MRP - Planned Delivery Time as 'Number of workdays' - How ?

Hi All,
We want to use 'Planned Delivery Time'(PDT) as 'Number of workdays' rather than 'Number of calendar days' while running MRP (Single item, multi level) from MD02 AND eventually that would be reflected in 'Availability date' in MD04. Can we achieve this by config or we need to search a proper user exit / BADI / enhancement spot for this ? Any suggestion on this is most welcome.
Note - Factory Calendar ID has been maintained properly with Mon - Fri as working days.
Thanks,
Ashok

Hi Csaba,
Thanks for your input. The link you have provided does give information on how to assign the factory calender at plant level. However it doesn't answer to my question of how to use 'Planned Delivery Time' as 'Number of workdays'  rather than 'Number of Calender days' .
My concern is 'Is it possible achieving this ? If YES, How ? By using config OR by any enhancement spots / User exits ?'
Any suggestion is welcome.
Thanks,
Ashok

Similar Messages

  • MRP - Auto creation of del schedule lines based on planned delivery time

    Hi,
    We have activated MRP (type PD) where Purchase requiesition is auto created by system for requirement quantity. We require to optimize delivery schedule in such a way that entire PR quantity is broken into various delivery schedule based on planned delivery time and requirement.  Scenario can be further explained with following example.
    Material Requirement for a month is say 1,25,000 units
    Closing Stock say 25,000 units
    PR Generated by system for 1,00,000 units. The entire quantity is schdulled with only one delivery schedule line as per planned delivery time. 
    The requirement is to generate multiple delivery schedule lines automatically in Purchase requisition based on planned delivery time so that Purchase orders can be placed with system generated delivery schedule lines.
    How can it be achieved ?
    Regards,
    Nirav Kinkhabwala

    Nirav,
    This subject has been discussed repeatedly in this and other forums.  I must assume that you overlooked the rules of engagement, which state that you should first search the forums and other public sites, before posting questions here.
    Standard SAP MRP cannot be made to generate multiple items in a Purchase requisition.  The functionality you seek is usually achieved when converting purchase reqs to Purchase orders, where many single purchase reqs can be adopted into a single Purchase order.
    You also might want to investigate use of Vendor Scheduling agreements.
    Best Regards,
    DB49

  • Planned delivery time in Scheduling agreement and MRP

    Hello,
    Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.
    Regards, jaana

    This can be customized in
    SAP Customizing Implementation Guide
    -> Production
    --> Material Requirements Planning
    ---> Planning
    > Procurement Proposals
    > Define External Procurement
    Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

  • Planned Delivery time not considered after MRP run for scheduling

    Dear All,
    After running MRP, the planned delivery time maintained in Purchase info record is not taken into consideration for calculating start date of the schedule line of externally procured material generated by the system.
    Planned delivery time is 3 days & Requirement of parent material falls on 15/02/2010. With this, system should calculate the start date for schedule line as on 12/02/2010 considering 3 days Planned Delivery time.
    Any idea as to what might have gone wrong?
    thx for your help in advance.
    Rgds,
    Ranjeet

    Hi,
    Determination of PLD from the Purchase info record is maintained in transaction code:OMDT. Planned Delivery time is also maintained in Scheduling agreement. However, it is not calculating delivery date as well as release date.
    Rgds,
    Ranjeet

  • Report with material number and planned delivery time

    Is there any standard report with material number and planned delivery time ?

    Hi,
    I do not know any standard report. Please try SE16 + MARC...
    BR
    Csaba

  • Planned delivery time as workdays

    Hello,
    Do you know if there is any way to get the planned delivery time (MRP2 / MARC-PLIFZ) to workdays ?
    For us, goods do not travel over week-end, that's why it does not work well for us.
    It seems, that the standard version does not allow to calculate delivery time in working day. Do you know which user-exit I could use to change that ?
    We create PR with MDBT, MD03 and MD01.
    Thanks,
    Regards,
    PYR

    Hello,
    Thank you for your replies.
    Could you tell me where I could define a calendar for my vendors ?
    You say that delivery time depends upon the working of the vendor, but I didn't manage to define the working days of the vendors in SAP.
    Thanks

  • Consider planned delivery time field in MRP Areas

    Hi,
    I would like to know if the "Consider Planned Delivery Time" field in the MRP areas is taken into the scheduling of materials during MRP run? From the help documentation, it seems to be yes. Otherwise the system will take the Planned Delivery Time from the Plant level. May I ask how we can tick this field for all materials? We are currently in the process of activating the MRP areas in our system. Before, we didn't use the MRP areas but we think the need for it has arrived. Is there a mass maintenance tool to do this? Or do I have to use LSMW? Thanks!
    Regards,
    Chester

    Hello Chester
    If you flag the field "consider planned delivery time" the planned delivery time defined on the MRP area will be considered by MRP. You should tick it for all the materials if the value from the MRP area should be considered.
    Also, the report RMMDDIBE can be used for mass processing of MRP areas.
    BR
    Caetano

  • Simoultaneous planned delivery time (MRP)

    Dear Experts,
    I would like to set my MRP for material purchases in order that I can have 2 different lead times, depending on the route (air/sea)
    For instance, if MRP can supply enough material with 1kg or less, then it should take a shorter lead time for it would be air freight than if the minimum necessary was more than 1 kg. (Actual freight lead times= air 60 days, sea 90 days)
    Best regards
    Marco Aramini

    Hello Marco
    It is possible to have different lead times for different vendors on MRP.
    On the customizing transaction OPPQ, choose the option "external procurement" and make sure that the flag "scheduling: info rec agreement" is set.
    With this setting, the planned delivery time is read from the info record or from the scheduling agreement.
    After that, you should create a quota arrangement for both vendors (see note 1508647 for details).
    On the quota arrangement, you can use the minimum and maximum size to define that the source will only be selected if the lot size is higher than 1KG or smaller than 1 kg.
    If have a more complex logic to select the vendor, you can use BAdI MD_MODIFY_SOURCE.
    BR
    Caetano

  • Planned delivery time in material master

    Is planned delivery time in material master considering holidays ? I mean when I say 7 days, is it one week and 2 days or only one week ?

    Dear Balaji,
    If you push F1 when your mouse is set on that field you will see that help says that PDT is defined as calendar days. However, you can carry out some changes:
    http://www.sap-img.com/materials/planned-delivery-time-as-workdays.htm
    About meaning of PDT:
    http://www.sap-img.com/production/calculation-to-determine-the-delivery-date-and-release-date.htm
    In addition to that link, you can use safety time as well (with this setting you can pull back in time the requested availabilty date during MRP run). You can also use PDT in info records if you have several source of supple for one material.
    BR
    Csaba

  • Planned Delivery Time from Material Master instead of PIRs

    Hi SAP Gurus,
    Do you know if there is a way to have MRP look at the Planned Delivery Time from the Material Master (MRP 2 tab) instead of the PIR?
    We would like to create global PIRs with a PDT of 1 and have the Material Master PDT set to a different number (example 5).  So when MRP runs it will read 5 instead of 1.
    Any additional information is appreciated.
    Thank you
    -nic

    Hi Nicholas,
    In Standard SAP will consider Planned delivery time maintained in Inforecord and than time maintained in Material master. Inforecord has higher priority than material master. When a requisition is manually created, the Planned Delivery date will always be taken from the material master.
    For MRP you can make setting OMDT for your plant or MRP group to determine planned delivery time.
    Deactive the flag 'Scheduling according to purchasing info record or agreement' in Customizing (Plant or MRP group). and test the same.
    Regards,
    R.Brahmankar

  • Planned Delivery time in case of Scheduling Agreement

    Hi All,
    Does system consider the planned delivery time in case of Scheduling Agreement for Vendor like in normal Purchase order and requisition?
    I am doing the MRP run, but system is taken planned delivery time into consideration. I have one material that is Inhouse produced material for plant X and Y Plant needs this material for further making of a finished goods.
    Y plant have scheduling agreement for STO from plant X. After MRP Run required Delivery date in plant X for Material is same as plant Y. but from Plant X to Y, it take 4 days to reach. So Ideally in Plant X this delivery date should be less than 4 days as plant Y.
    Please look into the issue and reply if you have some answers.
    Thanks
    Pavan

    Hope you have maintained different Planned Delivery times in plant X and Plant Y as per your requirement. For procurement in Plant Y the system would consider the planned delievry time maintained in Plant Y. If you want in-house production time to be considered with Basis date sheduling during MRP run in PLant X then enter the in-house production time approprietely. Else if ou want to consider the exact routing times then consider Lead time scheduling in plant X.
    If the above are maintained properly then you should get the desired result.
    Regards
    Ramanujan

  • System is not considering Planned Delivery time

    Dear Gurus,
    As iam planning for the month of January and running the MRP,schedulelines are getting generated but system is not condering Planned Delivery time maintained in the material master ie. 7days.Following is the example:
    I have a FERT-X with a component A-1PC in its BOM and its planned delvery time from vendor is 7 Days.If iam running the MRP on 13/12/2010 for FERT-X  100 PCS for January1,2011 then the schedule lines are getting generated for for component A is on 01/01/2011.But PDT is maintianed in material master is 7 days and same has been maintianed in vendor inforecord.But system is not considering it.
    Kindly help to resolve the issue.
    With Regards.

    I have one ROH which has two different vendors.
    Two scheduling Agreemnt with target qty 100000 kg each.
    Two different Vendor info record with Min. order qty maintained.V1-1000Kg,V2-6000Kg.
    One source list with two vendors and with respective scheduling agreement.
    Quota arrangement is there in which SOB is maintiained 50:50.
    I hv the requirement of 3084 kg of ROH.
    I run the MRP and two diiferent schedule lines are getting generated with 50:50 qty as mentioned in Quota arrangement.
    Not considering the minimum order qty maintiained in vendor info record.
    The above process is correct
    Only One doubt In Quota Arrangement?
    IS two schedule line is created after MRP run?
    Generally System will  select a vendor Whose Quota value is less
    quota rating   = quota base quantity + quota-allocated quantity/ quota
    Edited by: Sundaresan . E. V on Dec 14, 2010 3:26 PM

  • Is planned delivery time is considered in scheduling agreement ????

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"". System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) G .R processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 10.07.2008
    Please Guide . How i can take care of that time which is requiered at vendor ends.
    Regards
    Rahul Bhardwaj

    Go to OPPQ for that plant
    Click on "External Procurement " tab and check if you have maintained any planned delivery time?
    Tick indicator " Scheduling info record/agreement " (This will take Planned del time specified in scheduling info rec or agreement)

  • Planned delivery time issue

    Hello Experts,
    We have below requirement.
    Created sales order for a particular material. Planned delivery time is picked from info record for that material and PR has been created.
    We are converting PR into PO and the planned delivery time is fine. Now we are updating the ASN from vendor with some prior dates. In MD04, the same got updated. However the sales order still shows the old planned delivery time only. How to get the new planned delivery time  in the sales order based on the ASN updated in PO.
    Example:
    Material: A
    Planned delivery time is 10 in info record
    Created sales order. Planned delivery time in the sales order is 10. PR created with fixed vendor and planned delivery time is 10 days from the date of creation.
    Converted PO.
    Now we received the ASN from Vendor that the vendor will deliver this material in five days. So accordingly we are updating the ASN in PO with delivery date.
    In MD04, we could the new planned delivery time based on the ASN. However sales order delivery still shows the previouls delivery date only.
    How to get the new delivery date in the sales order based on the ASN update?
    Regards
    Bala

    This is not standard SAP logic. Required delivery date on the original line item stays as it was when you issued the order. Then you create a confirmation (ASN) that is relevant to MRP with the updated delivery date. Planning sees the new date and acts accordingly, and also in the order you can see both "old" and "new" (in the confirmation tab).

  • Planned delivery time

    Hi,
    I have created a sale order on 1/7/2009 with a material which has planned delivery time of 4 days.
    Now when I go to the schedule lines screen I see that the delivery date corresponding to the confirmed quantity is 1/8/2009.
    Why is not SAP taking the 4 days into considerations while determining the delivery date?
    Please see below the screen shots:
    Scheduling configuration in material master:
    [http://i40.tinypic.com/14b2fyc.jpg]
    Schedule lines screen shot:
    [http://i44.tinypic.com/9pxkzc.jpg]
    Sincerely.
    Ketan

    Hi,
    You seems confused with planned delivery time in MRP 2 view of material master to Sales order delivery date.
    Material master Planned delivery time is for the material which is procured externally  through PR -- PO process.
    In Sales order the delivery date is with respect the ATP--Avalible to Promise.
    If the stock is avalible in the storage location on the date of Sales order creation, then system will consider the delivery date an the basis of confirmed qty in the sales order. You can check in CO09 for confirmed qty.
    rgds
    gsc

Maybe you are looking for

  • Adding a 2nd iPhone - 1 Apple ID or 2?

    Hey folks: I've done a fair bit of searching on this, but I still have some unanswered questions.  I have a 16GB iPhone 4 and we just ordered my wife an 8GB iPhone 4.  (We also have an iPad 2 in the household).  I'm probably going to start by just us

  • My website works in IE but not firefox

    this is my web page: http://www.andrew-leonard.co.uk/Mallorca/mallorca%20ferns.htm It usess css to define layers and javascript to show and hide the layers. It uses a dhtml menu system by Milonic to execute the javascript This is part of the code for

  • Oracle PL/SQL or JavaScript Interaction with a PDF Document

    I'm new to LiveCycle - be gentle. . . :-) My department is attempting to develop a web application which will, among other things, generate fixed layout forms filled with data from the database or from an application web page. The web pages for this

  • Contents of a custom print program for a custom smartform

    Hi... Can you please tell me if we are writing a custom print program from scratch for a custom smartform for which there is no standard form available what are all the things that need to be coded in the print program.. My doubts on this are if we a

  • Dialog with a lot of XML content takes minutes to open in IE7.

    Good day to all. This is my first week with JDeveloper ADF, so, please, be forgiving. I have a page, which has this code <af:commandButton text="Show XML" id="cl2" action="dialog:showxml" useWindow="true" windowHeight="200" windowWidth="500" partialS