MRP run reg.,

Hi guru's can anybody tell can it be config., in such a way that the ext., req., can also be
taken into account while MRP run in consumpotion-based planning if VB is selected as MRP type.
thanx in adv.,
tulja singh

Hi,
In spro/ prodn/mrp/master data/check mrp type :
For mrp type VB you can include external requirements in total horizon or with in the replenishment lead time.
Select the external requirements to be considered by the system such as sub contract req, released purchase req, reservation etc.,
You can copy VB &make required changes & give a different name.
Hope this helps...
Regards,
Ramasamy

Similar Messages

  • Reg: MRP Run for all Materials

    Hi Abapers,
    I have an issue where in using MD01( Material Run), i need to raise one PR for all materials below the re-order stock. Currently system creates one PR for each material below the re-order stock.
    Please throw any ideas regarding this.
    Thank you

    Hi ,
    to procure assembly take 10 days.
    And delivery date is after 2 days
    After MRP run , system will take first backward schedulling from delivery date will take 2 days and going forward scheduling and take 8 days .
    So that from current date system will take 10 days so assembly will procure easily .
    Suppose today date 19/05/2011. And delivery date is after 2 days .( on date 21/05/2011 )
    if MRP is run on 19/05/2011. System will create delivery date 29/05/2011.So assembly will be easily procure within span of 10 days from 19/05/2011 to 29/05/2011. Delivery of FG is easily available on 29/05/2011.
    Regards
    Vinod

  • Reg.MRP Run without sale order

    Dear Experts
    We are in need of MRP run without sale order. I have created Finished product material (T-Shirt) and assigned components to that and then I ran MRP, If I do so, MRP is exploded but result is not satisfied some non components are displayed.
    What is my requirement is ,when I run MRP if there is stock availble production order should be created otherwise Material requirement has to created.
    Pls help what is the configuration for MRP run,
    Thanks
    Rajakumar.K

    Hi Raja,
    One of your requirements isn't available in R/3.
    What is my requirement is ,when I run MRP if there is stock availble production order should be created otherwise Material requirement has to created.
    Standard MRP will create Dependent requirements (demand elements).  MRP will create order PROPOSALs (purchase reqs or planned orders)(supply elements).  MRP can be immediately followed by an additional program that will convert planned orders to Production orders.  All these things are possible.
    However, MRP will not check for the availability of components, and then selectively create production orders.  Availability check, which is not part of MRP, is usually performed at a later part of the production order cycle.
    Regards,
    DB49

  • Reg....MRP Run Materials

    Dear Friends
    i have 300 finished materials now i updated forecast for 50 materials in MD61 and i am going to run MRP in MD01.
    How can i get  MRP run  list only for these 50 materials
    pl guide me
    Thanks
    selva

    Dear Selva,
    1.Is your requirement to get the MRP list for the 50 materials after MRP run or else to run MRP only for the 50 materials for
    which demand exists?
    2.If your intention is to run MRP only for the 50 materials means you can activate MRP run user exit(M61X0001) and run MRP
    based on MRP controller.
    3.If your requirement is to get the MRP list for the 50 materials,you can check this report MDLD or else from MD06.
    Regards
    Mangalraj.S

  • Project Based MRP run issue

    Hi Friends,
    There is one issue reg. Project Based MRP Run as below :
    We are running MRP through MD51 (Project based MRP run). For this we are assigning FG material code under respective WBS Element which generates Network reservation with movement type 281Q  which is base of MRP run in MD51. After MRP run we get planned order generation and then convert it to Production order and execute Production Order to receive Project Stock after GR.
    After receiving Project stock and then selling it through Post Goods Issue through SD cycle, project stock is consumed but network reservation is not getting closed which results in again generation of planned order if MRP is run again. 
    I need your valuable inputs if we are missing any configuration setting which can set Final issue indicator in reservation while Posting Goods Issue (PGI) in SD because FI indicator checking will only ensure reservation doesnu2019t take part in planning again.
    Your earliest reply will be highly appreaciated.
    Regards,
    Tejas

    Hi Vivek,
    Thanks for your reply. Actually my issue has got resolved the way suggested by Mario Adler.
    Hi Mario,
    Thanks for your solution. PGI through Project is working fine for me.
    Hi Krishna,
    Follow the procedure as suggested by Mario which will resolve your issue.
    Once again thank you all for spending your precious time to respond my query.
    Regards,
    Tejas

  • MRP run performance

    Hi,
    We have upagrded from 4.6c to ECC 6.
    During testing, we find that the MRP Run takes very long time, which is very abnormal.
    Can anybody come up with some reason for this behaviour?
    Here are some inputs.
    Planning run through program - RMMPS000
    Parameters:
    NETCH
    Purchase Req - 2
    Scheduling lines - 3
    Create MRP List - 1
    Planning Mode - 1
    Scheduling - 1
    MRP Process for all the materials - activated
    Parallel processing - activated
    Reg
    Velu

    please refer the following SAP notes
    382037
    204517MRP: Performance problems - typical causes

  • Elaborate in MDBT and open scheduling agreement list through MRP Run

    Hi experts,
    After MRP Run in MD02 i had find out the list of Purchase requisition at ME5A , based on the purchase requisition no i will create scheduling agreement  not for PO, so how it is possible for the list of open scheduling agreement list  through MRP Run Only?
    Kindly elaborate the screen short steps at MDBT - MRP Run in background process what are possibilities >  weekly once or daily basis, report run repeated purchase requisition  no or not , update the daily stock status all those things ?
           what are the possibles in MDBT MRP Run > Maintain conditions,type of generate reports, open reports through t.code and report converted   excel or through mail recording MRP  run?
    Thanks,
    Umapathy

    Hi,
    In MDBT we can create the variant and Schedule as you wish  and execute .and also you can have the status of the schedule whether it is in cancelled or finished .
    Reg
    MSP

  • Order of delivery schedule line counter at schedule agreements from MRP run

    Currently we are using schedule agreements for our long term external suppliers, but we are facing a problem with the order of new delivery schedule lines created during MRP run.
    Because of master data settings like, lot size, rounding value, plan delivery time and planning time fence to set as firm new requirements, multiple schedule lines are created with no order for schedule line counter.
    Does anyone is aware of a BADI, user exit or customizing control to have this schedule line counter in order?
    Thank you
    Daniel Guillen
    IT
    Skyworks Inc.

    Hi,
    Pls put this query in SD fourms  and get immly help because this is technical fourms.
    Anil

  • Effect of manually created proposal on MRP Run

    if there is any proposal which might have been created by the user manually & not via MRP run, does it have effect on the results of MRP.
    will the system ignores the requirement as it has been covered already via manually created proposal.

    Dear Geetika,
    if there is any proposal which might have been created by the user manually & not via MRP run,
    does it have effect on the results of MRP.
    Yes definitely it have effect on MRP
    MRP checks All Firmed Receipts & creates procurement proposals
    will the system ignores the requirement as it has been covered already via manually created proposal.
    Say for example demand is there for material as 50 PCS
    Now manually user created Production order for that 50 pcs
    Now if run MRP than system will not create any plan order as already Production order consists for 50 pcs
    Again we have add demand for the same as for another 50 pcs
    so now total demand became for that material is 100pcs
    Now Run MRP system will create plan order for 50 pcs
    As we have already 50 pcs of production order which is created manually
    Hope the above clarifies
    Regards
    Madhu

  • Purchase order status in MRP run

    Hi Gurus,
    I have a doubt in MRP run.
    While doing the MRP run, can there be any open PO s or is it mandatory to close them.
    Can you also please suggest me on how to run the MRP.

    Hi,
    MRP Run
    Purpose
    The Material Requirements Planning (MRP) function enables you to plan material requirements for complex manufacturing processes. You use the MRP Wizard to create and run MRP scenarios. The MRP Wizard generates recommendations for the production and purchasing orders required to produce the final product on time and in the required quantity. You then use these recommendations to create production and purchase orders in the Order Recommendation Report.
    The order recommendation cannot be issued for requirements that happened in the past (before the present day). Since the purchasing or production process cannot be completed in time, the MRP does not mix the real past data with new recommendations for the same period.
    Prerequisites
    ●     You have defined the
    ○     Planning system
    ○     Procurement method
    ○     Order mutliple
    ○     Minimum order
    ○     Lead time
    See also: Item Master Data, Planning Data Tab.
    ●     You have set the time interval between orders. See also: Define Inventory Cycles.
    ●     You have defined the appropriate items as non-production bills of materials (if required). See  also: Item Master Data, General Tab.
    ●     You have defined default warehouses. See also: Define Warehouses.
    ●     You have defined forecasts. See also: Forecasts.
    ●     You have selected the Consume Forecast option to make the system exclude existing sales orders from the forecast. If this is not selected, the forecast considers existing sales orders as an additional requirement. See also: Sales Order.
    ●     You have set the planning definitions. If you chose Consume Forecast, you have defined the consumption method, days forward and days backward. See also: General Settings, Inventory Tab.
    Process Flow
           1.      Start the MRP Wizard.
           2.      Create a new MRP scenario or select an existing one. (See also: MRP Wizard: Select New or Existing Scenario.)
           3.      Define the parameters for your scenario, such as the planning horizon and item details.
    You also choose your display preferences. (See also: MRP Wizard: Scenario Details.)
           4.      Define the data sources for requirements that you want to include in your MRP scenario.
    For example, you define whether you want to consider the existing stock or the minimum stock level. You can also include a predefined forecast. (See also: MRP Wizard: Data Source.)
           5.      Save the scenario or run it.
    After you run the scenario, the system displays the MRP Results.
    If there are red figures in the result table, solve the problem and re-run the MRP.
           6.      Analyze the MRP results. You can display the final stock quantity before the MRP run or after it.
           7.      Save the recommendations and exit the MRP Wizard.
    Result
    After completing the MRP Wizard, you still need to create the purchase and production orders in accordance with the MRP recommendations. See also: Order Recommendation Report.
    Hope this will help.
    Reward Point if helpful
    Thanks,
    Raja

  • Is there a report to track the exception messages after a MRP run ?

    We have a scenario at our client site where MRP run is not optimized to the fullest.
    The planners are not trained on how to interpret those exception messages.
    They are not trained on how to reschedule / expedite planned orders resulting from an MRP run.
    Is there a report out in SAP that keeps track of
    1) History of number of exception messages by type ( Expedite/Reschedule/Cancel)
    2) History of number of exception messages that were acted on or ignored by the planner.
    This is to create metrics on the usage of MRP exception reports by planners.
    Appreciate your inputs..

    Hi
    The exception messages are dynamic and time dependant. You cannot have history of exception message.. If your user is feeling difficult to use standard MRP reports. Create a new report using a function module MD_STOCK_REQUIREMENTS_LIST_API
    It gives all MRP data including exception messages.
    Regards
    Antony

  • When MRP run through background process in MDBT open PR and PO not comming?

    Hi,
    When MRP run through backgroung process in MDBT open PR and PO not coming in MDBT result.
    Pls advise accordingaly.
    Regards
    rk

    Ram,
    Either I am totally misunderstanding your statements, or your business people are misinformed.  
    The output of MD01 (MRP total run in foreground) and the output of MDBT (MRP total Run in Background) ARE IDENTICAL, provided you have selected the same parameters.  
    Neither output contains a discrete listing of open Purchase orders and Purchase requisitions.
    Standard output of both MD01 and MDBT are:
    1.  List of materials processed, with exception messages
    2.  Statistics
    In addition, both of these programs also write MRP records to the MRP databases, provided that the "Display Material List" parameter is set.  In this case, both of these programs will produce data that can be further reviewed and managed in MD05 and MD06. MD06 is the tool that most planners use to process the MRP database info.
    If you wish to see a listing of the entire MRP results (either MD01 or MDBT), then execute transaction MDLD.  This will produce either a spoolfile or a printed document.
    For the PO or PR listings, review my earlier suggestions.
    Rgds,
    DB49

  • Open Purchase Orders not considered as requirement for MRP Run

    Hi ,
    We are facing a issue of Open Purchase orders not appeared in Stock requirements list and also it is not considered as requirement for MRP Run against reservation.
    As aresult for a reservation demand of 10 units we are ending with Open POs 10 units and a additional planned order 10 units.
    Material Type : ERSA
    MRP Type : PD (or VB)
    Lot size : EX (  HB if MRP Type is VB)
    Could you please throw some light to correct our settings to MRP to consider Open POs?
    Saravanan

    Can you check to see if there is a re-order point set up for this materia? That could be causing the problem too.

  • Open order quantity for mrp run

    hi
    for x material i was made a subcontracting PO
    ORDER uantity was say 2000
    deliverd quantity was 1500
    rest of the 500 nos tobe deliverad on 30th agust
    ie, OPEN ORDER QATNTIY OF 500 NOS WHITH delivery date
    on 30th agust.
    for the same materail there was an dependent requirement of say 1500 in the month of MAY2008
    while MRP RUN for the dependent  reqirement of 1500
    i got a purchase requistion of 1000nos
    and for  the 500 nos saytem taken fron the purchase order
    which was made as subcontracting
    and throughs an expetion message which says  needs the rescheduling
    my requirement here is it should not consider the open order quantity which was there for sub contracting
    it sholud create purchase requirement of 2000nos
    plz suggest how to achive it
    regards
    sasikanth/vst

    I wanted to the same as you where getting in subcontract po but in a std po
    hi
    for x material i was made a subcontracting PO
    ORDER uantity was say 2000
    deliverd quantity was 1500
    rest of the 500 nos tobe deliverad on 30th agust
    ie, OPEN ORDER QATNTIY OF 500 NOS WHITH delivery date
    on 30th agust."
    guide me in terms of configuration
    i think i am missing some configurations

  • Sale Order MRP Run for All Order Line Items

    Greetings...
                     I have One Sales Order , in which i have ten different Line Items .
    Now I have to Run the MRP on basis of Created sales Order so that all Line items wi get consider insingle MRP Run on sales order base MRP Run.
    How to take MRP Run of One Sale Order for all Line Items.???
    In MD50 , we can have sales Order with Item..

    In MD50 you can give only one item at a time.
    Its a standard transaction meant to accomodate changes relevant for MRP after plant level MRP run  related to specific sales order Item.
    so either you need to do it multipal times by changing material or you need to go for MD02.
    Please explain bussiness case in detail why you want to restrict your MRP run for items in a specific sales order.
    Regards