Hi Experts,
There one  Independant Req per month dated the 1st day of the month.  When I run the MD02, the Purchase Requisition is placed the 1st day of the month. we do not maintain Planned delivery time. We would to have as Purchase Requisition date ; the last date of the previous month.
We have :
01.12.2010     PurRqs     0010011236/00010
01.12.2010     IndReq     ZLS1
We would like to have
30.11.2010     PurRqs     0010011236/00010
01.12.2010     IndReq     ZLS1
Pl explain me what to do!
Thank you for your help!
Rgds
Thibaut

Thibaut,
The easiest way to offset the date of the supply element from the date of the demand element by one day is to put one day into "Goods receipt processing time" in the Material master of each material.  (purchasing tab or MRP2 tab).
Rgds,
DB49

Similar Messages

  • Pricing conditions for the articles are getting triggered one day before the actual activation date to 3rd party systems through job WPMU.

    Hi SAP Guru´s,
    Currently we are sending the pricing, promotions & article master data delta load to 3rd party system from SAP ECC via SAP XI through IDOCS using daily scheduled batch jobs WPMU. IDOC segment - WP_PLU.
    Here the issue is the promotion & pricing data are sent to 3rd party system one day before the actual start date.
    Eg: Promotion 123456 which has start date as 15/05/2014 & ending on 30/05/2014 & was created & activated on 13/05/2014.
    This promotion 123456 is getting triggered from SAP ECC through batch job on 14/05/2014 morning & 3rd party system receives the data on 14/05/2014 & the promotion are getting activated at 3rd party system end on 14/05/2014 itself which actually gets active from 15/05/2014.
    Same in the case for Standard Pricing data which needs to be active from 31/05/2014 once the promotion 123456 ends on 30/05/2014.
    The standard pricing data gets triggered from SAP ECC on 30/05/2014 through batch job & reaching 3rd party system on 30/05/2014 & getting activate on 30/05/2014 itself.
    This creates more issues at the store end as well as affecting business.
    We checked at 3rd party system end & they replied that their system considers the updated time stamp & date to activate the prices & it does not considers the actual active from & active to date. They need the data to be sent from SAP ECC on the effective date of the pricing & promotions.
    Can any one help me how to change the pricing conditions beign triggered through batch job in SAP ECC based on the actual promotion & pricing conditons start date or is there any other process to trigger the data through the batch job on the actual promotion & pricing data activation date.
    Thanks in Advance.
    Thanks & Regards,
    P.P.Shankar

    Hello Shankar,
    Change the lead time in the POS Outbound Profile. You can't put less than 2 days there so data for today and tomorrow will be transferred which also means you need to adjust your batch timing accordingly.
    Sales and Distribution -> POS Interface -> Outbound -> Maintain Profile for POS Outbound.
    See if it helps. The best option would still be that the 3rd part system considers the activtion date.
    Kind Regards
    Kaizad

  • How to set SPD workflow to send email one day before the Due Date? ?

    I need to add a step in workflow for a item tracking list: send reminder email one day before the due date.
    I thought there is an Action in SPD: wait for [Due Date] to equal [Today]minus one day
    But there is no way to do that.
    I figured may be I need to create a calculated field [cal-date] that set to: =[today] plus one day.
    Then in workflow -
    wait till [Due Date] is equal to [cal-date], and send an email
    What is the formula for the above calculated field [Today] plus one day?

    Hi,
    You can add an approval action( such as Start Approval Process) -> click "Approval" -> go to “Change the behavior of a single task” . Then you will
    see the "When Task expires" stage.
    You can have a look at the blog:
    https://www.nothingbutsharepoint.com/sites/eusp/Pages/5-Steps-to-Enhance-SharePoint-2010-Approval-Workflow.aspx 
    Thanks,
    Eric
    Forum Support
    Please remember to mark the replies as answers
    if they help and unmark them if they provide no help. If you have feedback for TechNet Subscriber Support, contact [email protected]
    Eric Tao
    TechNet Community Support

  • Problem in MRP generated purchase requisition.

    Hi Friends,
    We have run MRP via MD02 transaction for one material.
    MRP generated purchase requisition created.
    In that MRP generated purchase requisition, under item level in the status tab we are getting below field values is like below.
    Processing status : No edited
    Block ID: Blocked by requester.
    Due to above values we are not able to convert this MRP PR to PO.
    Could you please let us know is there any master setting is cause of this?
    Thanks in advance.
    Regards
    Jegen Mohan

    Hi Friends,
    After debugging MRP programme, we came to know that there is BADI implemented to block the MRP PR's intially and then z programme called for adding secondary materials/services to that MRP PR's.
    After addition of secondary materials/services to MRP PR's,  Status will be unblock automatically then save the PR.
    This is my client specific scenario.
    Thanks & Regards
    Mohan.

  • Purchase Requisition Date before SC Creation Date

    Hi
    We have a odd situation with a shopping Cart where Purchase Requisition Date (REL_DATE = March 11 2009) before SC Creation Date (March 31 2009).
    Any comments/suggestions?
    Nikhil

    HI
    I think this is an backend PO, the shopping cart created with reference to this PO.  Becase of that this may happen.
    tell me one think it is a production order.
    Regards
    Satish

  • What is the difference between the new 13" MacBook Pros and the previous version of the 13" MacBook Pro?  I purchased an "old" one from Best Buy the day before the announcement of the new models.

    What is the difference between the new 13" MacBook Pros and the previous version of the 13" MacBook Pro?  I purchased an "old" one from Best Buy the day before the announcement of the new models.

    See the specs:
    Compare Notebooks - Apple Store (U.S.)
    Compare with your model. If you are within 14 days of purchase you can exchange for the new model for the difference in price, if any. Be sure to have all the original packaging and your receipt.

  • How do I stop calendar from setting a second alert one day before?

    I have iOS 7.0.6 with calendar synced to my gmail account with CalDAV. When I create a new event in the calendar on my iphone, I set either a single alert or none. When I check back a few seconds later, the alert I set has become the "second alert," and the first alert is set to "one day before." Google calendar correctly shows a single alert, the one I set. If I then delete the first alert, it stays deleted. But then if I edit the even in google calendar, the "one day before" alert reappears on the iPhone. (Though still not on Google calendar.)
    It's driving me batty with all of these false alarms that are actually for tomorrow's activities. Is there a way to set alarms in iOS 7, or is that just a sacrifice we have to put up with to fix the iOS SSL bug? Should I set the current date in my iPhone to be one day late? 

    Settings > Mail Contacts, Calendars.
    Scroll down to Calendars and this sets default alert times.
    If you add an alert to a new appt, it is in addition to the default alert time.
    Either turn off default alert time or set the default alert time to when you want you want & don't add alert to the event when you create it

  • Assign document date to purchase requisition date

    Hi All,
    I have a question regarding purchase requisition. I have a requirement where i have to change the purchase requisition date based on certain condition. I tried to change it in the user exit "MV45AFZZ" when the sales order is released, but at this point the purchase requisition number is not yet created in the database though it is available in this internal table "XVBEP-BANFN" in the include "FV45EFMA_BESCHAFFUNG_SICHERN" of "SAPFV45E". Can anyone tell me when will EBAN table get updated and when should i change the requisition date? I hope the doubt is clear, otherwise let me know.
    Thanks and have a nice day.
    Cheers,
    Ashley

    Hi Ashley
       I have tried on my system and itz working, Can you
    place a break-point in MV45AFZB and see if the flow is
    reaching the place at the point where you need.
       Coming to the Customer Function in
    FV45EFMA_BESCHAFFUNG_SICHERN, have you checked as per
    the documentation of it:
    FU EXIT_SAPFV45E_001
    Text
    Update Purchase Order from Sales Order
    With this customer exit the standard system behavior
    regarding updating order data from the sales order can
    be expanded or restricted.
    The module is called up when the sales order is changed,
    as long as the conditions for changing the order have
    been filled. It transfers the document number, the
    purchase requisition number and a table for the fields
    to be changed in the order (T_PURCHASE_DATA). <b>This
    can be expanded or restricted in the existing
    Customizing.</b>
    <b>The rule is: To change a field with the name
    FIELDNAME, a subprogram (form routine) with the name
    POSITION_CHANGE_FIELDNAME must exist in the program SAPMM06E.</b>
    Try to find if POSITION_CHANGE_BADAT exists in
    SAPMM06E. If not found ask you functional consultant to
    expand it for purchase requistion date and see if it
    works.
    Hope your problem resolves.
    Kind Regards
    Eswar

  • Vendor not able to see bid invitations created one day before

    Hi friends,
    We are workig with SRM5.0 SP08. I have observed that vendors are not able to see bid invitations processed one day before.
    Could you pls suggest the probable reason, if anybody has come across similar problem? Bid invitation version is active and can be seen with purchasers login.
    Your responses will be highly appreciated.
    Regards,
    Prashant

    Hi Marcin,
    all these bid invitation statuses are not closed. its published only. The problem is bidder is not able to see bid invitations with dates in the past.
    Dinesh,
    Ur right. There is also problem with search functionality. In fact I can display list of bid invitations only if I am not giving any search criteria.
    Regards,
    Prashant

  • HT4623 one day before,i update my iphone5 system,but i really don't like the operation,i want change back to ios6.1.4,what can i do?

    one day before,i update my iphone5 system,but i really don't like the operation,i want change back to ios6.1.4,what can i do?

    OK, I downloaded the utility, but during the installation process I was advised to shut down Outlook, or restart it after installation. I immediately cancelled the installation. Obviously, this thing is going to muck about with Outlook. I don't want anything to be touching or looking at any of my installed program unless I tell it too AFTER I fully understand what it is doing and how to reverse the whole process in case it gets mucked up.
    I looked for a manual or some sort of documentation on the configuration utility, but there does not seem to be any.
    Anyone have a link to program documentation for
    iPhone Configuration Utility 3.6.2  for Windows?
    I find it incredilble that there does not seem to be a stand alone, plug the usb cable in, and make a back up (system image) of an iPhone. After all, the thing seems to be hand held computer. Why not have a simple back up utility? Even the newer phones only have, what, a few GB. Lots of images would fit on an outboard TB disk.
    Then if every thing gets FUBAR, simply restore the phone the the last working image.
    Does no one keep controled squential backups of iPhones and iPads like you should do with any other computer, workstation or laptop that is a serious business tool?
    iTunes for back-up. Does and business seriously do that?
    iCloud? I'd be fired if the boss caught me putting client contact information on 'the cloud' or anything outside my secured hard drives. (Unless we have a specific paid contract for services).
    My company does not even allow wifi in the office. Security begins with a hard wired connection.
    sigh....

  • Purchase requisition date in SNP planning book and product view not in sync

    Hello Experts,
    We have an issue with display of purchase requisition date in SNP planning book.
    We are manually entering the PR's for a perticular week from Monday - Sunday(01.09.2014- 07.09.2014), when the last PR is entered on 07.09.2014, it does not appear on the same day in planning book(cell becomes empty) and moves to 06.09.2014, thus quantity on 06.09.2014 is the summation of the quantities present on 06th and 07th.
    The PR dates are appearing correct when we click on display details in planning book and they are correct in product view, MD04 as well.
    Additionally, this is the same date on which daylight saving time comes  into effect.
    Kindly advise if anyone has faced similar situation earlier.
    Many thanks,
    Aditi

    Hi Aditi,
    Check the time zone that you have in your location in ECC and APO.
    Also note it is recommended that you maintain the same system time zone in APO and in ECC. (check tcode STZAC in both systems).
    Different time zones should generate this kind of inconsistencies.
    Kind Regards,
    Mariano

  • I just bought my iMac 2 days before the new iMac was launched. Is that possible that I can replace it with the new one?

    I just bought my iMac 2 days before the new iMac was launched.
    Is that possible that I can replace it with the new one?

    You can return a computer within 14 days of purchase for a refund.
    http://www.apple.com/legal/sales_policies/retail_us.html - Returns in the USA:  iPhones within 30 days, other items within 14 days.
    Do you really mean an iMac2?  If you do you're about 10 years too late in wanting to return it.  I guess if you do have an iMac2 then it makes sense you posted on the iMac(PPC) forum since this one is for models at least 6 years old.

  • User Exit/BADI to change the Purchase Requisition date,creating threw MD02

    Hi,
    I've a requirement to change the Purchase Requisition creation date.
    I'm using MD02 to create Purchase Requisition.
    Based on the requirement if the available qty is less than the required quantity,we can change Purchase requisition date.
    Please let me know if any BADI's/User Exits we can use for this purpose.
    I've checked EXIT_SAPLMEREQ_010. I've kept debugging point nad i run MD02, but it is not stopping in the exit.
    we are using SAP 4.6c.
    Thanks,
    Adi.

    Hi Experts,
    Could you please give me a suggestion for the above problem???
    Thanks,
    Adi.

  • Add one day to the current date

    Hi all,
    A stupid question...
    How can I add one day to the current date in a select. I want something similar to add one month to current date, but with days:
    something like:
    select TO_CHAR (ADD_MONTHS (SYSDATE, -1), 'DD-MM-YYYY')
    from dual
    Thanks

    select sysdate+1 "add one day" from dual;

  • Send a reminder mail to a person in 'Assigned To' 7 days before the 'Due Date'

    I want to create a workflow on SharePoint list and it should send a notification email to 'Assigned To' person before 7 days of Due Date (another column in the list).
    I'm new to SharePoint. Please explain the steps in detail.
    Any suggestions would be greatly appreciated. Thank you.

    Hi Sekhar,
    Hope the below links should be useful to you.
    http://sharepoint713.blogspot.in/2011/09/sharepoint-designer-workflow-to-send.html
    https://social.technet.microsoft.com/Forums/sharepoint/en-US/e85c2fcb-81fa-4c8d-9f0d-3c4799de771b/send-a-reminder-mail-5-days-before-and-1-day-before-the-due-date?forum=sharepointcustomizationlegacy
    https://social.technet.microsoft.com/Forums/sharepoint/en-US/1e2912f4-3119-49b0-b620-e67f629596d0/how-to-send-alert-on-2-days-before-of-task-due-date?forum=sharepointcustomizationlegacy
    https://mysharepointchronicles.wordpress.com/2012/11/05/sharepoint-list-with-workflow-email-reminder-set-to-send-30-days-from-created-date/
    http://markeev.com/Articles/item-expiration-reminders-in-sharepoint-using-workflow.aspx
    Please remember to click 'Mark as Answer' on the answer if it helps you

Maybe you are looking for