MRP running problem

Hi gurus,
When i try to run the total MRP in MD01, i can see that only certain material is being run, and most of it are not run.
So, when i go to MD05 to view the MRP list, i can see that the material is still in old date MRP run date where the stock qty is wrong.
I tried to go to MD02 to run that particular material, then that material is updated accordingly.
Any one has any idea what had happen?
Why when I run in Md01 some material is not picking to be run?
Thanks!

I've check in MR21, i found that planning file entry is there. But i can see some of the material that is not run do not have NETCH set.
How do i make the material as NETCH set so that when i run the MRP in MD01 it can run it as well?
Infact i try to create the planning file thru MD20 the entry is created but most of are not set as NETCH, why it can happen in such a way? (My processing key is NETCH when run MD01)
Does it mean all the materials must have set as NETCH then only it can run the MRP?
But i found some of the material do not have the NETCH set but when i try the total MRP run in MD01 it still can works?
What is the reason behind?
Please help, thanks!

Similar Messages

  • MRP run problem

    Hi experts,
    During MRP run for a material , open PO quantity is not considered If delivery date mentioned in that open PO exceeds 110 days from planning date(MRP run date). If it is less , it considers open PO quantity.
    MRP type = V1 (Reorder point planning)
    Lot size = HB
    planned delivery time = 0 days
    What could be the reason for it? Pls help me out.
    Thanks in advance,
    Rgds,
    jay

    When u keep your planning horizon 100 and in MD02 if ur using NETCH planning then system will consider the planning in between 100 days only If your open PO in out of planning horizon then it will not consider for the same.
    If u want to do the same u have to go for increase ur planning horizon time in OPPQ.
    whatever u required.
    Kind Regards,
    Nilesh

  • MDBT : MRP RUN Problem

    I have one storeage locaion  for which i want to tun MRP run in backgruond .
    Now i have cerated MRP area (STORE) as stoarge location asssigne th erespective storge location there.
    Now i created  scop of planning & i assigne tthat MRP area as "STORE"to scope of planning.
    Now cerated varaint as "CONSUMPTION"and in scope of plalning i selcetd the scope of planing as my MRP area  and saved the variant .
    Now all material under this area are cinsumption baed material means everyone has MRP type as VB, reordre point and lot siza as HB, max lot qty  and STORE as MRP area in material master.
    NOw in MDBT i selcted the variant and click on start inmmediate i m getting mesage as "Request with variant CONSUMPTION Started"
    If i see MD04 til no requirenment is genrtaed with this Run ??
    1. Please tel ..where i ned to corect
    2. Is there any mesage after background MRP executed ;like in MD02 planning result screen .

    Dear,
    Please check whether planning file entry exists in MD21 also check MDAB & MDRE ?
    or run program RMMRP000.
    Please note With MRP type VB (Manual Reorder Point Planing) system will not consider Dependent requirement or any other reservation.
    It will take care about only Reorder point.
    If You have set reorder point of 100 Nos.
    And dependent requirement is of 35 Nos , and available stock is 90 Nos. then at the time of MRP run system will generate PR of 10 Nos only just to cover that less qty than the reorder point of 100 Nos.So there is nothing wrong in your case.
    If you want to concider Dependent requirement also during Planing run then you have to change MRP type VB to PD then check.
    Regards,
    R.brahmankar

  • MRP Run Problem With Shipment Notification

    Hi Experts,
    Issue
    In MD04 i have 1 shipment Notification,but after MRP Run it should get display in MD05 but in my case it is not happening.CAn anybody tell me the possible causes / reasons why this is happeinig.
    Awiitng for your quick response
    Need any furher inputs please revert back to me immediately.
    Cheers,
    Kumar.S

    Hi karthik,
    Thanks for your reply,even i know Md04 is Dynamic and MD05 is static,also i cant able to clearly understtood what u r telling,
    Kindly check whether shipment notification is updated during the 2nd run then it wont reflect in MD05
    but when i check the same scenario in Q shipment notification getiing updated but not in prdn.
    Pls clarify
    Cheers,
    Kumar.S

  • MRP run problem in TCode-MD01

    hi experts,
    There were some MRP controllers were assigned for User exit in SPRO for planning run (T code :- MD01 ). Now i have defined additional MRP controllers and also assigned them for user exit (in SPRO) for planning run.
    With old MRP controllers defined as user exits , Planning run is considering materials with only particular MRP controller.
    But for these newly defined MRP controllers , user exit is not restricting planning of materials with only particular MRP controller and materials planning is carried out for all materials with newly defined MRP controllers.
    please help me out
    thanks in advance
    rgds.
    jai

    The name of the extension where you can find the user exit is M61X0001
    You have to read the code to find out why it is not working for the new controllers.
    Probably the code is not that dynamic as you thought and the controllers are hardcoded ...

  • MRP Run Problem through MDBT

    Hi,
    We are running the MRP based on MRP controller through Transaction MDBT.
    As per SAP threads, We insert the User Exit Key as CB1 & User exit parameters as MRP Controller and click on start immediately.
    After result come, we see the output from SP02 transaction.
    There all the materials showing with 8 number exception (Terminations), means all the material's having the Deletion Indicator when i am seeing in MARC table against that MRP Controller - CB1.
    Please tell me how only deletion material's showing. How other material's will display, which display in MARC table except Deletion Indicator.
    Plz guide...

    Hi Kundan,
    STAD to trace combination of User and Tcode, but particular material its diffcult to trace in std sap.
    If you want to trace then you need do some enhancements, create customized table (mateial number, plant, date, time, etc) for when user run the mrp in MD02 then save all data's to your own table.
    I hope this will help to you
    Regards,
    Sankaran

  • Problem with Back ground MRP Run (MDBT) or MD01

    Hello SAP Experts,
    Issue :- Material is not considering during Automatic back ground MRP run ( MDBT or MD01)
    But when we run MRP in forground (MD02) system is considering the material.
    we have checked both the selection parameter are same for MD01 and MD02 .
    can you help us on this issue ?
    Regards
    Mahesh

    Hi,
    Problem is due to entry in Planing File is missing for that Material.
    Go to MD21 and check whether Planing File entry is maintain for that Materiel.
    If not then maintain it by T.code MD20 (Manual) or you can do it by using back Ground JOB - OMDU.
    Regards,
    Dhaval

  • Problem with MRP running

    Hello Gurus,
    i have a problem with my product. lets take an example. my semifinished product abc is made up of a, b and c.
    i have made them(abc, a, b and c) to use MRP type VB. i made palnning file entry and BOM and then i run the MRP.
    I run single item multilevel MRP for semi-finished product abc, it showed me result in MRP running only for abc but not for a, b and c.
    can u please tell me where i am making any mistake.
    regards

    Hi Maggi,
    If you have used mrp run for single item,single level  planning (ie) md03, it will plan only for that particular material & will not plan for the dependent material in the BOM.
    If you run with t.code md02, MRP run for single item,multi level, all the dependent requirements will be planned.
    Also VB is for reorder point planning. ie if you maint reorder level as 100 for a,b & c materials & if the stock goes below 100, say  50 Nos. for all the three material. Then procurement proposal(Pur req) will be created for 50 nos for all the material(a,b,c).
    If you use MRP type PD, there is no question of reorder level, during mrp run system check the stock of the dependent requirements. If there is a shortage procurement proposal are created.
    Regards,
    Senthilkumar SD

  • Problem during MRP RUN.

    HELLO, FRIENDS,
    if i select mixed MRP in the material master with indicator 2 i.e.gross reqirement
    for MRP run ,but after taking MRP run through md01 .its not exploding dependent requirement of its component.Is there any setting for this?
    lpease give solution
    regards,]mangesh

    Hi,
    Check with t.code CS11 & check the result whether BOM is exploding or not.
    Then check in t.code OS23, whether mrp exlosion is activated or not.
    Check the BOM usage used while creating the BOM.
    Regards,
    Senthilkumar

  • Alternative BOM problem in MRP run

    Hello Experts,
    We have two BOM for one material.Now I want to use BOM-1 for MRP run & BOM-2 for subcontracting.I have maintined following settings.
    1) Production version.
    2) BOM explosion selection method in MRP4 -2
    3) Assign PV in inforecord for subcontracting.
    4) Assign PV in MD61 in schedule line .
    But when I run MRP it still consider subcontracting BOM.Have I missed any setting?
    Kindly guide.Thanks you.

    Hi, Follow the below process,
    1.Enter the BOM selection method as 2 in the MRP4 view of the material master.
    2.In case if you have not assigned the production version in MD61 against the PIR's under schedule line
    tab key (in the top menu click on settings and prod version ,then you can assign the prod version which
    you need to pick during the MRP run),the system always picksup the first production version during
    MRP run even if all the prod versions contains the same validity dates and lot sizes.
    3.If you are not willing to assign the prod version in MD61 ,but the system should consider the second
    prod version for MRP run means,then set the locked status for the first prod.version.
    4.When run MRP via MD02 or MD50 in the simulation mode.(i.e w/o giving tick in simulation mode).
    Click on Save,You will get a pop screen,
    Now click on the continue icon, Then go to Plaining Results: Individual lines screen.where you will get Plan order on which when double click you will get pop screen below,where you have Planned order no,quantity,plant,storage location,and version.
    Now here you can select the required version,and it will become firmed. This BOM will be used in the order now. Try it.

  • Dates problem in MRP Run

    Hello
    i m running mrp using zpp_md50 is the zprogramme for running the mrp for all the line items in one sales order,  after running the MRP, whatever the pur. req. generated we will convert it to PO, but client need one release statergy here so that  they can take the assurance from the suppling plant that whatever the date mrp run showing is that plant is really able to supply the goods on that date or not.
    1) if suppling plant is not able to send the goods on the requested date in that case receving plant should be able do the amendment (change) in dates in their panning so that they can give the new delivery date to the customer?how to achive this?
    2) They also want when we run the MRP, system has to consider the unrestricted stock present for the sales order line item,but without giving the sales order ref. using 412e to sales order.cause their r huge no of line item in sales order.
    3) my client is not able to achive the customer date so it is very imp to do the amendment in mrp dates cause the dependacy is on the supplying plant & the suppling plant can produse only taking  material grades of the same item at a time & it is not possible for suppling plant to produce as per the delivery date of the order.so  the date in master ie. in house production date maintain is not really going to be follow, as the plant is critical, plz suggest some solutions for this also?
    Regards
    Nishj.

    Nishj,
    Wow.  Substantial requirements.  Let me see how many of these I can help you with.
    i m running mrp using zpp_md50
    Please understand that that program is custom to your system.   It will be hard for us to comment on it's workings.
    they can take the assurance from the suppling plant
    It seems that you are selling the product from one plant but manufacturing in another
    if suppling plant is not able to send the goods on the requested date in that case receving plant should be able do the amendment (change) in dates in their panning so that they can give the new delivery date to the customer?
    This is standard in SAP.  Basically, the suppying plant will create a supply element (production order, process order, perhaps in conjunction with a Stock Transport order) to move the parts to the selling plant.  Once this element is in place, someone from Sales or another appropriate functional group will re-ATP the sales order.  The sales order will then re-confirm against the new, more accurate dates.
    They also want when we run the MRP, system has to consider the unrestricted stock present for the sales order line item,but without giving the sales order ref.
    This can be achieved easily, by not using a MTO strategy.  If you use strategy 40, Sales orders ATP, and all MRP calculations, will make use of all unrestricted stock.  If there then is NO sales order stock, then this means that ALL stock is included.  Just avoid any MTO strategies throughout your BOM.
    There is no standard SAP functionality that will include Sales order stock and unrestricted stock simultaneously for the same part for the same requirement.
    my client is not able to achive the customer date so it is very imp to do the amendment in mrp dates....
    I am not sure what you are asking for here.  You have stated the solution:  The supplying plant does their research, and they then create a supply element with the realistic dates.  The Sales order ATP check will then re-confirm to those dates.  MRP will also run using those modified dates.
    Rgds,
    DB49

  • Order of delivery schedule line counter at schedule agreements from MRP run

    Currently we are using schedule agreements for our long term external suppliers, but we are facing a problem with the order of new delivery schedule lines created during MRP run.
    Because of master data settings like, lot size, rounding value, plan delivery time and planning time fence to set as firm new requirements, multiple schedule lines are created with no order for schedule line counter.
    Does anyone is aware of a BADI, user exit or customizing control to have this schedule line counter in order?
    Thank you
    Daniel Guillen
    IT
    Skyworks Inc.

    Hi,
    Pls put this query in SD fourms  and get immly help because this is technical fourms.
    Anil

  • Purchase order status in MRP run

    Hi Gurus,
    I have a doubt in MRP run.
    While doing the MRP run, can there be any open PO s or is it mandatory to close them.
    Can you also please suggest me on how to run the MRP.

    Hi,
    MRP Run
    Purpose
    The Material Requirements Planning (MRP) function enables you to plan material requirements for complex manufacturing processes. You use the MRP Wizard to create and run MRP scenarios. The MRP Wizard generates recommendations for the production and purchasing orders required to produce the final product on time and in the required quantity. You then use these recommendations to create production and purchase orders in the Order Recommendation Report.
    The order recommendation cannot be issued for requirements that happened in the past (before the present day). Since the purchasing or production process cannot be completed in time, the MRP does not mix the real past data with new recommendations for the same period.
    Prerequisites
    ●     You have defined the
    ○     Planning system
    ○     Procurement method
    ○     Order mutliple
    ○     Minimum order
    ○     Lead time
    See also: Item Master Data, Planning Data Tab.
    ●     You have set the time interval between orders. See also: Define Inventory Cycles.
    ●     You have defined the appropriate items as non-production bills of materials (if required). See  also: Item Master Data, General Tab.
    ●     You have defined default warehouses. See also: Define Warehouses.
    ●     You have defined forecasts. See also: Forecasts.
    ●     You have selected the Consume Forecast option to make the system exclude existing sales orders from the forecast. If this is not selected, the forecast considers existing sales orders as an additional requirement. See also: Sales Order.
    ●     You have set the planning definitions. If you chose Consume Forecast, you have defined the consumption method, days forward and days backward. See also: General Settings, Inventory Tab.
    Process Flow
           1.      Start the MRP Wizard.
           2.      Create a new MRP scenario or select an existing one. (See also: MRP Wizard: Select New or Existing Scenario.)
           3.      Define the parameters for your scenario, such as the planning horizon and item details.
    You also choose your display preferences. (See also: MRP Wizard: Scenario Details.)
           4.      Define the data sources for requirements that you want to include in your MRP scenario.
    For example, you define whether you want to consider the existing stock or the minimum stock level. You can also include a predefined forecast. (See also: MRP Wizard: Data Source.)
           5.      Save the scenario or run it.
    After you run the scenario, the system displays the MRP Results.
    If there are red figures in the result table, solve the problem and re-run the MRP.
           6.      Analyze the MRP results. You can display the final stock quantity before the MRP run or after it.
           7.      Save the recommendations and exit the MRP Wizard.
    Result
    After completing the MRP Wizard, you still need to create the purchase and production orders in accordance with the MRP recommendations. See also: Order Recommendation Report.
    Hope this will help.
    Reward Point if helpful
    Thanks,
    Raja

  • Open Purchase Orders not considered as requirement for MRP Run

    Hi ,
    We are facing a issue of Open Purchase orders not appeared in Stock requirements list and also it is not considered as requirement for MRP Run against reservation.
    As aresult for a reservation demand of 10 units we are ending with Open POs 10 units and a additional planned order 10 units.
    Material Type : ERSA
    MRP Type : PD (or VB)
    Lot size : EX (  HB if MRP Type is VB)
    Could you please throw some light to correct our settings to MRP to consider Open POs?
    Saravanan

    Can you check to see if there is a re-order point set up for this materia? That could be causing the problem too.

  • MRP Run error " Schedule Lines not generating properly"

    Hi Folks,
    I am facing a typical issue with MRP Run.
    Every time when I am running the MRP for a particular material I have made settings such that Schedule lines to be generated by maintaining the Source list and MRP relevancy as 2 in source list. Also I have fixed the vendor. Now my problem is I am getting Schedule lines for first run and Combination of Purchase requests and Schedule lines or only PRs for the next MRP run.. This is keep on repeating in such as way that the planning is shifting as said above for subsequent MRP Run.
    Note that the initial settings during MD02 remain same for all run.
    I want only schedule lines to be generated but not PR.
    Pls advise and provide input where the wrong might be.
    Quick responce would be appreciated.
    Regards
    Shash

    Dear shash,
    Check with What are the MRP control Parameters values which you are using for the MRP run.
    In MD02, For Deleivery schedules run with value 3 - That's -  Schedule lines.
    The other options are     1  No schedule lines
                                       2  Schedule lines in the opening period.
    check with this & revert back.
    Regards
    Mangalraj.S

Maybe you are looking for

  • How can I tell if a String is a double?

    How can I tell if a certain String represents a double value? I'm sure it's something very simple, but I can't find it... for example, String s = "45.432"...

  • When is new Air coming out?

    should I wait to buy a MAcbook Air until a new Air is released?

  • SAP users identification - rename SAP Ids

    Dear all, We have a project to change the codification of our SAP users. We will use the AD ids as SAP users instead of the current codification. We will copy the current user to a new one and close the current. After this operation, all the users wi

  • Web Application Crashes (PB 11.5 Build 3127)

    Hi Everyone, First of all, I am newbie when it comes to using PB 11.5 (so please bear with me).  I would like to ask for help regarding my issue. IE browser crashes with a message like this "Unexpected error was thrown, the browser will be closed! Pl

  • Trying to transfer from time machine backup

    I had a new hard drive installed on my system. When I booted up for the first time, it asked me if I wanted to transfer information from a source and I selected Time Machine. It then calculated the amount of information and after that was complete I