MRP - Problem in scheduling of MRP created schedule lines

Hi,
I am working with single level BOM of FG and trying to generate Schedule lines for RM as per requirement coming from FG - BOM explosion during MRP run - 
Material master setting of RM is  as below -
MRP type - PD,
Lot Size - Ex,
Procurement type - F,
Planned dlv time - 14 days
i am getting dependent requirement as below -
06.07.2009 - 2000 EA
13.07.2009 - 1500 EA
01.08.2008 - 1000 EA
And schedule lines are generated as below -
06.07.2009 - 2000 EA
13.07.2009 - 1500 EA
01.08.2008 - 1000 EA
The date of schedule line should be after taking calculation of planned del time of the RM, which is not happening. I can't understand why?
The planned dlv time is same in all 1) Material Master 2) Scheduling agreement and 3) Pur info record
Please help.
Regards,
Amol

Dear Amol,
the date shown is the ultimate reciet date and not start date.
Since you have already converted PR into schedule lines you will not be able to see the actual start date.
If it was still a PR you can see the release date as planed delivery time days early.
If the requirements date was say 31/05/2009 and you were taking planning run today then the recieved date would come as 05/06/2009.that is 14 days from today.
if requirement well beyond planned delivery time then the planned delivery time will not reflect in recipt date.

Similar Messages

  • Very strange MRP Problem

    HI ALL
    I am having a very strange mrp problem and that is
    I created a material with all mrp1and mrp2 requirement,created the info record and source list for that material.I created a reservation for that material which in turn created the deficiency when I did the MD04.I run the MD03,as per re-order point and fix lot size two Preqs created( vendor was not shown in the Preqs even though I established the source list for the material?).I change these Preqs into PurOrds and did the Gr.Every thing fine till here all changes happened in material requirement list(MD04).Now I did one more reservation and created the deficiency again and run MD03 again with a message that mrp done but this time when I went back and checked MD04, there is no Preqs shown and deficiency remained  same as was before. I did the same exercise on several material and every time I am having the same problem as the 2nd time the Preqs don't show in MD04. Please help me as I check upto my knowledge but unable to resolve this one.

    what is the control parameter of the MRP run that you select.

  • Log for schedule agreement  division created/modify/delete at MRP (MD04)

    Tables CDHDR and CDPOS were saved when the user changed data manually using the transaction ME31L and  ME32L.
    When the new schedule divisions  were create direct at MRP, the registries were not saved.
    I searched for any configuration to activated this registry though without succesfully.

    Transaction AUT10 display the execution process though it doesn't mention exact information was changed.
    Is there any configuration to change the behavior of this transaction or another transaction I could see the information was changed, deleted or inserted?

  • Planned order scheduling in mrp

    hi
    iam trying to run MRP at my client place
    facing problem in planned order dates
    i choosen  tequirement type BSF and strategy group as 11
      in md 61 pir was given in a month of june2008(monthly)
    after mrp run at modo4 iam getting planned order with
    execption message 64 called order date in past
    means iam getting planned order START DATE AND END DATE IN THE MONTH OF JUNE
    where as i need to  my planned order satar date in MAY MONTH and
    end date must be 1st of june
    means i given PIR which is my start of my june month
    checked scheduling parameters which  says backword scheduling, and i choosed planning mode 3 and leddtime scheduling
    plz suggest which setting effects the planned order start and end dates??
    regards
    sasikanth

    hi
    i selected schedule margine key with 0 flots (key000)
    and chossed *LEED TIME SCHEDULING (in mrp controll parameters :-scheduling 2 at MD02 )
    how the reduction strategy helps in this case ,casue i am doing lead time scheduling system has to consider only routing time ??? right ??
    plz suggest how to  arrest message 64
    regards
    sasikanth 
    message 64 diagnosis enclosed
    64: Production finish after order finish                                                                  (P4)
    Message no. MD427
    Diagnosis
    The production finish date calculated using the routing lies after the order finish date that was calculated using the in-house processing time in the material master record.
    As the system uses the order finish date in the planning run, this situation may lead to material shortages if production is not finished until the production finish date calculated by the system.
    System Response
    This exception is displayed in the MRP list and in the current stock/requirements list.
    Procedure
    Check the times in the material master record and in the routing.
    Check whether the order has to be rescheduled in.

  • BADI or User Exit for scheduling in MRP

    Hello,
    I am searching a possibility to influence the scheduling of planned orders, when they are created in the MRP run. There exists a BADI which is called when creating planned orders manually, but not in MRP. Its name is MD_PLDORD_SCHEDULING
    Does anybody know about such an alternative for scheduling in MRP?
    Thanks in advance
    Roland Böhm

    Hi,
    Check these Enhancements
    LMDR2001 User exits restr. profiles of opt. pur.ord.-based load bldg
    LMDZU001 User exits in additional planning
    Regards,
    Satish

  • Influence on lead time scheduling in MRP

    Hello,
    I am searching a possibility to influence the scheduling of planned orders, when they are created in the MRP run. There exists a BADI which is called when creating planned orders manually, but not in MRP. Its name is MD_PLDORD_SCHEDULING
    Does anybody know about such an alternative for scheduling in MRP?
    Thanks in advance
    Roland Böhm

    Hi,
    During MRP run for single material by MD02 or on plant level by MDBT,
    For MRP control parameters-
    Scheduling take value as 2 - Lead time Scheduling and Capacity Planning.
    and run the MRP.
    With this you will get planned orders, and production rates are calculated as per time mentioned in routing.
    But if you take scheduling value as 1 - Basic dates will be determined for planned order, then you system not consider lead time. Dates are picked from material master.
    Srini

  • Generate Delivery Schedules via MRP Planning run

    The company wants to create Scheduling Agreements and generate the Delivery Schedules from the MRP Planning run - MRP 2 view via JIT.
    Can you generate Delivery Schedules from Schedule Agreements if the company does not have an EDI server or APO set up?
    Thanks,

    Shirley Globe,
    You seem to be putting the experts to the test.
    As it was told you, you can generate schedule lines via MRP run. MRP run can be done (e.g.) trough MD01 /MD02 / MD03. Of course, you have to use the proper selection parameters to achieve your goal.
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d2da044af11d182b40000e829fbfe/frameset.htm
    As for how to use SA with MRP please check SAP online help:
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/3b/66596eda7b11d1b6330000e8a738dc/frameset.htm
    Regards,
    Csaba
    Edited by: Csaba Szommer on Apr 9, 2009 7:40 PM

  • Scheduling in MRP Run MD02

    dear all,
    i still confuse for using scheduling in MRP run MD02,
    what is the use of using both scheduling type "1" and type "2"?
    because if i run the MRP using scheduling type 2,  after i generate the planned order, then i can see the capacity planning evaluation,
    but not if i run scheduling type 1
    if i run the scheduling type 1, how can i analyze the capacity planning?
    until now, i always run the scheduling type 2, because i think it is more useful to run scheduling type 2,
    so what is the plus and the minus using scheduling type 1 or type 2?
    best regards,
    MARUFAT

    Hi,
    In simple words:
    The main difference between scheduling type 1 (Basic date scheduling) & Scheduling type 2 (Lead time scheduling & Capacity requirements) is from which records MRP reads the values.
    Basic dates is more like a rough scheduling where the values are read from the material master & the exact operation times are not considered or capacity requirements generated.
    Lead time scheduling is more precise meaning for each in-house produced material it reads the routing & checks the time maintained for each operation, it then calculates the exact times for each operation based on the working days, shift timings, breaks & also generates capacity requirements.
    Now what is the criteria to select... it depends on the business requirement. But the data maintenance for Scheduling type 2 is higher as compared to Scheduling type 1.
    What is the benefit for going for Scheduling type 2.... well it gives you a clear picture on your production planning process & how much capacity is required, whether you have the requisite capacity etc etc.
    Basic date scheduling is preferred when you do not want such fine control on your production planning process.
    For more info refer to SAP help, it should make it more clear.
    Regards,
    Vivek

  • Whether MRP can be carried out for work scheduling GR. 20 i.e. work to orde

    Dear Experts,
    Whether MRP can be carried out for work scheduling GR. 20 i.e. work to order.
    mahendra

    Hi MShirodkar,
    Yes, s and it specifies the time needed to process the material in the operations at the different work centers.
    The GR processing time depends on the order quantity.
    The GR processing time is required to calculate the lot size dependent in-house production time. The system then uses the in-house production time to determine the planned dates for planned orders in materials planning.
    You can define work scheduling times in the material master record in one of two ways.
    Either you enter the in-house production time. If required, you can get the system to update this value from the routing.
    Or you enter the setup, teardown, processing, and interoperation times. If you maintain these values, the system determines the in-house production time on the basis of lot size.
    I hope it clears you doubt any queries please revert me back.
    Regards,
    Madhu.G

  • Scheduling in MRP

    Hi, one fert req one roh to maufacture. we have mentioned 2 days for fert mat as in-house prod days, 2 days as pland delivery days for roh. after mrp run, how system will schedule the dates? pls explain. we know delivery date in sales order.

    Dear Yadav,
    As per the scheduling parameters given to OPU5 (for plan orders) scheduling takes place in MRP
    There are two types of Schedulings
    1) basic date scheduling
    2) lead time scheduling
    basic date scheduling -  in initial parameters of MRP if u give scheduling as basic scheduling then system takes the data from material master i.e in-house production time. in this scheduling capacity requirments are not generated
    lead time scheduling -  in initial parameters of MRP if u give scheduling as lead time scheduling then system takes data from Routing to calculate dates. here cacity requirments are generated.
    Coming to dates
    if ur maiantaing in-house production time as 2 days for FERT & 2 days as plan delevery time  (without GR processing Time)
    Then system does backward scheduling as (if u maintain backward scheduling in OPU5)
    so total days for FERT to be availble will be 18.07.2009 (starting from today)
    Regards
    kumar

  • Unable to create Schedule line(Maintain sch.agreement)

    Hi experts,
    After running MRP i got Planned order for a certain material and for that material procurement type maintained as "Both internal and external" in material master. After completing the process planned order to purchase requisition, i separately created schedule agreement . Now here i am facing one problem that if i create schedule line with reference to purchase requsition i am getting the error Requisition doc. type NB not allowed with doc.type LP.
    pls anybody suggest is there any prob made in the above process
    Regs,
    SR
    Edited by: SP Ramesh on Jan 1, 2010 8:22 AM

    go to tcode OLME> schedule agreement> select the line of document type LP and then slecte the folled item category and then selce each item category one by one and then click on the second folders link document type and there give source document type NB
    cause of the issue is : the source document type NB is not set with LP document type of schedule agreement

  • MRP does not creates Shcedule Line

    I have a valid scheduling agreement LPA in place. Scheduling Agreement is approved and released status.
    I have source list also maintained for same scheduling agreement with long validity and MRP indicator as 2 - Create Schedule line automatically. 
    I am running MRP using following parameters in MD02.
    Processing key          NETCH               Net Change in Total Horizon
    Create purchase req.    3                   Planned orders
    Delivery schedules      3                   Schedule lines
    Create MRP list         1                   MRP list
    Planning mode           3                   Delete and recreate planning data
    Scheduling              2                   Lead Time Scheduling and Capacity Planni
    Even schedule line and other parameters maintained properly, MRP creates planned order and does not creates Schedule Line automatically. Material Master is maintained MRP Type PD, Lot Size as Replenishment to maximum stock level, Safety stock, No strategy and availability on.
    What I am doing wrong? With same setting in other system it is working perfectly fine.
    Any feedback appreciated.
    Thanks
    PP

    Hi
    Check whether the Agreement Open Target value .
    If the target quantity was completed . so system will not create the Schedule lines for the material
    2. If you mainatian the open period in the smk.
    so system will create the planned order instead of schedule agreement. check

  • Problem In time of creation wprk Scheduled...

    Hi...
    I have faced a problem in time of creation work scheduled, it is displaying a error massage like " Error while accessing public holiday calender on 20100101".
    Can anybody help me to resolve the problem....
    with regards,
    Diptendu

    Hi Diptendu,
    I believe you are creating work schedule rule for the year 2009. So for this, u need to mandatorily generate holiday calendar upto Jan 2010.
    This is because in order to generate workschedule rule for Dec2009, holidays in the holiday calendar should be assigned atleast in the month of Jan 2010 and then generate the holiday calendar upto Jan 2010. So the dates for generating holiday calendar would be 2009-2010
    Hope this would solve ur issue.
    Thanks.

  • Scheduler doesn't create Jobs

    Hello folks!
    We have scheduled some reports with BI Publisher Scheduler in our Development Enviroment and works very fine. But when we passed that reports to Prod Enviroment, BI Publisher scheduler doesn't create any Job (verified in Report Job History and XMLP/QRTZ tables in Database Schema that isn't any Job created). There isn't any error, exception or message, only scheduler doesn't create Jobs.
    Any idea, solution or way to find any trail about that problem?
    Thanks for your preciated time spent in our issue.
    Best Regards,
    Martín

    I am also facing same issue with BI Publisher Scheduler but showing below mentioned error while creating new job.
    Error
    "Job submission failed : Error occurred while scheduling the job. org.quartz.ObjectAlreadyExistsException: Unable to store Job with name: '-1' and group: 'weblogic', because one already exists with this identification."
    Cheers.
    Vishal

  • Cannot create scheduled task, access denied

    Windows Server 2003 R2
    I am logged in as a local administrator and cannot create a scheduled task:
    [Task Scheduler]
    The new task could not be created.
    The specific error is:
    0x80070005: Access is denied.
    Try using the Task page Browse button to locate the application.
    [OK]
    My research lead me to look look in the Group Policy Object Editor for:
    Windows Settings > Security Settings > File System > %SystemRoot%\Tasks
    On this machine, there is no "File System" folder. In the MSDN Library, I find:
    "The File System folder is available only in Group Policy objects associated with domains, OUs, and sites. The File System folder does not appear in the Local Computer Policy object."
    Any ideas?

    found this information, problem solved...
    Problem Description:
    ===================
    When trying to create a new scheduled task, error occurred "The new task could not be created." "0x80070005: Access is denied. Try using the Task page Browse button to locate the application."
    Cause:
    ===================
    The Administrators group lack permission on the C:\WINDOWS\Tasks folder.
    Resolution:
    ===================
    Start - Run - CMD - C:/windows - CACLS TASKS /E /G builtin\administrators:F
    The steps above grant Administrators group full control permission to the C:\WINDOWS\Tasks folder.
    Again, thank you for posting in the SBS newsgroups. Please feel free to contact us again in the future.
    Best regards,
    Robbin Meng(MSFT)
    Microsoft Online Newsgroup Support

  • Creating Schedule lines in Scheduling agreement using LSMW

    Hi,
    I want to upload multiple schedule lines in scheduling agreement using LSMW. I have done the recording and maintained multiple lines in input file. However during execution LSMW creates only one line and keeps on ovewritting the same line. Please let me know how can I create multiple schedule lines.
    Regards

    First you should search for existing standard LSMW migration objects that possibly cover your scenario. These normally take care of complex header / multiple items / multiple subitems relations.
    With a recording you can only load flat structures. Sometimes a "create new  lines" / "enter first line" / "save transaction" logic can be constructed to load multiple items to a header (or even subitems to an item?) with a recording, but this can be pretty awkward.
    Thomas

Maybe you are looking for

  • Xi Data Cache Refresh Problem

    Hello, We have following Problem: We send an XML-Request with HTTP-Adapter to XI and get Data from R/3, works fine. But when we send a Second Request we become an Error. The error comes because in the Java Runtime the XI writes wrong values into Mess

  • How to write selection-screen block on 15th position?

    Hello all, I want to write selection-screen block on 15th position, How can I do this? I know that we can write parameter/select-option on perticuler position using following code. SELECTION-SCREEN BEGIN OF BLOCK b1 WITH FRAME TITLE t7. SELECTION-SCR

  • CRM: using BW cubes in Segment Builder

    Hello all, I am trying to use BW Cubes as data sources in the CRM Segment Builder uisng transaction CRMD_MKTDS. For this purpose I set up RFC destinations and logical systems in both the BW and the CRM 5.0 system. In transaction SM59 the connection t

  • Pricing procedure for Excise

    HI, I maintained Pricing procedure for Excise with the combination of SODISDIVCUS PPDOCPP and i maintained* JINFAC*.......now i would like to maintain customer line item wise discount.but that condition type in DIff pricng procedure.........How can i

  • Error "(-10) -" when updating a BP via the DI API

    Hi, When updating a business partner with iBolt (and add-on which uses the DI API to retrieve, add or update data) we sometimes get the following error message from the DI API: "SAPB1 error: (-10) - " (Yes, the explanation is a mere "-"...) This beha