.
    In OMD9 define a special procurement key for plant which is sending you the PO.
    For the special proc key maintain Proc type as F, Spl. prc type as U, then specify Plant - 2 in plant field.
    In MRP - 2 view of the mtl in Plant - 1 maintain this special procurement key.
    Now when MRP runs in plant - 1, it will generate a stock transport requisition for Plant - 2.
    In Plant - 2 maintain a procurement key say E if its in-house. Run MRP for plant - 1 first followed by Plant - 2.
    This way you wont have to follow the PO - SO flow.
    Hope it is clear.
    Regards,
    Vivek

  • Planning file entry and purchase orders

    Hi all:
    The documentation for MRP planning states that the planning file entry is updated for relevant changes to the material that includes among other things creation of purchase orders for the material.
    In our system, MRP requisition creation does update table MDVM as part of the MRP run. However, purchase order creation does not update the planning file entry, even though the documentation says it should.
    Anyone ever encounter this? Are there controls that need to be set?
    thanks in advance
    weston

    Not sure where you had read that a Purchase order creation updates the PFE. Have a look at this.
    http://forums.sdn.sap.com/thread.jspa?threadID=2129091&messageID=11046363#11046363
    Edited by: UKSAPPP on Feb 16, 2012 6:27 AM

  • Empty list in Purchase Order Release

    I have the components and notes applied as suggested for the Approve Purchase Order Application.and configurations are done as required in the document.App Implementation: Approve Purchase Contracts - SAP Fiori principal apps for SAP ERP 1.0 - SAP Library
    Back-End/Front-End Server
    Back-End/Front-End Component
    Technical Name of Software Component
    Support Package Level
    Back-end server
    Back-end component
    SRA001 1.0
    04
    Front-end server
    Front-end component
    UIX01EAP 100
    03
    But the Po s are not displayed in the application. and no errors are thrown in the chrome console. attached are screenshots for suggestions
    NO Purchase Orders count and no errors in the console.
    No Purchase Orders displayed and No errors in the console
    QUery of the workflow returing Null values from the request
    WorkFlow Collection empty in the gateway query
    i had also checked the task id properlyassigned and maintained in backend
    spro -> mm -> purchasing -> Purchase order ->Approve purchase order app
    and checked Trusted RFC Connection was  maintained properly.
    Log on security was filled with Current user.
    I have unreleased PO in my system but not displayed.
    How can this issue be resolved ?please suggest

    i realised that i have nt configured and defined an approval scenarion in my gateway SPRO settings.
    To do the same i am following the guide http://help.sap.com/saphelp_fiori/fiori10_install_en.pdf page 58 , to define an approval scenario.
    As per the guide should define an approval scenario in spro at
    In your SAP NetWeaver Gateway system, run transaction SPRO and choose SAP Reference IMG >SAP
    NetWeaver >Gateway Service Enablement> Content >Task Gateway Service> Scenario Definition .
    and i could find the exact location to define a scenario
    my settings screenshot in SPRO, and Scenario Definition is not available in SP08 embedded gateway system

  • I need output type NEU automaticaly for create purchase order document type

    Dear Experts,
    I need output type NEU automaticaly for create purchase order document type NB
    when transaction code MN04, I am doing the following:
    (1) I selected the third option Purchasing Output determination: Document type
    (2) I selected the output type NEU.
    (3) In condition records in document type , i have chosen NB.
    (4) In name its automatically coming as Purchase requisition
    Please suggest how Purchase Order NB will come

    Hi,
    Check & press F4, NB Purchase Order (for catagory F) will be there after entering PO output type NEU & then maintaion the condition record in MN04.
    Output type NEU automaticaly defaulted during purchase order creation with document type ,then just fine tune the output (message) type in following path:
    SPRO--->MM->Purchasing>Message>Output control->Message types> Define message type for Purchase Order----->Fine-Tuned Control: Purchase Order
    Now here select the check box corresponding to your output(message) type NEU to have print output automatically displayed & save.
    Now try to creating Purchase Order & you will have default message type NEU.
    Regards,
    Biju K

  • MRP Minimum order qty not recognized

    Hello together!
    We found out (note 862814 ) that mrp does not manage minimum order quantities right (see below).
    Version: SAP BUSINESS ONE 2007 A PL 6
    Description of requirements:
    Dear Madams and Sirs,
    MRP Wizard yields unexpected result.
    For an item having Minimum Stock 4 and having only two item in stock MRP suggests only two items for
    purchase though Minimum order Qty. is 3.
    From my point of view this result is wrong.
    Please help us !
    Wrong purchase amount of 2 items is proposed
    Proposal of 3 items as Min oOrder Qty. is 3
    Partner / Kundenkontakt: bob Systemlösungen
    Abwicklung auf Englisch möglich? (Antwort 'Ja' vereinfacht die Bearbeitung Ihrer Meldung) Ja
    Name: Daniel Rosen
    Valid as of: ASAP
    Business needs:
    As there are hundreds of items to be ordered at the vendors, it is almost impossible to control the Minimum order Qty. Ordering non adequate quantities results in bad prices! This should be a basic function in MRP.
    Examples:
    For an item having Minimum Stock 4 and having only two items in stock MRP suggests only two items for
    purchase though Minimum order Qty. is 3.
    Current Workaround:
    Laborious control of every Purchase order from MRP suggestion.
    Proposed solution:
    MRP should recognize Minimum order Qty. Best it could be set individually if Minimum order Qty is recognized or not.

    Hi
    did you define default warehouse for items?
    If it is true: did you select the default warehouse for the MRP process? Did you select another warehouse?
    If you select another warehouse (not default) the behavior is correct.
    Kind regards.
    Agustin

  • Purchase order status in MRP run

    Hi Gurus,
    I have a doubt in MRP run.
    While doing the MRP run, can there be any open PO s or is it mandatory to close them.
    Can you also please suggest me on how to run the MRP.

    Hi,
    MRP Run
    Purpose
    The Material Requirements Planning (MRP) function enables you to plan material requirements for complex manufacturing processes. You use the MRP Wizard to create and run MRP scenarios. The MRP Wizard generates recommendations for the production and purchasing orders required to produce the final product on time and in the required quantity. You then use these recommendations to create production and purchase orders in the Order Recommendation Report.
    The order recommendation cannot be issued for requirements that happened in the past (before the present day). Since the purchasing or production process cannot be completed in time, the MRP does not mix the real past data with new recommendations for the same period.
    Prerequisites
    ●     You have defined the
    ○     Planning system
    ○     Procurement method
    ○     Order mutliple
    ○     Minimum order
    ○     Lead time
    See also: Item Master Data, Planning Data Tab.
    ●     You have set the time interval between orders. See also: Define Inventory Cycles.
    ●     You have defined the appropriate items as non-production bills of materials (if required). See  also: Item Master Data, General Tab.
    ●     You have defined default warehouses. See also: Define Warehouses.
    ●     You have defined forecasts. See also: Forecasts.
    ●     You have selected the Consume Forecast option to make the system exclude existing sales orders from the forecast. If this is not selected, the forecast considers existing sales orders as an additional requirement. See also: Sales Order.
    ●     You have set the planning definitions. If you chose Consume Forecast, you have defined the consumption method, days forward and days backward. See also: General Settings, Inventory Tab.
    Process Flow
           1.      Start the MRP Wizard.
           2.      Create a new MRP scenario or select an existing one. (See also: MRP Wizard: Select New or Existing Scenario.)
           3.      Define the parameters for your scenario, such as the planning horizon and item details.
    You also choose your display preferences. (See also: MRP Wizard: Scenario Details.)
           4.      Define the data sources for requirements that you want to include in your MRP scenario.
    For example, you define whether you want to consider the existing stock or the minimum stock level. You can also include a predefined forecast. (See also: MRP Wizard: Data Source.)
           5.      Save the scenario or run it.
    After you run the scenario, the system displays the MRP Results.
    If there are red figures in the result table, solve the problem and re-run the MRP.
           6.      Analyze the MRP results. You can display the final stock quantity before the MRP run or after it.
           7.      Save the recommendations and exit the MRP Wizard.
    Result
    After completing the MRP Wizard, you still need to create the purchase and production orders in accordance with the MRP recommendations. See also: Order Recommendation Report.
    Hope this will help.
    Reward Point if helpful
    Thanks,
    Raja

Maybe you are looking for

  • How do you monitor a background thread and update the GUI

    Hello, I have a thread which makes its output available on PipedInputStreams. I should like to have other threads monitor the input streams and update a JTextArea embedded in a JScrollPane using the append() method. According to the Swing tutorial, t

  • Accounting Documents - Assignment feild  error

    Hi All,   I am creating a   contract, line item of contract having an item category relevant for time based revenue recognition. 1) When I am billing the contract, the accounting document assignment field (line items) is populated with the contract n

  • 11i : Can we run Apache and Forms on cluster for failover?

    Hi... We are currently running 11.5.5 successfully on 4 servers: URANUS (cluster made up of HADES and ATHENA) : database and reports ARTEMIS : forms server PEGASUS : http server We are now attempting to reconfigure the application architecture to inc

  • ANSI/9i Join Syntax and Pretty Code

    I've always tried to keep my SQL statement code formatted in a way that I think helps readability. I picked up the following style because I found it easy to quickly find the FROM clause and the JOINS or conditions: select e.ename,        e.sal,     

  • How to identify which applicarion is using the DVD burner?

    How to identify which applicarion is using the DVD burner? Ot is not allow me to burn the DVDs genetrated in the Final Cut 7